Sub topic 3
Gathering stakeholder requirements
This chapter assumes you know how projects are organized, can recognize roles such as sponsor, project manager, and team member, and have worked with customers or stakeholders on a deliverable. It follows the chapter on objectives and success criteria. It comes before the chapter on deliverables. The goal here is to collect what stakeholders need and turn it into requirements that a team can build and test.
Why requirements sit between objectives and deliverables
An objective says why the project exists. A deliverable says what the project hands over. Requirements connect the two. They describe what the people affected by the project need the result to do or be.
Take the objective from the running example: reduce support tickets about account access by 20% within 6 months of launch. That objective does not tell a developer what to build. Talking to support agents, customers, and the security team does. From those conversations you learn that customers get locked out, that agents spend time resetting passwords by hand, and that security requires reset links to expire. Those findings become requirements. The requirements then shape the deliverables, such as a self-service password reset.
The decision step in the diagram is where scope gets set. Not every requirement a stakeholder states belongs in the project. Gathering is about learning what people want. Deciding is a separate step, and mixing the two causes most early scope problems.
Identify the stakeholders first
A stakeholder is anyone who is affected by the project or can affect its outcome. You cannot gather requirements from people you have not identified, so start with a list.
For the portal project, a first pass might include:
- The sponsor, who funds the project and owns the objective.
- Customers, who use the portal.
- Support agents, who handle the account access tickets today.
- The security team, who set rules for credentials and email links.
- The identity service team, who own a system the project depends on.
- Marketing, who manage customer communication and may want features of their own.
Two groups are easy to miss. The first is people who operate or maintain the result, such as support and the identity service team. The second is people with authority over constraints, such as security, legal, and finance. If you skip them, their requirements arrive late, usually as a demand to change finished work.
A simple stakeholder register helps. For each person or group, record what they care about, how much influence they have, and how you will get input from them.
| Stakeholder | Main interest | Influence | How to gather input |
|---|---|---|---|
| Sponsor | Ticket reduction target | High | Interview |
| Support agents | Fewer manual resets | Medium | Workshop, ticket review |
| Customers | Quick, simple access recovery | Medium | Survey, usability test |
| Security team | Safe credential handling | High | Interview, policy review |
| Marketing lead | Customer-facing features | Medium | Interview |
Techniques for gathering requirements
No single technique finds everything. Choose a mix based on who the stakeholders are and how much is already known.
- Interviews. One-to-one conversations. They work well for senior stakeholders and for sensitive topics. Ask about problems and goals before solutions. "What happens when a customer forgets a password?" teaches more than "Do you want a reset button?"
- Workshops. A facilitated group session. They surface conflicts between stakeholders early, because the people who disagree are in the same room.
- Surveys. Written questions sent to many people. They suit large groups such as customers, but they only answer the questions you thought to ask.
- Observation. Watching people do the current work. Watching a support agent handle a lockout shows steps nobody would think to mention.
- Document and data review. Existing tickets, policies, contracts, and process documents. In the example, a review of last quarter's tickets might show that 60% of access tickets are password resets. That number is stronger evidence than anyone's opinion.
- Prototypes. A rough mock-up that stakeholders react to. People often cannot describe what they want but can say what is wrong with something in front of them.
Whatever the technique, record who said what and when. A requirement with no source cannot be questioned or confirmed later.
Writing a good requirement
Raw notes are not requirements. A requirement is a statement of a need that the result must meet. A usable one has these qualities:
- Necessary. It traces to an objective or a real stakeholder need.
- Clear. One reading only. Avoid words such as "fast", "easy", and "user-friendly" without a measure.
- Single. It states one need. If it contains "and", consider splitting it.
- Testable. Someone can check whether it was met.
- Solution-neutral where possible. It says what is needed, not how to build it, unless the design is itself a constraint.
Compare these:
| Weak | Better |
|---|---|
| The portal must be easy to use. | A first-time user can complete a password reset in under 3 minutes without contacting support. |
| Improve security. | Password reset links expire after 24 hours. |
| Support wants better tools. | Support agents can see whether a customer has requested a reset in the last 24 hours. |
The "better" versions are still requirements, not acceptance criteria. Acceptance criteria are covered in a later chapter. In practice they are closely related, and a well-written requirement is often close to a test.
Functional and non-functional requirements
Requirements fall into two broad kinds. Functional requirements describe behavior: what the result does. Non-functional requirements describe qualities: how well it does it, such as speed, availability, security, accessibility, and compliance. Teams often collect the first kind thoroughly and forget the second. The password reset example needs both. "A user can reset a password using a link sent to their registered email" is functional. "The reset link expires after 24 hours" is a security quality. "The reset page meets the organization's accessibility standard" is a compliance quality.
Record requirements so they can be traced
A requirements list is more useful when each item has an identifier, a source, a priority, and a link to the deliverable that will satisfy it. This is a traceability matrix in its simplest form. It lets you answer two questions later: "Why are we building this?" and "Is every requirement covered?"
A compact format works fine. Here is a requirements register for the portal project:
requirements:
- id: R1
statement: A user can reset a password using a link sent to their registered email
source: Support agents (ticket review)
objective: Reduce account access tickets by 20%
priority: must
deliverable: D1
status: accepted
- id: R2
statement: Reset links expire after 24 hours
source: Security team (policy review)
objective: Reduce account access tickets by 20%
priority: must
deliverable: D1
status: accepted
- id: R3
statement: Users can change name, email, and notification preferences
source: Customer survey
objective: Reduce account access tickets by 20%
priority: should
deliverable: D2
status: accepted
- id: R4
statement: Customers can sign in with their company identity provider
source: Marketing lead (interview)
objective: none identified
priority: could
deliverable: none
status: deferredNotice R4. It came from a real stakeholder, but it does not trace to the objective, and it maps to no deliverable. That is a signal. It either needs a clear link to the objective, or it should be recorded as out of scope. In the scope statement from the overview, single sign-on appears under exclusions. The register explains why: it was asked for, considered, and set aside on purpose.
The priority labels used here (must, should, could) are one common scheme. Use whatever your organization uses, but define it. "High priority" means different things to different people.
Resolve conflicts and gaps
Stakeholders will disagree. Support wants the reset to require as little as possible. Security wants extra verification. Neither is wrong, and the project manager should not pick a winner silently.
A reasonable approach:
- Write both requirements down with their sources.
- Test each against the objective and constraints.
- Bring the stakeholders together, or take the question to the sponsor if they cannot agree.
- Record the decision and the reason.
Gaps are quieter than conflicts. Ask each stakeholder, "Who else should I talk to?" and "What would make you reject the result?" The second question often exposes unstated requirements. Also check each requirement against the objective in reverse: if every requirement were met, would the objective be reached? If not, something is missing.
Common errors
- Taking requests as requirements. "Add a chat widget" is a proposed solution. Ask what problem it solves, then write the need.
- Treating the loudest or most senior voice as the full picture. Customers and operators have requirements that executives do not see.
- Gathering once and never again. Requirements shift as people see progress. Plan checkpoints, and route changes through the change control process described in a later chapter.
- No source or owner. Without these, no one can confirm a requirement is still wanted.
- Mixing needs with scope decisions. Writing "won't do" during an interview closes off discussion. Collect first, then decide with the sponsor.
- Skipping non-functional needs. These often decide whether the result is accepted.
Confirm the requirements
Before you move to defining deliverables, send the register back to the stakeholders. Ask each one to confirm the items that came from them and to flag anything wrong or missing. The sponsor approves the final set of accepted items. This step is short, but it gives you a shared record to point to when a later request begins with "I thought that was included."
Exercise
A stakeholder in a workshop says, "The portal should have a live chat button so customers get help faster." The objective is to reduce account access tickets by 20%. List the steps you would take before deciding whether this belongs in scope, and rewrite the statement as a requirement.
Show answer
First, treat the chat button as a proposed solution and ask what problem it solves. Probably customers who are locked out cannot reach help quickly. Second, check the ticket data to see whether that problem causes many access tickets. Third, compare the need against the objective and constraints, and record the source (the workshop stakeholder). A requirement could read: "A customer who cannot sign in can get help or recover access without waiting for a support agent." This need is already met in part by the self-service password reset deliverable. The chat button itself should be recorded as a request and either deferred or excluded unless the sponsor decides it adds value beyond the reset flow. Record the decision and the reason in the requirements register.
Exercise
In the requirements register above, why is R4 marked "deferred" instead of being added to deliverable D1?
Show answer
R4 (sign-in with a company identity provider) does not trace to the project objective, and no deliverable covers it. Adding it to D1 would expand the work without a decision from the sponsor. Recording it as deferred, and listing single sign-on under exclusions, keeps the scope clear and gives the requester a documented place to raise a change request if they still want it.