Sub topic 2
Starting from Objectives and Success Criteria
This chapter assumes you know how projects are organized, can name the common roles (sponsor, project manager, team member), and have worked with a stakeholder or customer on a deliverable. It covers the second step in the scope sequence. The previous chapter set the boundary between what a project does and does not do. This chapter explains where that boundary should come from: the project's objectives.
Why scope starts with objectives
A scope is a list of things the team will deliver. A list of deliverables with no reason behind it is hard to defend, hard to trim, and hard to judge. If someone asks "should we add this?", you need something to compare the request against. That something is the objective.
An objective is the business result the project exists to produce. A deliverable is a thing the team hands over. The objective explains why the deliverable is wanted. If you reverse the order and start from deliverables ("we need a new settings page"), you can finish the page and still miss the business problem.
In the Topic Spine's running example, the objective is: Reduce support tickets about account access by 20% within 6 months of launch. The deliverables (a self-service password reset and an updated account settings page) exist because the team believes they will reduce those tickets. If that belief is wrong, the objective tells you the project has failed even though both deliverables shipped.
The concept graph for this topic shows the dependency: objectives and requirements both feed deliverables. Scope is derived from objectives, not the other way round.
What makes an objective usable
Many objectives are written as slogans: "Improve the customer experience", "Modernize the portal", "Be more efficient". These cannot guide scope, because almost any piece of work can be argued to support them. A usable objective has four properties.
- Specific. It names the thing that changes. "Support tickets about account access" is specific. "Support load" is not.
- Measurable. It has a number or an observable state. "20%" can be checked. "Fewer" cannot.
- Time-bound. It says when the result is judged. "Within 6 months of launch" fixes the date of judgment.
- Tied to the business. It states a result the organization cares about, not an activity the team performs.
You may know this as the SMART pattern (specific, measurable, achievable, relevant, time-bound). The pattern is a checklist, not a guarantee. An objective can pass every letter and still be the wrong objective, so also confirm with the sponsor that it is the result they want.
Objectives versus outputs
The most common error at this stage is writing an output as an objective. An output is something the project produces. An outcome is a change in the world that results from it.
| Statement | Type | Problem |
|---|---|---|
| Build a self-service password reset | Output | Says what to build, not why |
| Launch the new portal by June | Output with a date | Success means "it exists" |
| Reduce account-access tickets by 20% within 6 months of launch | Outcome | None. It can be measured and it justifies the work |
Outputs are not wrong. They belong in the deliverables section. The mistake is stopping at them. When an objective is only an output, nobody can say whether the project worked, and scope debates have no anchor.
Success criteria
Success criteria are the conditions that must be true for the sponsor to call the project successful. The objective states the intent. The success criteria turn it into tests.
Often one objective needs several criteria, because one number rarely captures success. For the portal example:
- Support tickets tagged "account access" fall by at least 20% compared with the 6 months before launch.
- The password reset is used successfully by at least 70% of users who start it.
- The project is delivered before the end of the fiscal year.
- No increase in security incidents related to account takeover.
The last criterion is a guard against unwanted side effects. A password reset that cuts tickets but weakens account security would hit criterion 1 and still harm the business. Good criteria include at least one condition of this kind.
Project success versus product success
The two are different, and the difference affects scope.
- Project success concerns the delivery: scope, schedule, cost, quality. It can be judged when the project closes.
- Product success concerns the result in use: tickets reduced, revenue gained. It is often judged months after the team has disbanded.
The example objective is a product-success measure ("within 6 months of launch"). Your project closes long before that date. This creates a practical problem. Someone must own the measurement after closure, usually the sponsor or a business owner, and the scope statement should say so. If no one owns it, the objective becomes unverifiable and the project is judged on delivery alone.
A sound approach is to record both kinds of criteria and label them.
success_criteria:
project: # judged at project close
- id: SC1
statement: Deliverables D1 and D2 accepted by the sponsor
- id: SC2
statement: Launch occurs before the end of the fiscal year
product: # judged after launch by a named owner
- id: SC3
statement: Account-access tickets fall by at least 20% versus the prior 6 months
measured_by: Support operations manager
measured_on: 6 months after launch
- id: SC4
statement: At least 70% of started password resets complete successfully
measured_by: Product owner
measured_on: 3 months after launchThis block is not part of the Topic Spine's scope statement. It is a working note you keep while building toward it. Each criterion has an identifier, so deliverables and later acceptance criteria can point back to it.
Getting from a business need to an objective
Objectives rarely arrive in clean form. A sponsor usually brings a need, a complaint, or a proposed solution. Your job is to move from that starting point to a measurable objective without losing what the sponsor means.
- Ask what problem is being solved. If the sponsor says "we need single sign-on", ask what happens today that SSO would fix. The answer may be "people forget passwords and call support." That is the real need, and SSO is one possible solution.
- Find the evidence. Look for a number: ticket counts, abandonment rates, cost per transaction. A baseline lets you set a target. Without a baseline, "reduce by 20%" has no meaning.
- Propose a target and a date. Targets are negotiated, not discovered. Use the baseline, known constraints, and comparable projects to suggest a figure, then agree on it with the sponsor.
- Name the measurer. State who will collect the data and where it comes from.
- Write it as one sentence. If the objective needs a paragraph, it probably contains several objectives. Split them.
Notice what step 1 does to the SSO request. It demotes a solution to a candidate deliverable. Later, when SSO is judged out of scope for this project, you can point to the objective and show that the password reset is expected to reach the target without it. That argument is far easier than a bare "SSO is not in the budget."
Handling more than one objective
Projects often have several objectives, and they can conflict. A sponsor may want to cut costs, launch quickly, and add features. These pull against each other.
- Limit objectives to what the project can reasonably achieve. Three to five is a common ceiling, and fewer is better.
- Rank them. When two conflict, the ranking decides which gives way.
- State which dimension is fixed and which can flex. For example: the date is fixed, scope can flex. This choice affects what you later cut when pressure arrives.
Common errors
These are the mistakes that most often damage scope later.
- Solution disguised as objective. "Implement SSO" is a solution. The objective sits behind it.
- No baseline. A percentage target without a starting figure cannot be verified.
- Unreachable by the project. If tickets depend on factors the team cannot influence (a product redesign owned by another group, for example), the objective is not fully within the project's control. Either narrow it or record the dependency as an assumption. The next chapters return to assumptions.
- Vanity measures. Page views, features shipped, and tasks completed are easy to count, and they rarely show a business result.
- Success criteria added afterward. Criteria invented after delivery tend to fit whatever was delivered. Agree on them before work starts, and keep them in writing.
- Unowned measurement. The criterion is clear but nobody collects the data.
Using objectives to test scope
Once objectives and success criteria are written, they become a filter. For any proposed deliverable or request, ask three questions.
- Which objective does it support?
- Which success criterion would it help meet?
- Is it needed to meet that criterion, or only useful?
A request that supports no objective is a candidate for the exclusions list. A request that supports an objective but is not needed to meet any criterion is a candidate for a later phase or a change request. A request that is needed for a criterion belongs in scope.
Apply this to the example. The marketing lead asks for single sign-on. It supports the objective loosely, because it may reduce access problems. But the password reset already targets the main cause of tickets, and the 20% target does not depend on SSO. So SSO is not needed, and it goes on the exclusions list. If the baseline data later showed that most access tickets came from users juggling several logins, the answer would change, and the change would go through change control, which is the topic of a later chapter.
The filter works only if the objective is measurable. With a slogan, every request passes.
Exercise
A sponsor says, "The objective of this project is to build a mobile app for field technicians." Rewrite it as a measurable objective, and name two pieces of information you must collect from the sponsor before you can finish the rewrite.
Show answer
The statement is an output, not an objective. Ask what problem the app solves, for example "technicians spend too long on paperwork." A rewrite could be: "Reduce the average time technicians spend on job paperwork from 40 to 20 minutes per job within 3 months of launch." Information needed: (1) the current baseline, such as the average paperwork time per job and how it is measured, and (2) the target and date the sponsor accepts, along with who will collect the measurements after launch. Other valid answers include the business reason for the target and the measurement source.
Exercise
A project's success criteria are: "Deliverables accepted by the sponsor" and "Account-access tickets fall by 20% within 6 months of launch." The project closes one month after launch. What problem does this create, and how do you fix it in the scope documentation?
Show answer
The ticket criterion is judged five months after the project closes, so the project team cannot verify it and no one may be responsible for checking it. Fix this by labeling it a product-success criterion, naming an owner (for example the support operations manager), stating the measurement date and data source, and keeping the delivery criterion as the project-success criterion judged at close.
Exercise
A stakeholder requests a loyalty-points feature for the portal. The project objective is to reduce account-access tickets by 20%. Using the three-question filter, what is the likely outcome, and where does the request go?
Show answer
The feature supports no stated objective and would help meet no success criterion, so it fails the first two questions. It is a candidate for the exclusions list. If the stakeholder still wants it, they submit a change request, and the change authority assesses its impact on schedule, cost, and risk.