Sub topic 8
The capital allocation process
Capital allocation is how a company decides which long-term projects get its money. This chapter assumes you know present value and discounting, can read the three financial statements, and understand that investors require a return for bearing risk. NPV and IRR get their own chapter next. Here the focus is the process around them and, above all, which cash flows belong in the analysis.
What capital allocation is
Capital budgeting is the process of identifying and evaluating projects whose cash flows extend beyond one year. Examples include a new plant, a product launch, an acquisition, or a software platform. These decisions matter for three reasons.
- They are hard to reverse, so mistakes are costly.
- They commit cash today for benefits that arrive later and are uncertain.
- They determine the firm's future cash flows, and therefore its value.
The process links to earlier material. Agency problems can distort it. Managers may favor empire building over value creation. Working capital and liquidity also constrain it, because a profitable project still fails if the firm cannot fund it.
The four steps
- Generate ideas. Ideas come from many places: employees, customers, regulators, competitors, or senior management.
- Analyze proposals. Forecast the incremental after-tax cash flows and apply a decision rule such as NPV or IRR.
- Plan the capital budget. Rank accepted projects, consider timing, and fit them to the funds available. Strategic fit and resource limits matter here.
- Monitor and conduct a post-audit. Compare actual results with forecasts, find the causes of any gap, and use what you learn to improve the next round of forecasts.
The post-audit has two uses. It improves forecasting, and it discourages managers from submitting inflated forecasts, since they know results will be checked.
Categories of projects
| Category | Purpose | Typical analysis |
|---|---|---|
| Replacement, maintenance | Keep existing operations running | Often simple. Cost savings are the main benefit. |
| Replacement, cost reduction | Swap old assets for more efficient ones | Detailed analysis of savings. |
| Expansion | Grow capacity or enter new markets | Detailed analysis of demand and margins. |
| New products or services | Create new revenue streams | Most uncertain and most detailed. |
| Regulatory, safety, environmental | Meet legal or other requirements | May be mandatory, so value may not decide it. |
| Other | Pet projects, hard-to-quantify items | Judgment and strategic review. |
Mandatory projects are usually accepted even when NPV is negative. The analysis then helps choose the cheapest way to comply.
Relationships among projects
- Independent projects can be judged on their own. Accepting one does not affect another.
- Mutually exclusive projects compete for the same role. You can choose only one, such as two machines for the same job.
- Project sequencing means later projects depend on earlier ones. A small pilot may come before a larger rollout.
- Unlimited funds means you accept every project with a positive NPV.
- Capital rationing means funds are limited. You then choose the combination of projects with the highest total NPV within the budget.
Under rationing, ranking by NPV alone can mislead. A large project with the highest NPV may use the whole budget, while two smaller projects together add more value. The profitability index, which is present value of future cash flows divided by the initial investment, helps compare projects per dollar invested.
Which cash flows belong in the analysis
Use these principles for forecasting.
- Incremental. Include only the cash flows that change because the project goes ahead. Compare the firm with the project against the firm without it.
- After-tax. Taxes are real cash outflows. Include the tax effect of depreciation, which is a non-cash expense that lowers taxes.
- Cash, not accounting profit. Depreciation reduces net income but is not a cash outflow. Add it back after calculating tax.
- Timing. Record each flow when it occurs, not when it is accrued.
Common items to handle:
- Sunk costs are already spent and cannot be recovered, such as earlier market research. Exclude them.
- Opportunity costs are the value of the best alternative use of a resource the project uses, such as a building the firm already owns that could be rented out. Include them.
- Externalities are effects on other parts of the firm. Cannibalization, where a new product takes sales from an existing one, is a negative externality and is included. A positive externality, such as a new product that lifts sales of a complementary one, is also included.
- Working capital changes are cash flows. An increase in receivables or inventory consumes cash at the start, and the firm typically recovers it at the end.
- Financing costs are excluded from cash flows. Interest and dividends are captured by the discount rate, usually the weighted average cost of capital (WACC). Subtracting interest from the cash flows as well would count the cost of financing twice.
- Salvage value. If an asset is sold for more than its book value, tax is due on the gain. If sold for less, the loss gives a tax saving.
A worked example in code
A firm considers a machine costing 500,000. It needs 50,000 of added working capital. The project lasts four years. Annual revenue is 400,000 and cash operating costs are 150,000. Depreciation is straight-line to zero over four years, so 125,000 per year. The tax rate is 30%. At the end of year 4, the machine sells for 40,000 and the working capital is recovered. The discount rate is 10%.
Annual operating cash flow is (revenue − cash costs − depreciation) × (1 − tax) + depreciation. That equals (400,000 − 150,000 − 125,000) × 0.70 + 125,000 = 212,500. The book value at the end is zero, so the sale produces a gain of 40,000, and tax on it is 12,000. After-tax salvage is 28,000. Year 4 also gets the 50,000 of recovered working capital.
def npv(rate, cash_flows):
# cash_flows[0] occurs today (time 0)
return sum(cf / (1 + rate) ** t for t, cf in enumerate(cash_flows))
cost, nwc = 500_000, 50_000
revenue, cash_costs = 400_000, 150_000
years, tax, rate = 4, 0.30, 0.10
salvage = 40_000
depreciation = cost / years
operating_cf = (revenue - cash_costs - depreciation) * (1 - tax) + depreciation
book_value_end = 0
after_tax_salvage = salvage - (salvage - book_value_end) * tax
cash_flows = [-(cost + nwc)]
cash_flows += [operating_cf] * (years - 1)
cash_flows.append(operating_cf + after_tax_salvage + nwc)
print(cash_flows)
print(round(npv(rate, cash_flows))) # about 176,871The NPV is positive, about 176,871, so the project adds value at a 10% required return. Notice that interest does not appear anywhere in the cash flows.
Common errors in practice
- Anchoring on accounting profit. Using net income instead of cash flow ignores the timing of depreciation and working capital.
- Forgetting working capital recovery. This understates later cash flows.
- Including allocated overhead. Overhead that does not change if the project proceeds is not incremental. Only extra overhead caused by the project counts.
- Ignoring inflation consistency. Nominal cash flows need a nominal discount rate. Real cash flows need a real rate.
- Biased forecasts. Managers who benefit from approval may overstate sales. Independent review and the post-audit reduce this.
Exercise
A firm spent 20,000 last year on a feasibility study for a new product. The product would cost 300,000 in new equipment, would reduce sales of an existing product by 15,000 per year after tax, and would be financed 40% with debt at 6%. Which of these items should be included in the project's incremental cash flows?
Show answer
Include the 300,000 equipment cost and the 15,000 annual loss from cannibalization, which is a negative externality. Exclude the 20,000 study, because it is a sunk cost. Exclude the debt financing and its 6% interest, because financing costs are reflected in the discount rate (WACC) and not in the cash flows.
Exercise
A project needs a 200,000 machine and a 30,000 increase in inventory. At the end of its life, the machine, which is fully depreciated, is sold for 25,000. The tax rate is 20% and the inventory is fully recovered. What is the final-year cash flow from salvage and working capital, excluding operating cash flow?
Show answer
The gain on sale is 25,000 − 0 = 25,000, so tax is 25,000 × 0.20 = 5,000 and after-tax salvage is 20,000. Adding the recovered working capital gives 20,000 + 30,000 = 50,000.