Sub topic 10
Payback and Discounted Payback
This chapter covers two simple capital budgeting screens: the payback period and the discounted payback period. It assumes you already know present value and discounting, and that you have seen NPV and IRR in the previous chapter. Payback measures how fast a project returns its cost. It does not measure how much value the project creates.
What payback measures
The payback period is the number of years needed for a project's cumulative cash flows to recover the initial investment. Managers use it as a rough measure of liquidity risk and of how long capital is exposed. A project that returns its cost in two years leaves less time for things to go wrong than one that takes seven.
The decision rule is to accept a project if its payback period is shorter than a maximum period the firm sets in advance. When ranking projects, a shorter payback is preferred.
Payback ignores two things:
- Cash flows after the payback point. A project can pay back quickly and then earn nothing, or pay back slowly and then earn a great deal.
- The time value of money, in the simple version. A dollar in year 1 counts the same as a dollar in year 4.
Calculating payback
Use the cumulative cash flow. Find the last year in which the cumulative total is still negative, then add the fraction of the next year needed to finish recovery.
The formula is:
Payback = (full years before recovery) + (unrecovered cost at start of the recovery year) / (cash flow during the recovery year)
The fractional part assumes cash flows arrive evenly through the year. This is an assumption, and exam questions usually accept it without comment.
Here is a worked example using the cash flows from the NPV chapter: -1000 today, then 300, 400, 500, and 200 in years 1 to 4.
| Year | Cash flow | Cumulative cash flow |
|---|---|---|
| 0 | -1000 | -1000 |
| 1 | 300 | -700 |
| 2 | 400 | -300 |
| 3 | 500 | 200 |
| 4 | 200 | 400 |
Cumulative cash flow turns positive during year 3. At the start of year 3, 300 is still unrecovered, and year 3 produces 500. Payback is 2 + 300/500 = 2.6 years.
Discounted payback
The discounted payback period fixes the time-value problem. You discount each cash flow at the project's required rate of return, then find when the cumulative discounted cash flow reaches zero.
With a 10% required return, the discounted cash flows are:
| Year | Cash flow | Discounted cash flow | Cumulative discounted |
|---|---|---|---|
| 0 | -1000 | -1000.00 | -1000.00 |
| 1 | 300 | 272.73 | -727.27 |
| 2 | 400 | 330.58 | -396.69 |
| 3 | 500 | 375.66 | -21.03 |
| 4 | 200 | 136.60 | 115.57 |
The cumulative total is still negative after year 3, at -21.03. It turns positive in year 4. Discounted payback is 3 + 21.03/136.60 = 3.15 years. The final cumulative figure, 115.57, equals the NPV computed earlier. This is a useful check: the last row of the cumulative discounted column is always the project's NPV.
Discounted payback is always longer than simple payback for a project with positive required return, because discounting shrinks every future cash flow.
Computing both in code
The function below finds both measures. It returns None when the investment is never recovered within the forecast.
def payback(cash_flows, rate=0.0):
"""Return the payback period in years.
rate=0.0 gives simple payback; rate>0 gives discounted payback.
Assumes cash flows arrive evenly within each year.
"""
cumulative = 0.0
for t, cf in enumerate(cash_flows):
discounted = cf / (1 + rate) ** t
previous = cumulative
cumulative += discounted
if t > 0 and previous < 0 <= cumulative:
return (t - 1) + (-previous) / discounted
return None
cash_flows = [-1000, 300, 400, 500, 200]
print(round(payback(cash_flows), 2)) # 2.6
print(round(payback(cash_flows, 0.10), 2)) # 3.15Why payback is still used
Payback has real weaknesses, yet many firms report it. The reasons are practical:
- It is easy to calculate and explain.
- It favors liquidity. A firm with limited access to financing may need cash back quickly.
- It works as a rough guard against risk when cash flows far in the future are very uncertain.
- It is a quick first screen before a fuller NPV analysis.
Limitations and errors to avoid
The table compares the two measures.
| Feature | Payback | Discounted payback |
|---|---|---|
| Time value of money | Ignored | Included |
| Cash flows after recovery | Ignored | Ignored |
| Cutoff period | Arbitrary | Arbitrary |
| Link to value creation | None | Partial |
| Relative length | Shorter | Longer |
Common errors:
- Treating payback as a profitability measure. A short payback does not mean a high NPV. A project can recover its cost in one year and then stop producing cash.
- Believing discounted payback is a complete rule. It includes time value, but it still ignores cash flows after the payback point. A project can have a discounted payback within the cutoff and a negative NPV only if later cash flows are negative, which is unusual. The more common failure runs the other way: a project with a long discounted payback is rejected even though large later cash flows give it a high NPV.
- Forgetting the cutoff is arbitrary. No theory tells you whether 3 years or 5 years is the right limit. Management picks it.
- Using discounted payback with the wrong rate. The discount rate must be the project's required return, usually the cost of capital adjusted for project risk.
- Misreading the fraction. The fraction uses the unrecovered amount at the start of the recovery year, not the cumulative figure at the end of it.
The next diagram summarizes the calculation steps.
Payback versus NPV in a conflict
Consider two projects, each costing 1000, with a 10% required return.
- Project A returns 600 in year 1, 500 in year 2, and nothing afterward. Payback is 1 + 400/500 = 1.8 years.
- Project B returns 100 in years 1 and 2, then 300, 400, and 600 in years 3, 4, and 5. Payback is well over 3 years.
On payback alone, A looks better. A's NPV is 600/1.10 + 500/1.21 - 1000 = 545.45 + 413.22 - 1000 = -41.33. B's NPV is positive: 90.91 + 82.64 + 225.39 + 273.21 + 372.55 - 1000 = 44.70. Payback ranks the project that destroys value ahead of the one that creates it, because it ignores the later cash flows.
Exercise
A project costs 2,000 and produces cash flows of 800 in year 1, 900 in year 2, and 1,000 in year 3. The required return is 8%. Calculate the payback period and the discounted payback period. Is the project acceptable if the firm requires discounted payback within 3 years?
Show answer
Simple payback: cumulative flow after year 2 is 1,700 against a cost of 2,000, so 300 remains. Year 3 produces 1,000. Payback = 2 + 300/1,000 = 2.3 years. Discounted flows: 800/1.08 = 740.74, 900/1.08^2 = 771.60, 1,000/1.08^3 = 793.83. Cumulative after year 2 is 1,512.34, leaving 487.66 unrecovered. Discounted payback = 2 + 487.66/793.83 = 2.61 years. This is within 3 years, so the project is acceptable on this criterion. The total discounted inflows are 2,306.17, so NPV is 306.17, which agrees.
Exercise
A project has a discounted payback of 2 years, but its cash flows in years 3 to 8 are all negative because of a large decommissioning cost. What does this show about discounted payback?
Show answer
It shows that discounted payback ignores cash flows after the payback point. The project meets a short discounted payback cutoff, yet the later negative flows can make the NPV negative. NPV, which includes every cash flow, is the reliable measure of value creation.