Why plans run over
Most schedules fail in the same direction. Tasks take longer than planned far more often than they take less. This chapter explains the mechanisms behind that pattern. Later chapters build on it to show how much buffer you need and where to put it.
Prerequisites
This chapter assumes you have:
- Basic familiarity with calendars or task lists, such as blocking time for tasks or keeping a to-do list with dates.
- Some experience estimating how long your own tasks take, even if the estimates were often wrong.
- Enough Python to read a short script. The one simulation here uses only the standard library.
You don't need any statistics beyond the ideas of an average and a typical value.
The planning fallacy
The planning fallacy is the tendency to underestimate how long a task will take, even when you know similar tasks have run late before. Daniel Kahneman and Amos Tversky named it in 1979. Later research by Roger Buehler, Dale Griffin, and Michael Ross tested it with students who were writing a thesis. The students gave an average estimate of about 34 days. The theses took about 55 days on average, and only around 30% were finished within the students' own estimate. The students had also been asked for a worst-case estimate, and many still exceeded that.
Two details matter for scheduling:
- The error is systematic. It isn't random noise that cancels out over many tasks. It leans one way.
- Knowing about the bias does not remove it. People can recite that projects run late and still give an optimistic estimate for their own next task.
Inside view and outside view
Kahneman describes two ways to estimate:
- The inside view builds the estimate from the specifics of this task: what you plan to do, in what order, with what resources. It feels thorough, but it only contains the events you thought of.
- The outside view ignores the specifics and asks how long tasks of this kind have taken in the past. It uses a reference class of similar tasks.
The inside view tends to produce a best-case story. The outside view is more accurate because it includes the delays, interruptions, and rework that you can't foresee individually but that happen reliably as a group. Later chapters apply the outside view by tracking your estimates against actuals.
Why the inside view runs short
Several mechanisms combine to make plans optimistic. Most of them are not carelessness.
- Best-case scenarios. When asked "how long will this take?", people picture a smooth run in which nothing goes wrong. A "realistic" prediction often turns out to be the same story.
- Forgotten work. The estimate covers the core activity, such as writing the report. It leaves out finding the data, getting a review, fixing feedback, and sending the result. Each omission is small, but together they are often 20% to 50% of the real effort.
- Interruptions and switching. Messages, questions, and meetings split focused time. Each return to the task has a restart cost that the estimate never included.
- Dependencies. Your work waits on other people's answers, approvals, or deliveries. You can't control these, and you rarely include them in your own estimate.
- Estimates that turn into commitments. If a low number will be accepted and a higher one will be challenged, there is pressure to give the low one.
- Memory edits. You remember past delays as one-off events ("that was unusual") instead of as part of the normal pattern.
Durations are skewed
A less obvious reason is purely mathematical. Task durations aren't symmetric around the typical value. A task estimated at 60 minutes can't finish in negative time, and it rarely finishes in 20 minutes. It can easily take 120, or 240 if something breaks. The distribution has a short left side and a long right tail.
That has two consequences:
- The average (mean) duration is higher than the typical (median) duration, because the tail pulls it up.
- People tend to estimate the typical case. If your estimate is the median, you finish on time only about half the time, per task.
Sums of skewed tasks
Planning a day means chaining several tasks. Even when every task has a 50% chance of finishing within its estimate, the chance that the whole sequence finishes within the sum of the estimates is much lower. The overruns are larger than the underruns, so the tail dominates the total.
The following script simulates this. Each task has a median of 60 minutes and a long right tail (a lognormal distribution). A "day" is 10 such tasks planned back to back at 60 minutes each.
import math
import random
random.seed(42)
MEDIAN_MINUTES = 60
SIGMA = 0.5 # controls how long the right tail is
TASKS_PER_DAY = 10
TRIALS = 10_000
def task_duration():
"""One task duration in minutes, with median MEDIAN_MINUTES."""
return random.lognormvariate(math.log(MEDIAN_MINUTES), SIGMA)
plan = MEDIAN_MINUTES * TASKS_PER_DAY
single_on_time = sum(task_duration() <= MEDIAN_MINUTES for _ in range(TRIALS)) / TRIALS
day_on_time = 0
total_minutes = 0.0
for _ in range(TRIALS):
day = sum(task_duration() for _ in range(TASKS_PER_DAY))
total_minutes += day
if day <= plan:
day_on_time += 1
print(f"Planned length of a day: {plan} minutes")
print(f"Average actual length: {total_minutes / TRIALS:.0f} minutes")
print(f"One task on time: {single_on_time:.0%}")
print(f"Whole day on time: {day_on_time / TRIALS:.0%}")Run it and you should see the following:
- Each single task finishes within 60 minutes about half the time.
- The whole day finishes within its 600-minute plan only about a quarter of the time.
- The average day runs close to 680 minutes, roughly 13% over plan.
The exact values vary a little with the random seed. The pattern doesn't change. The estimate for each task was fair, and the plan for the day still fails most of the time.
Real tasks are not independent as in this simulation. A bad morning can slow every task after it, which makes the real picture worse, not better.
Meetings and transitions
The same pattern appears in meetings. A meeting booked for 30 minutes can run to 40, but it rarely ends at 20 minutes in a way that gives you back usable time. Even when it ends on time, you spend a few minutes getting there, finding a place, and getting back into your own work. These are transition costs. They exist whether or not the calendar shows them.
A calendar that shows back-to-back blocks implies that the move from one block to the next is free. It never is. In the next chapters, the buffers that cover this gap are called transition buffers.
Delays spread through a schedule
Tasks in a schedule are linked. A late task pushes the start of the next one. Two kinds of link matter:
- Sequential links. A delay of 20 minutes in the first task moves everything after it by 20 minutes, unless something absorbs it.
- Merge points. When several tasks must all finish before the next one starts, the next task begins when the slowest of them finishes. Early finishes on the other tasks don't help. Delays pass through and early finishes are lost.
This asymmetry is the main reason that plans with no slack drift late. Delays accumulate and gains are wasted.
Putting the causes together
| Cause | What it does to a plan | Where you will see it |
|---|---|---|
| Best-case thinking | Estimate matches the smooth path only | Most estimates for new work |
| Forgotten work | Adds unlisted steps | Review, rework, delivery, admin |
| Interruptions | Splits focus time and adds restart cost | Open-plan offices, chat tools |
| Dependencies | Adds waiting you don't control | Approvals, handoffs, deliveries |
| Skewed durations | Makes the average exceed the typical case | Any task that can go badly wrong |
| Merge points | Passes delays on and discards early finishes | Multi-person or multi-step work |
| Commitment pressure | Pushes estimates lower | Estimates given to managers or clients |
Common errors in reasoning about overruns
- "I'll just be more careful next time." Effort and attention don't remove the causes above. Interruptions, dependencies, and skew come from the environment, not from your discipline.
- "My estimates are right on average, so I'm fine." Because of skew and chaining, estimates that are right for the typical case still fail for the whole plan. The question is how often the plan is met, not how close the typical estimate is.
- "This task is different." Each task feels unique from the inside. That feeling is the inside view at work. A reference class of similar past tasks is usually a better guide.
- "Late means I did something wrong." Sometimes it does. Often the schedule had no room for normal variation. Treat the first as a performance question and the second as a design question. Buffers address the second.
- Treating one overrun as unusual. If it happens most weeks, it is the normal pattern and the plan should account for it.
What this means for the rest of the tutorial
Because overruns are systematic and skewed, the response is also systematic: add deliberate slack, sized from your own record, and placed where it can absorb delay. The upcoming chapters cover why a fully booked day has no room for surprises, the types of buffer, how to record estimates and actuals, and how to size and place buffers.
Exercise
You plan a day of eight tasks, each estimated at 45 minutes, which is the typical duration for each. Your past records show each task finishes within its estimate about half the time. Why is it still unlikely that the whole day will finish on time, and what part of the cause is not about your attention or effort?
Show answer
Task durations are skewed: they have a short left side and a long right tail. A task can only finish a little early but can finish much later. When eight tasks run in sequence, the long overruns outweigh the small early finishes, so the total falls within the plan far less often than 50%, in the simulation's case only about a quarter of the time. The sequence also passes delays on to later tasks and wastes early finishes. These are properties of how durations and chained schedules behave, so they apply regardless of your focus or effort.
Exercise
List three items that are commonly missing from an inside-view estimate of "write a report", and say which view would find them more reliably.
Show answer
Examples include gathering or checking the data, waiting for and applying review feedback, formatting and delivering the report, and handling interruptions during writing. Any three of these are acceptable. The outside view finds them more reliably, because it looks at how long similar reports took in the past, which includes this extra work whether or not you thought of it in advance.
Exercise
A colleague says, "I know projects run late, so my estimates already take that into account." What is one way to check whether that is true?
Show answer
Compare past estimates with actual durations for a set of finished tasks. If the actual time exceeds the estimate in most cases, or if the whole plan was met less often than expected, the estimates do not yet account for the overruns. The record, not the colleague's impression, gives the answer.