Sub topic 4
Recording Estimates and Actuals
This chapter assumes you can already estimate how long your own tasks take and that you use a calendar or task list. It covers what to record, how to record it, and how to avoid the errors that make a record misleading. The next chapter uses this record to size buffers.
Why a record beats memory
The planning fallacy, covered earlier in this tutorial, means your sense of "how long things usually take" is biased toward the best cases. Memory also favors the vivid ones. You remember the report that took a whole day. You forget the five that ran 20 minutes over.
A written record replaces impressions with numbers. It lets you answer questions such as:
- By what factor do my estimates miss, on average?
- Is the miss the same for every kind of task?
- How bad is a bad case, not just a typical one?
The record is the input to buffer sizing. Without it, any buffer is a guess.
What to record
Keep the record small. If logging takes more than about 30 seconds per task, you will stop doing it. Capture these fields for each task:
| Field | Meaning | Example |
|---|---|---|
| Date | The day you did the work | 2026-01-05 |
| Task | A short name | Write report |
| Category | A type you can group by | writing |
| Estimate | Your prediction in hours or minutes, made before starting | 2 |
| Actual | Time you really spent | 3 |
| Note | Optional reason for a big miss | waited on data |
Three rules keep the data usable.
- Write the estimate before you start. An estimate written afterward is contaminated by what you now know. This is the most common way records become useless.
- Use one unit. Hours (or minutes) throughout. Mixed units cause silent errors in later calculations.
- Record elapsed working time, not calendar time. A task you worked on for 3 hours across two days has an actual of 3 hours, not 2 days.
Choose a category
Tasks of different kinds miss by different amounts. Writing a document with a clear outline is usually predictable. Debugging an unknown fault or waiting on another person is not. A category field lets you see this. Use a handful of broad categories, such as writing, review, meetings, coding, errands, and communication. Too many categories leave each one with too few entries to say anything.
Decide which tasks to log
You do not need to log everything. Start with tasks that:
- take 30 minutes or more,
- you estimated explicitly, and
- recur in some form, so past data can predict future work.
Skip trivial tasks. Their errors are small in absolute terms and they cost more to log than they teach.
Where to keep it
Any format works if you will actually fill it in. A spreadsheet with the columns above is enough. A plain CSV file is better if you want to analyze it with code, because it opens in a spreadsheet and in scripts alike.
date,task,category,estimate_h,actual_h,note
2026-01-05,Write report,writing,2,3,
2026-01-05,Review pull requests,review,1,1,
2026-01-06,Fix login bug,coding,4,5,reproducing took long
2026-01-07,Draft proposal,writing,1,1.5,
2026-01-08,Migrate data,coding,5,8,waited on dataYou can also add two columns to an existing task manager if it supports custom fields or time tracking. The test is whether recording a task fits into the moment you finish it.
A habit that works
A reliable routine has three touch points:
- Before starting: write the estimate next to the task.
- While working: note the start time. You do not need a stopwatch, but a rough start and stop is better than recalling the total hours later.
- At the end of the task or the day: write the actual and, if the miss was large, a one-line reason.
If you log only at the end of the day, do it within a few hours of finishing. Actuals reconstructed a week later are usually wrong, and wrong in a consistent direction: people remember the work as shorter than it was.
Turning the record into a ratio
Comparing raw differences ("I was 1 hour over") hides the pattern, because a 1-hour miss on a 1-hour task is far worse than on a 10-hour task. Use the ratio of actual to estimate instead:
- A ratio of 1.0 means the estimate was exact.
- A ratio of 1.5 means the task took 50% longer than planned.
- A ratio below 1.0 means you finished early.
The ratio scales with task size, so you can apply it to a new estimate by multiplying. The following script reads the CSV above, computes each ratio, and reports the average and the spread overall and per category.
import csv
import io
from collections import defaultdict
from statistics import mean, median
DATA = """date,task,category,estimate_h,actual_h,note
2026-01-05,Write report,writing,2,3,
2026-01-05,Review pull requests,review,1,1,
2026-01-06,Fix login bug,coding,4,5,reproducing took long
2026-01-07,Draft proposal,writing,1,1.5,
2026-01-08,Migrate data,coding,5,8,waited on data
"""
rows = list(csv.DictReader(io.StringIO(DATA)))
by_category = defaultdict(list)
for row in rows:
estimate = float(row["estimate_h"])
actual = float(row["actual_h"])
if estimate <= 0:
continue # a zero estimate has no meaningful ratio
by_category[row["category"]].append(actual / estimate)
all_ratios = [r for ratios in by_category.values() for r in ratios]
print(f"All tasks: n={len(all_ratios)}, "
f"mean={mean(all_ratios):.2f}, median={median(all_ratios):.2f}, "
f"max={max(all_ratios):.2f}")
for category, ratios in sorted(by_category.items()):
print(f"{category:8} n={len(ratios)}, "
f"mean={mean(ratios):.2f}, max={max(ratios):.2f}")Running it on the sample data gives an overall mean of about 1.35 and a maximum of 1.60. Writing averages 1.50, review 1.00, and coding 1.43. Even five rows hint at a pattern: your estimates run short, and review work is accurate while writing and coding are not.
Mean, median, and the tail
The mean tells you about the typical overrun. A buffer, however, exists for the bad cases, so the upper end of the distribution matters more. You will use a high percentile such as the 80th when sizing buffers. For now, record enough data that the upper end is visible. Keep the max and the notes on large misses, because they tell you whether bad cases come from a known cause (waiting on someone) or from nowhere in particular.
How much data is enough
Percentiles and averages from a few points are noisy. A single outlier can change them a lot. As a rough guide:
- Under 10 entries: treat the numbers as a hint. Use a simple rule, such as planning for the largest ratio you have seen.
- 10 to 30 entries: the overall ratio becomes useful. Per-category numbers are still shaky.
- 30 or more entries overall, and about 10 per category: you can trust category-level ratios and a high percentile.
If a category has too few entries, fall back to the overall ratio and say so in your notes. Do not draw conclusions from two data points.
Common errors in the record
These errors are the main reason people distrust their own data.
- Estimating after the fact. Covered above. The estimate must predate the work.
- Revising the estimate mid-task. If you realize halfway that a task will take longer, keep the original estimate in the record. The original is the prediction you are calibrating. You can add the revised figure in the note.
- Logging only the surprises. If you record only the tasks that went wrong, every ratio looks bad and the buffer comes out too large. Record the ones that went well too. This is survivorship bias in reverse.
- Dropping the "ugly" tasks. The opposite problem: leaving out interrupted or abandoned tasks because they are messy. Interrupted tasks are exactly the ones that eat buffer. Record the time spent and mark them in the note.
- Counting interruptions inconsistently. Decide in advance whether the actual includes time lost to interruptions. Either choice is valid, but mixing them makes ratios inconsistent. A practical choice is to log the working time as the actual and track interruptions separately, since they are the thing a transition or task buffer absorbs.
- Anchoring on a deadline. If you set the estimate to fit the time you have rather than your honest prediction, the ratio measures nothing about your skill at estimating. Write the honest number first, then compare it to the time available.
- Rounding. Rounding every estimate and actual to the nearest hour turns a 20-minute task into 0 and breaks the ratio. Use 15-minute increments (0.25 hours) for short tasks.
Reading the pattern
Once you have some data, look for three things.
- Direction. Is the overall ratio above 1.0? Most people find it is. A ratio around 1.3 to 1.5 is common, but your own number is what matters.
- Consistency. Are ratios clustered (most between 1.1 and 1.4) or spread out (some at 1.0, some at 3.0)? Clustered misses can be handled with a proportional buffer. Spread-out misses point to unpredictable work that needs a larger or more flexible buffer.
- Differences between categories. If meetings run on time and coding runs 1.5 times over, one blanket percentage will over-buffer the first and under-buffer the second.
Also look at the notes on your worst misses. If three of your five biggest overruns say "waiting on someone," the problem is not estimating skill. It is dependency, and a buffer on the task alone will not fix it. A better fix is to start earlier or to schedule a follow-up before the work begins.
Weekly review
Spend 10 minutes at the end of each week:
- Make sure every task you did has an estimate and an actual.
- Rerun the ratio script or update your spreadsheet.
- Write one sentence on what stood out, such as "review tasks accurate, coding 40% over."
Do not change your buffers every week. A week of data is too little. Use the review to keep the log complete and to spot data problems early. The next chapter covers how to turn the accumulated record into a buffer size, and a later chapter returns to periodic recalibration.
Exercise
A colleague logs only the tasks that ran badly over. Her log has 8 entries with an average ratio of 2.1, so she plans to multiply every future estimate by 2.1. Name the problem with her record and say what she should do.
Show answer
She has selection bias. Because she logged only the bad cases, the ratio overstates how much her estimates normally miss, and multiplying everything by 2.1 will over-buffer most days and waste time. She should record every task of meaningful size, including the ones that went fine, with the estimate written before starting. After she has 10 to 30 entries from all kinds of tasks, she can compute the ratio again.
Exercise
A task was estimated at 2 hours and took 3 hours, which is a ratio of 1.5. Another was estimated at 10 hours and took 11 hours. Why is the ratio more useful than the difference when applying the result to future estimates?
Show answer
The second task is 1 hour over, the same difference as the first at a glance, yet it is only 10% over (ratio 1.1) while the first is 50% over. The ratio scales with task size, so you can multiply a new estimate of any length by it. A fixed difference does not transfer between a 1-hour task and a 10-hour task.
Exercise
You start a task estimated at 3 hours. After one hour you realize it will take 6 hours, so you change the estimate in your log to 6. Why does this weaken your record, and what should you do instead?
Show answer
The estimate is supposed to be your prediction before the work started, since that is what you are calibrating. Replacing it with 6 makes the ratio look like 1.0 and hides the miss. Keep the original 3 hours in the estimate column and put the revised figure and the reason in the note.