Sub topic 12
Reviewing and adjusting over time
This chapter assumes you already record estimates, size buffers from your history, and place them in your schedule. It also assumes you know what happens when a buffer is used up. Here you will close the loop. You will check whether your buffers worked, decide what to change, and avoid changing the wrong thing.
Why a buffer needs a review
A buffer is a forecast. It says "tasks of this kind run about this much over their estimate." Like any forecast, it drifts out of date. Your work changes, your tools change, and your estimating improves or worsens. A buffer you set in January may be too large or too small by June.
Without a review you can fail in two opposite ways:
- The buffer is too small, so you keep overrunning and lose trust in your schedule.
- The buffer is too large, so you finish early, fill the gap with low-value work, and carry more slack than you need.
Both failures look fine from the inside. A review makes them visible by comparing what you planned with what happened.
What to measure
Review a small set of numbers. More than this and you will stop doing the review.
| Measure | How to compute it | What it tells you |
|---|---|---|
| Overrun ratio | actual ÷ estimate, per task | How wrong the raw estimate was |
| Coverage | share of tasks that finished within estimate plus buffer | Whether the buffer is big enough |
| Buffer use | buffer minutes consumed ÷ buffer minutes planned | Whether the buffer is too big or too small |
| Spill-over | tasks that pushed into the next day or week | Whether overruns are escaping the buffer |
Coverage is the most useful of these. If you size buffers at the 80th percentile of past ratios, you expect about 80% coverage. If your measured coverage over the last month is 55%, the buffer is too small or your work has changed. If it is 98%, the buffer is probably larger than you need.
Buffer use is a second check from the other side. A buffer that is never touched across many weeks is a candidate for shrinking. A buffer that is fully consumed every week is a candidate for growing. A buffer that is sometimes empty and sometimes full is doing its job.
The review loop
Run the review on a fixed rhythm. A short weekly check and a longer monthly check work well for most people.
The two "keep" branches matter as much as the "adjust" branch. Most reviews should end with no change. If you change a buffer every week, you are reacting to noise.
Weekly check (10 minutes)
- Look at which tasks overran and which finished early.
- Make sure every task has an estimate and an actual in your log. Missing data is the main reason reviews fail.
- Note any one-off cause, such as an outage, illness, or a task that was badly specified. Mark these as exceptions so they do not distort the numbers later.
Monthly check (30 minutes)
- Compute ratios and coverage per category.
- Compare them with your current buffer for that category.
- Change a buffer only if the gap is clear and the sample is large enough.
- Write down what you changed and why.
Review per category, not overall
A single average hides the differences that matter. Writing, meetings, and code review overrun in different ways. Meetings often run close to their length, because the calendar enforces an end time. Creative or exploratory work overruns more and with more spread. If you pool them, the pooled buffer is too large for meetings and too small for writing.
Group tasks by how they behave, not by project. Three to five categories is enough. More categories split your history into samples too small to trust.
A review script
The script below groups records by category, computes the median and 80th percentile of the overrun ratio, and compares the percentile with the buffer factor you currently use. It reports "raise", "lower", or "keep", and refuses to judge a category with too few samples.
from collections import defaultdict
from statistics import median, quantiles
MIN_SAMPLES = 5
TOLERANCE = 0.10
# (category, estimated_hours, actual_hours)
records = [
("writing", 2, 3.0),
("writing", 4, 5.5),
("writing", 3, 3.5),
("writing", 1, 1.5),
("writing", 5, 7.0),
("meetings", 1, 1.0),
("meetings", 0.5, 0.5),
("meetings", 1, 1.0),
("meetings", 1, 1.25),
("meetings", 2, 2.0),
]
# Buffer factor now in use: planned time = estimate * factor
current_factor = {"writing": 1.25, "meetings": 1.25}
by_category = defaultdict(list)
for category, estimate, actual in records:
by_category[category].append(actual / estimate)
for category, ratios in by_category.items():
if len(ratios) < MIN_SAMPLES:
print(f"{category:9} n={len(ratios)} too few samples, keep logging")
continue
p80 = quantiles(ratios, n=10)[7]
current = current_factor[category]
gap = p80 - current
if gap > TOLERANCE:
action = "raise"
elif gap < -TOLERANCE:
action = "lower"
else:
action = "keep"
print(
f"{category:9} n={len(ratios)} median={median(ratios):.2f} "
f"p80={p80:.2f} current={current:.2f} -> {action}"
)Running it prints:
writing n=5 median=1.40 p80=1.50 current=1.25 -> raise
meetings n=5 median=1.00 p80=1.20 current=1.25 -> keepWriting consistently runs about 40% over its estimate, so a factor of 1.25 leaves it under-buffered. Meetings run close to estimate, and the current factor is within tolerance of the data, so you leave it alone.
The TOLERANCE value is a dead band. Without it, a gap of 0.02 would trigger a change, and you would keep adjusting by amounts smaller than the noise in your data.
Choosing a window
The history you use is a design choice.
| Window | Advantage | Risk |
|---|---|---|
| All history | Largest sample, stable numbers | Slow to reflect that you improved or that your work changed |
| Rolling window (last 20 to 30 tasks) | Tracks recent behavior | Noisier, and one bad stretch can dominate |
| Since last major change | Matches your current situation | May start with too few samples |
A rolling window is a good default. After a major change, such as a new role, a new team, or a new tool, start a fresh window for the affected categories. Old data from a different situation will mislead you. Until the new window fills, use a conservative buffer from your best guess and say so in your notes.
Separate the estimate from the buffer
When actuals exceed your plan, two different things can be wrong:
- Your estimates are biased. You consistently predict too little time.
- Your buffer is too small for the variability of the work.
These need different fixes. If every task of a type runs about 40% over, the estimate is biased, and a consistent multiplier corrects it. If most tasks finish on time but a few run to three times the estimate, the problem is spread. A larger multiplier would waste time on every ordinary task. Instead, hold a shared buffer for rare big overruns.
You can tell them apart by comparing the median ratio with the 80th percentile ratio. A median well above 1.0 points to bias. A median near 1.0 with a high 80th percentile points to spread.
In the script output, writing has a median of 1.40, so the estimate itself is biased. Meetings have a median of 1.00 and a p80 of 1.20, so the tail is the only issue and it is small.
Reading the signals
Use this table to turn what you see into an action.
| Signal | Likely cause | Action |
|---|---|---|
| Coverage far below target, ratios consistently above 1 | Estimates biased low | Raise the multiplier for that category |
| Coverage below target, median near 1, a few large outliers | High variance | Add or enlarge a shared buffer; do not inflate every task |
| Buffers unused for many weeks | Buffer too large, or work got more predictable | Lower the buffer a step, then watch |
| Buffers always fully used | Parkinson's law, or buffer too small | Check whether tasks expand to fill time (see below) before raising |
| Overruns cluster on certain days | Placement problem, not size | Move the buffer; see the placement chapter |
| One category has too few samples | Not enough data | Keep logging, use a provisional buffer |
The fully-used row needs care. A buffer that is always exactly consumed does not prove that you need more. People tend to let work grow to fill the time available. Check whether the tasks that "used" the buffer were actually behind schedule or just ran to the end of the slot. If you finished the core work early and polished until the time ran out, the buffer is working as slack, not as insurance, and raising it will not help.
Adjust in small steps
When the data says a buffer should change, change it by a modest amount, such as 0.1 on the multiplier or 5 to 10 minutes on a fixed gap. Then review again after the next period. Large jumps overshoot, and you cannot tell afterward which part of the change helped.
Also record every change with the date and the reason. A short log entry is enough:
2026-03-02 writing factor 1.25 -> 1.40 (last 20 tasks: median 1.38, p80 1.52)This log lets you check later whether a change improved coverage. It also prevents a common loop: you raise a buffer, forget you did, then conclude months later that the buffer "never worked."
Do not tune toward a perfect score
Coverage of 100% is not the goal. It would require a buffer large enough to cover your worst day, and that cost falls on every other day. The target is a level of coverage you have chosen on purpose, with the remaining overruns handled by your response plan when a buffer runs out. For most personal schedules an 80% target is a reasonable start. For work with serious consequences for lateness, choose a higher percentile and accept the cost.
Reviews can also fail by being too clever. If your review takes an hour and requires a spreadsheet of formulas, you will skip it. A simple log and a monthly look at two or three numbers beats a sophisticated process you abandon.
Common errors
- Reviewing without actuals. If you do not record how long things took, you can only guess whether the buffer worked. Log the actual at the end of each task, while you still remember.
- Excluding every bad week. Marking a task as an "exception" is legitimate for true one-offs. If most overruns end up as exceptions, your numbers will look better than reality, and your buffers will shrink.
- Changing several things at once. If you alter estimates, buffer sizes, and placement in the same week, you cannot tell which change mattered.
- Reacting to the last task. One overrun is an event. A pattern across a category is evidence.
- Pooling unlike work. An average across writing and meetings fits neither.
Summary of the practice
- Log an estimate and an actual for each task.
- Group tasks into a few categories.
- Each month, compute the median and 80th percentile ratio and the coverage per category.
- Compare with your current buffer. Ignore gaps inside your tolerance.
- Tell bias apart from spread, and fix each in the right place.
- Change one thing, in a small step, and record it.
- Review again next period to see whether the change helped.
Exercise
Over the last 25 tasks in one category, your median overrun ratio is 1.02 and your 80th percentile ratio is 1.9. You currently use a multiplier of 1.2 on every task of that category, and your coverage is 62%. Is the main problem biased estimates or high variance, and what would you change instead of simply raising the multiplier to 1.9?
Show answer
The median near 1.0 means a typical task is estimated well, so the estimates are not biased. The high 80th percentile means a minority of tasks overrun by a lot, which is variance. Raising every task to 1.9 would add large unused slack to the many tasks that finish on time. Keep a small multiplier, perhaps 1.1 to 1.2, and hold a shared buffer for the occasional big overrun. Also look at what the large overruns have in common, such as unclear requirements, since reducing that cause may help more than any buffer.
Exercise
A category has only 6 recorded tasks. The script says "raise", because one task ran at 2.5 times its estimate. What should you do, and why?
Show answer
Treat the result as provisional. Six samples is barely above the minimum, and one outlier can set the 80th percentile on its own. Look at the outlier first. If it had a one-off cause, mark it as an exception. If it is a normal example of how this work goes wrong, it is evidence of variance. Either way, keep logging until you have a larger window of about 15 to 30 tasks, and make at most a small change in the meantime, such as a 0.1 increase, with a note of the reason so you can check it later.
Exercise
Your afternoon buffer has been fully used every day for three weeks. Before enlarging it, what should you check?
Show answer
Check whether the buffer is absorbing real overruns or whether work is expanding to fill the time (Parkinson's law). Look at the tasks that consumed the buffer. If they were behind schedule for reasons outside your control, the buffer may be too small. If the core work was done early and the rest of the time went to extra polish or low-priority tasks, a larger buffer would just be filled too. Compare against the overrun ratios in your log, and move or resize the buffer only if the ratios support it.