What Counts as a Risk
Prerequisites
You should understand how projects are organized into scope, schedule, budget, and stakeholders. You should have worked on or alongside a project team, and you should be comfortable using a spreadsheet to track items.
Risks, issues, assumptions, and constraints
A risk is an uncertain future event that would affect one or more project objectives if it happened. Four kinds of items often get mixed up in a register, so separate them first:
| Item | Meaning | Example |
|---|---|---|
| Risk | Uncertain event that has not happened yet | The vendor may miss its delivery date |
| Issue | Problem that has already happened | The vendor missed its delivery date |
| Assumption | Condition taken as true without proof | The vendor will deliver on time |
| Constraint | Fixed limit the project must work within | The budget cannot exceed 200,000 |
Why keep a risk register
A risk register is one list of identified risks, with each risk's score, owner, and planned response. It gives the team a single place to see what could go wrong and who is watching each risk. A register that nobody updates goes stale and stops helping decisions.
Anatomy of a register: fields that matter
Most useful registers include these fields:
- ID: a unique label, such as R-001, for referring to the risk.
- Statement: a cause, event, and effect written in one sentence.
- Probability and impact: ratings, usually on a 1 to 5 scale.
- Owner: the one person accountable for watching the risk.
- Response and status: the planned action and whether the risk is open or closed.
Finding risks: workshops, checklists, and reviews
Use three methods together. Hold a workshop with the team and key stakeholders to brainstorm. Check a list of risks from past projects. Review the assumptions and open issues from the current project, because a weak assumption often hides a risk.
Writing clear risk statements
Write each risk as: "Because [cause], [event] may happen, causing [effect]." For example: "Because the payment vendor has no sandbox SLA, integration testing may be delayed, causing a two-week launch slip."
Exercise:
Exercise
A team writes "Vendor problems." Why is this a weak risk statement, and what would make it stronger?
Show answer
It names no cause, no event, and no effect, so nobody can judge how likely it is or what to do. A stronger version is: "Because the vendor has no sandbox SLA, integration testing may be delayed, causing a two-week launch slip."