Sub topic 3
Triggers, contingency plans, and reserves
This chapter assumes you can write risk statements with cause, event, and effect, and score them on a 5 by 5 probability and impact matrix. You should also be comfortable reading a CSV register.
Triggers and contingency plans
A trigger is a measurable signal that a risk is occurring or about to occur. A contingency plan is the prepared response you run when the trigger fires. Set both when you record the risk, not later.
risks = [
{"id": "R-001", "trigger": "Sandbox not ready by 1 March", "sandbox_ready": False},
{"id": "R-003", "trigger": "Migration under 50% complete on 1 May", "pct_complete": 35},
]
def fired(risk):
if "sandbox_ready" in risk:
return not risk["sandbox_ready"]
return risk["pct_complete"] < 50
for r in risks:
status = "FIRED" if fired(r) else "ok"
print(r["id"], status, "-", r["trigger"])Reserves
A contingency reserve is money or time held back to pay for a risk if it occurs. Size it from the expected monetary value (probability multiplied by cost) of the risks it covers.
Residual and secondary risks
A residual risk is the risk left after a response. A secondary risk is a new risk that the response creates. Record both, and score them the same way as any other risk.
Keeping the register alive: review cadence
Review the register on a fixed schedule, such as every two weeks, and after any major change. At each review, update scores, check triggers, and close risks that have passed.
Reporting and escalation
Report the top risks by score, each trigger's status, and reserve use. Escalate any risk whose exposure exceeds the tolerance the sponsor has set, and do not wait for the next review.
Closing risks and lessons learned
Close a risk when its event can no longer happen or its effect has passed. Record what the team learned: which triggers were early, which responses worked, and which risks were missed.
Pitfalls and good practices
Avoid scoring every risk as high, leaving owners blank, and letting the register go stale for months. Good practice is a short register that gets reviewed on schedule.
Exercise
In the script above, what does the output show for R-003 if its pct_complete value changes to 60?
Show answer
The trigger no longer fires, so the line prints "ok" for R-003.