Sub topic 2
Risk appetite and tolerance
This chapter assumes you know what a project risk register is, can read a spreadsheet, and understand the basic project areas of scope, schedule, budget, and stakeholders. The code requires Python 3.
Risk appetite and tolerance
Risk appetite is the total amount of risk an organization will accept to reach its goals. Risk tolerance is the acceptable variation around one specific objective, usually stated as a limit. Appetite might be "moderate risk for new markets," while tolerance might be "schedule slip of no more than two weeks." Set both before scoring so every rating has a reference point.
Defining probability and impact scales
Probability is the likelihood that a risk occurs. Impact is how much the risk would hurt objectives if it occurred. Use a 1 to 5 scale for each, and define every level in terms your team understands.
| Score | Probability | Impact on schedule |
|---|---|---|
| 1 | Rare (under 10%) | Less than 2 days |
| 3 | Possible (30 to 50%) | 2 to 4 weeks |
| 5 | Almost certain (over 90%) | More than 2 months |
Scoring and ranking with a risk matrix
Multiply probability by impact to get a score from 1 to 25. Then band the score. The matrix below uses 15 or more for High, 8 to 14 for Medium, and under 8 for Low. Your team chooses the bands.
def rating(probability, impact):
score = probability * impact
if score >= 15:
return score, "High"
if score >= 8:
return score, "Medium"
return score, "Low"
print(rating(4, 4)) # (16, 'High')
print(rating(2, 3)) # (6, 'Low')Expected monetary value
Expected monetary value (EMV) is the probability of a risk multiplied by its cost if it occurs. A 40 percent chance of a 50,000 cost has an EMV of 20,000. Summing the EMVs gives a basis for sizing a contingency reserve.
risks = [
{"id": "R-001", "probability": 0.40, "cost": 50000},
{"id": "R-003", "probability": 0.30, "cost": 20000},
]
total = sum(r["probability"] * r["cost"] for r in risks)
print(total) # 26000.0Choosing a response strategy
Each risk needs one response strategy. Avoid changes the plan so the risk cannot occur. Mitigate reduces probability or impact. Transfer shifts the impact to a third party, such as an insurer or a fixed-price contract. Accept keeps the risk and plans for it.
> Note: the table below lists each strategy with an example.
| Strategy | Meaning | Example |
|---|---|---|
| Avoid | Change the plan so the risk cannot occur | Drop a vendor that has no test sandbox |
| Mitigate | Reduce probability or impact | Add a second test environment |
| Transfer | Shift the impact to a third party | Buy a fixed-price contract |
| Accept | Keep the risk and plan for it | Hold a contingency reserve |
Assigning owners and actions
Every risk needs one named owner, one dated action, and a trigger that tells the owner when to act. Owners make decisions. Several people can help, but only one person is accountable.
Exercise
A risk has a probability score of 3 and an impact score of 5. What is its score and band under the bands in this chapter?
Show answer
The score is 15, which is High, because 3 multiplied by 5 equals 15 and 15 or more is High.