Sub topic 1
Start from the project scope
A work breakdown structure (WBS) is a hierarchy that divides a project's total scope into smaller parts. This chapter shows how to derive the first levels of a WBS from a scope statement and check them.
Prerequisites
You should be comfortable with basic project vocabulary, including project, deliverable, and milestone. You should also have a written scope statement, or an equivalent description of what the project must deliver. Familiarity with outlines and tree structures will help.
Starting from the scope statement
Read the scope statement and list every deliverable it promises. A deliverable is a tangible result, such as a report, a system, or a trained team. Do not list activities such as "meet with stakeholders." Activities describe how work happens. Deliverables describe what the project produces.
Thinking in deliverables
Name each top-level element as a noun phrase that describes a result. For a website relaunch, "Design," "Content," and "Platform" are reasonable top-level elements. Each element should map to a result you can inspect when it is done.
Levels and parent-child relationships
A WBS is a tree. The project is the root. Each child element is a part of its parent, and each parent is the sum of its children. Level 1 holds the major deliverables, and deeper levels break those deliverables into smaller pieces.
The 100% rule and mutual exclusivity
The 100% rule states that the WBS includes all work in the scope, and nothing outside it. Mutual exclusivity means no piece of work appears under two elements. Together, these rules mean each scope item sits under exactly one element.
scope = {"page templates", "style guide", "migrated pages", "landing pages"}
wbs = {
"Design": {"page templates", "style guide"},
"Content": {"migrated pages", "landing pages"},
}
covered = [item for items in wbs.values() for item in items]
missing = scope - set(covered)
duplicates = {i for i in covered if covered.count(i) > 1}
print("missing:", missing) # missing: set()
print("duplicates:", duplicates) # duplicates: set()> Note: a check that passes only proves the names match. A team review is still needed to confirm the wording of each element.
Decomposing level by level
Break each top-level element into its parts, then repeat the process for each part. Stop when a piece is a work package that you can estimate, assign, and track. The first levels are the most important, because later decisions depend on them.
flowchart TD
A[Project scope] --> B[Design]
A --> C[Content]
A --> D[Platform]
B --> B1[Page templates]
B --> B2[Style guide]caption: Top-level elements derived from a website relaunch scope. alt: A tree with the project scope at the top, branching to Design, Content, and Platform. Design branches further into Page templates and Style guide.
Exercise
Q: The scope statement says "the website will include a contact form and a blog." Is "Build contact form" a valid top-level element? Explain why or why not.
A: No. It describes one piece of work, not a top-level deliverable. A better top-level element would be "Website features," with "Contact form" and "Blog" as child elements.