Sub topic 3
Documenting Elements in a WBS Dictionary
This chapter assumes you know the WBS hierarchy, the 100% rule, and work packages, and that you can estimate work in days or hours.
Documenting elements in a WBS dictionary
A WBS dictionary is a document that describes each WBS element in detail. The WBS shows what the work is. The dictionary records what each element includes, what it excludes, what it delivers, and who is responsible. Each entry usually records:
- Code and name
- Description and scope boundaries
- Deliverable and acceptance criteria
- Responsible owner
- Estimate and assumptions
- Exclusions, so that no two elements claim the same work
code: "1.1.1"
name: Page templates
deliverable: Approved HTML/CSS templates in the project repository
acceptance_criteria:
- Renders correctly on agreed browsers
- Approved by the product owner
responsible: Design lead
estimate_days: 8
excluded: Content writing (see 1.2)Validating the WBS with the team
Review the WBS with the people who will do the work. Check three things: every needed element is present, no two elements overlap, and every work package has an owner and an estimate. Record the team's agreement, and close gaps before the plan is baselined.
Rolling up estimates from work packages
Estimates belong at the leaves. Each parent's total is the sum of its children.
def rollup(node):
children = node.get("children")
if not children:
return node["estimate_days"]
return sum(rollup(child) for child in children)
tasks = {
"code": "1.2", "name": "Content",
"children": [
{"code": "1.2.1", "name": "Migrated pages", "estimate_days": 10},
{"code": "1.2.2", "name": "New landing pages", "estimate_days": 4},
],
}
print(rollup(tasks)) # 14Control accounts and responsibility assignment
A control account is a WBS element, usually at a middle level, where one manager tracks scope, schedule, and cost. Assign each work package to exactly one responsible person, and record that owner in the dictionary.
Rolling wave planning for uncertain work
When detail is unknown, plan near-term work in detail and keep distant work as high-level planning packages. Refine those packages as information arrives. Mark them as provisional in the dictionary so readers know they will change.
Keeping the WBS current under change control
Scope changes go through a formal change request. When a change is approved, update the affected WBS elements and dictionary entries, recalculate estimates, and record the revision date and reason. Do not edit the approved baseline silently.
Common mistakes and how to avoid them
- Describing activities instead of deliverables.
- Omitting exclusions, so two elements claim the same work.
- Estimating a parent directly and then double counting its children.
- Leaving out owners, so no one is accountable.
- Letting the dictionary drift from the WBS after changes.
Exercise
Element 1.2.1 "Migrated pages" is estimated at 10 days, and element 1.2.2 "New landing pages" is estimated at 4 days. What is the rolled-up estimate for element 1.2?
Show answer
14 days, the sum of its two child work packages.