Knowing When to Stop Decomposing
This chapter assumes you know basic project terms (project, deliverable, milestone), that you have a written scope statement, and that you can read an indented outline. It continues from the earlier chapters on scope and the 100% rule.
When to stop decomposing
Keep splitting an element until you can estimate it, assign it to one owner, and track its progress. If you cannot say how long it takes or who does it, split it again. Stop when another split would produce pieces that look the same or add tracking effort without adding control.
Defining work packages
A work package is a leaf element of the WBS, the lowest level where effort is estimated, scheduled, and assigned. Each work package should have:
- one clear deliverable or output
- one accountable owner
- an effort or duration estimate
- no scope shared with a sibling element
Choosing how to organize the first levels
The top levels can follow deliverables, phases, or a hybrid of both. Deliverable-based organization suits projects that produce distinct outputs. Phase-based organization suits projects where stages gate the work. Pick one approach for each level and state it in the WBS.
| Approach | Top-level elements are | Best when |
|---|---|---|
| Deliverable | Products or outputs | Scope is defined by what gets built |
| Phase | Project stages | Each stage must finish before the next starts |
| Hybrid | Deliverables, with phases below | Both matter to the sponsor |
Numbering and coding WBS elements
Use hierarchical codes so each element shows its position. Each child adds one segment to its parent's code:
1 Website Relaunch
1.1 Design
1.1.1 Page templatesNever reuse a retired code, because old reports and dictionary entries would then point to the wrong element.
Showing the WBS as an outline, tree chart, or table
An outline is an indented list that is easy to edit. A tree chart shows the structure visually for presentations. A table lists each element with its code, name, and owner, which suits spreadsheets and dictionaries. Choose the form your team will keep current.
Exercise
The work package "Write landing page copy" has two owners and no estimate. What should you do?
Show answer
Split it so each piece has one owner, then estimate each piece. A work package needs a single accountable owner and an effort estimate before the team can track it.