What a project budget is for
Prerequisites
This chapter assumes you can do basic arithmetic and percentages, that you can use a spreadsheet or run a short Python script, and that you have a general sense of a project's scope (the work it must deliver) and schedule (when that work happens).
Purpose of a project budget
A project budget is the approved amount of money a project may spend, together with a plan for spending it. An estimate predicts the cost of a piece of work. A forecast predicts the final cost and changes as work progresses. The budget is the baseline that estimates and forecasts are compared against.
Breaking scope into work packages
A work package is a unit of scope small enough to estimate, assign, and track. Split the scope until each package has a clear deliverable, an owner, and a cost you can estimate. For a website project, the packages might be Design, Development, and Testing.
Estimating labor and non-labor costs
Labor cost is hours multiplied by an hourly rate, summed over all packages. Non-labor cost covers everything else, such as software licenses and hosting. Adding both gives the direct cost.
tasks = [
{"name": "Design", "hours": 40, "rate": 80.0},
{"name": "Development", "hours": 120, "rate": 90.0},
{"name": "Testing", "hours": 50, "rate": 70.0},
]
non_labor = {"Software licenses": 1200.0, "Hosting": 600.0}
labor = sum(t["hours"] * t["rate"] for t in tasks)
direct = labor + sum(non_labor.values())
print(f"Labor: {labor:.2f}")
print(f"Direct costs: {direct:.2f}")Exercise
Design takes 30 hours at 80.00 per hour, and Testing takes 50 hours at 70.00 per hour. What is the total labor cost for these two packages?
Show answer
Design costs 30 x 80.00 = 2400.00 and Testing costs 50 x 70.00 = 3500.00, so the total labor cost is 5900.00.