Sub topic 3
Measuring variance against the baseline
This chapter assumes you have a budget baseline: a per-package budget already split across work packages. You should also be comfortable with basic arithmetic and running a short Python script.
Comparing actuals with the baseline
Variance is the difference between the budget and what you expect to spend. Calculate it as:
variance = budget - forecast
A negative variance means the work package will overrun. The code below uses the baseline and actual costs from the topic's example.
budget = {"Design": 3200.0, "Development": 10800.0, "Testing": 3500.0}
actual = {"Design": 3600.0, "Development": 5000.0, "Testing": 0.0}
estimate_to_complete = {"Design": 0.0, "Development": 6200.0, "Testing": 3500.0}
total_budget = 0.0
total_forecast = 0.0
for name in budget:
forecast = actual[name] + estimate_to_complete[name]
variance = budget[name] - forecast
total_budget += budget[name]
total_forecast += forecast
print(f"{name}: forecast {forecast:.2f}, variance {variance:.2f}")
print(f"Total: budget {total_budget:.2f}, forecast {total_forecast:.2f}, "
f"variance {total_budget - total_forecast:.2f}")Running it prints the variance for each package and the total.
| Work package | Budget | Forecast | Variance |
|---|---|---|---|
| Design | 3200.00 | 3600.00 | -400.00 |
| Development | 10800.00 | 11200.00 | -400.00 |
| Testing | 3500.00 | 3500.00 | 0.00 |
| Total | 17500.00 | 18300.00 | -800.00 |
Forecasting the cost at completion
The estimate at completion (EAC) is the actual cost to date plus the estimate to complete (ETC). The forecast in the code above is this EAC for each package.
> Note: Forecast only from measured actuals and a fresh ETC. Do not assume remaining work will cost exactly what the baseline said.
Handling changes without losing the baseline
When scope or cost changes, record the change in a change log with its amount and reason. Do not overwrite the baseline. Compare forecasts against the original baseline and the approved changes separately, so the overrun stays visible.
Reporting budget status to stakeholders
Keep the status report short. Include the baseline total, the forecast total, the variance, the approved changes, and the main reason for any overrun. For the example above, report that the project is forecast at 18300.00 against a baseline of 17500.00, an overrun of 800.00, driven by Design and Development.
Exercise
Exercise
Testing has a budget of 3500.00, actual cost of 1000.00, and an ETC of 2000.00. What is its forecast, and what is its variance?
Show answer
The forecast is 1000.00 + 2000.00 = 3000.00. The variance is 3500.00 - 3000.00 = 500.00, so Testing is forecast to finish 500.00 under budget.