Sub topic 2
Classifying costs: direct, indirect, fixed, variable
This chapter assumes you can add, multiply, and calculate percentages. It also assumes you have labor hours and rates for each work package, plus a list of non-labor items such as licenses and hosting.
Classifying costs: direct, indirect, fixed, variable
Sort each cost on two separate axes. A direct cost is charged to one work package, such as developer hours on Development. An indirect cost supports the whole project, such as shared project management or office space. A fixed cost stays the same regardless of how much work is done, such as a software license. A variable cost changes with the work, such as hours billed by a contractor.
Every cost gets one label on each axis. Contractor hours are direct and variable. Shared hosting is indirect and fixed.
Adding a contingency reserve
A contingency reserve is money set aside for risks you expect but cannot price exactly. A common starting rate is 10% of direct costs. Calculate it once, on direct costs only.
Assembling the budget total
Add labor, non-labor costs, and contingency:
tasks = {"Design": (40, 80.0), "Development": (120, 90.0), "Testing": (50, 70.0)}
non_labor = {"Software licenses": 1200.0, "Hosting": 600.0}
contingency_rate = 0.10
labor = sum(hours * rate for hours, rate in tasks.values())
direct = labor + sum(non_labor.values())
contingency = direct * contingency_rate
budget = direct + contingency
print(f"Labor: {labor:.2f}")
print(f"Direct: {direct:.2f}")
print(f"Contingency: {contingency:.2f}")
print(f"Budget: {budget:.2f}")The output is a labor cost of 17500.00, direct costs of 19300.00, contingency of 1930.00, and a budget of 21230.00.
Spreading the budget over time
Divide the total across periods to create the baseline, the approved plan you measure against. Show the running total as well, which is the cash-flow view.
| Month | Planned spend | Cumulative |
|---|---|---|
| 1 | 7000.00 | 7000.00 |
| 2 | 8000.00 | 15000.00 |
| 3 | 6230.00 | 21230.00 |
Recording actual costs
At the end of each period, record what you spent on each work package. Compare the cumulative actuals with the cumulative baseline for the same period. Keep actuals separate from the baseline so the original plan stays visible.
Exercise
Direct costs are 8000.00 and contingency is 10%. What is the budget total?
Show answer
Contingency is 800.00, so the budget is 8800.00.