Sub topic 8
Keeping the Matrix Current and Shared
This chapter assumes you can read a RACI matrix, know the four roles, and follow the rule that every task has exactly one Accountable owner. You should also have built and validated a matrix as covered in earlier chapters. Here the focus is on what happens afterward: a matrix that was correct in week one is usually wrong by month three, and a matrix nobody can find is no better than one that was never written.
Why a matrix decays
A RACI matrix describes a project at one moment. The project then changes in ways that quietly invalidate it:
- Scope changes. New deliverables appear and have no row. Cancelled ones stay on the sheet and confuse people.
- People move. Someone changes roles, leaves, goes on leave, or is replaced by a contractor. The cell still says "A" but the person is gone.
- Roles are reorganised. A team splits, two roles merge, or a job title changes. Columns no longer match how people talk about the work.
- Habits drift. People begin doing work that the matrix assigns to someone else. The matrix says one thing and the project does another.
A stale matrix is worse than none. People trust it, send approvals to the wrong person, and skip the people who should have been consulted. Maintenance is therefore part of the matrix's purpose and not an optional extra.
Decide who owns the matrix itself
The matrix needs an owner, and the same single-owner rule applies to it. Pick one person, usually the project manager, who is accountable for the document being accurate. That person does not decide every cell. They make sure changes are recorded, validated, and communicated.
You can put this in the matrix as a row:
| Task | Project manager | Product owner | Team leads | Sponsor |
|-------------------------|-----------------|---------------|------------|---------|
| Maintain RACI matrix | A/R | C | C | I |
| Approve scope changes | R | C | C | A |Two details matter here. The project manager owns the document, but the sponsor remains accountable for approving scope changes, because changing scope is a different decision from recording it. And the product owner and team leads are Consulted, since they know what people actually do.
Triggers for a review
Waiting until someone notices a problem is slow. Define the events that force a review, and add a regular calendar check as a backstop.
| Trigger | What to check |
|---|---|
| A change request is approved | New or removed rows; changed Accountable owners |
| Someone joins, leaves, or changes role | Every cell in that person's column |
| A phase ends and another begins | Whether the tasks and roles of the new phase match the old rows |
| An escalation reveals confusion about ownership | The rows involved in the dispute |
| A fixed interval passes (for example, each sprint or each month) | The whole matrix, quickly, using the validation checks |
The last row is the safety net. Even if nothing seems to have changed, a 15-minute scan at a fixed interval catches drift that no one reported.
A change process that stays light
The process does not need to be heavy. A short, repeatable loop is enough.
The steps in more detail:
- Draft the change. Edit a copy, not the live document. Change only the rows and columns the trigger affects.
- Validate. Run the same checks you used when you first built the matrix: exactly one Accountable per task, at least one Responsible, and no overloaded roles. Handover is where errors sneak in, such as two people briefly marked "A" for the same task.
- Confirm. The Accountable owner of each affected task should agree to the change. Someone who finds out they are accountable by reading a shared document has not really accepted the role.
- Publish with a change note. Say what changed, why, and when it takes effect.
- Acknowledge. Affected people confirm that they have read it. This can be a thumbs-up reaction or a reply, as long as it is recorded.
Version the matrix
Give each published version an identifier and keep a short history. You do not need a tool for this. A table at the bottom of the document works:
| Version | Date | Change | Approved by |
|---------|------------|-----------------------------------------------------|-------------|
| 1.0 | 2026-03-02 | First version after kickoff | Sponsor |
| 1.1 | 2026-04-14 | Added QA engineer; moved "Build feature" R to QA | Product owner |
| 1.2 | 2026-05-20 | New task "Run user training" added after scope change | Sponsor |The history answers a question that comes up in every dispute: "Who was accountable on the date this happened?" Without it, you can only say who is accountable now.
If the matrix lives in a spreadsheet or wiki, use the built-in page history as well, but still write the change note by hand. Automatic history shows what cells changed. It does not explain why.
Detecting changes with a script (optional)
If your matrix is kept as data, you can compare two versions automatically and paste the result into the change note. The script below holds the matrix as a dictionary of tasks to roles, as in the validation chapter. It combines the validation function with a function that lists differences between two versions.
def validate_raci(matrix):
problems = []
for task, roles in matrix.items():
codes = list(roles.values())
accountable = sum('A' in c for c in codes)
responsible = sum('R' in c for c in codes)
if accountable != 1:
problems.append(f'{task}: expected 1 Accountable, found {accountable}')
if responsible < 1:
problems.append(f'{task}: no one is Responsible')
return problems
def diff_raci(old, new):
changes = []
for task in sorted(set(old) | set(new)):
if task not in new:
changes.append(f'Removed task: {task}')
continue
if task not in old:
changes.append(f'Added task: {task}')
continue
for role in sorted(set(old[task]) | set(new[task])):
before = old[task].get(role, '-')
after = new[task].get(role, '-')
if before != after:
changes.append(f'{task} / {role}: {before} -> {after}')
return changes
old = {
'Write requirements': {'Product owner': 'A', 'Business analyst': 'R', 'Developer': 'C'},
'Build feature': {'Product owner': 'C', 'Developer': 'A/R', 'Sponsor': 'I'},
}
new = {
'Write requirements': {'Product owner': 'A', 'Business analyst': 'R', 'Developer': 'C'},
'Build feature': {'Product owner': 'C', 'Developer': 'A', 'QA engineer': 'R', 'Sponsor': 'I'},
'Run user training': {'Product owner': 'A', 'Trainer': 'R'},
}
problems = validate_raci(new)
if problems:
print('Fix before publishing:')
for problem in problems:
print(' -', problem)
else:
print('Validation passed.')
for change in diff_raci(old, new):
print(change)
# Validation passed.
# Build feature / Developer: A/R -> A
# Build feature / QA engineer: - -> R
# Added task: Run user trainingThe diff shows why the change note matters. It reports that the developer went from "A/R" to "A", but only a person can add why: the team added a QA engineer to do the testing work. The script saves you from missing a cell. It cannot supply the reason.
Handing over when a person leaves
Personnel changes are the most common cause of broken matrices, so handle them explicitly. A handover has three parts:
- Find every cell. Scan the person's column, or the roles they filled, for all four letters. Accountable and Responsible cells need a new owner. Consulted and Informed cells need a decision too: does the replacement still need to be in the loop?
- Assign Accountable first. If the departing person was the only Accountable owner for a task, no one is accountable until you name a successor. Do this before the person's last day. For short absences, name an acting owner and write the end date next to it.
- Check the load. The replacement may already be heavily loaded. Moving a departing person's tasks to a colleague can push that colleague into too many R and A cells. Re-run the overload check after the handover, not before.
Where a task is shared between a departing and an arriving person, use a handover period in which both are named in the change note, but keep only one "A" in the matrix at any time. Overlap in work is fine. Overlap in accountability is the failure the matrix exists to prevent.
Reflect reality, not the plan
A matrix that records intentions can drift from practice without anyone saying so. Watch for these signs:
- A person marked "I" is regularly making decisions that should belong to the Accountable owner.
- A task marked "R" for one person is routinely finished by another.
- Approvals come from someone who has no "A" in the matrix.
- People ask in chat "who owns this?" about a row that already has an owner.
When you see one of these, do not just correct the practice. Ask which one is wrong. Sometimes the matrix is right and the person needs reminding. Sometimes the person is doing the work better than the plan allowed, and the matrix should be updated to match. The decision belongs to the Accountable owner of the task and, for changes in who is accountable, to whoever approves scope and role changes in your project.
Sharing the matrix
A correct matrix does nothing if people cannot find it or do not understand it. Three decisions shape how well it is shared.
One source of truth
Keep one canonical copy in a place everyone on the project can open without asking permission, such as the project wiki, shared drive, or the top of the tracker. Other places should link to it, not copy it. Copies in slide decks and emails go stale on the day they are made. If a copy has to exist, such as an export for a steering committee, stamp it with the version number and date so a reader can tell whether it is current.
Access that matches the audience
Everyone on the project should be able to read the matrix. Only a small group, normally the project manager and a deputy, should be able to edit it. Open editing invites silent changes that nobody validated. Read-only access with a clear process for requesting changes keeps the document trustworthy.
Tell people what applies to them
A full matrix can be dense, especially with many tasks. Not everyone needs the whole picture. Consider these ways to help people find their own part:
- A personal summary. For each person, list the tasks where they have an A or R, then the tasks where they are C or I. A short message such as "You are accountable for these three tasks and consulted on these five" is easier to act on than a grid.
- Filtered views. In a spreadsheet, save a view per role or per workstream.
- Short role notes. Add a line to each column: who holds the role now, and who is the backup.
What to say in a change note
A good change note is short and gives the reader everything needed to act. Include:
- The version number and effective date.
- Which tasks and roles changed, listed by name.
- Who is newly accountable or responsible, and who is no longer.
- The reason, in one sentence.
- Who approved it.
- Who to contact with questions.
For example:
**RACI v1.2, effective 2026-05-20**
- Added task "Run user training". Accountable: Product owner. Responsible: Trainer.
- "Build feature": Developer is now Accountable only. QA engineer is Responsible for testing.
- Reason: scope change CR-14 added a training deliverable, and testing moved to the new QA role.
- Approved by: Sponsor.
- Questions: project manager.Notice that each line names a role and a task. A reader who is not affected can skip it in seconds. A reader who is affected knows exactly what to do next.
Common maintenance mistakes
| Mistake | Effect | Fix |
|---|---|---|
| Editing the live matrix without validation | Two "A" cells or an unowned task go live | Edit a copy, validate, then publish |
| No change note | People learn of changes by accident or not at all | Write a short note for every published version |
| Several copies in circulation | Different people follow different versions | Keep one source and link to it |
| Updating only after a dispute | Confusion persists until it hurts | Define triggers and a fixed review interval |
| Removing a task's row when it is cancelled | History is lost and no one knows if it was done | Mark it "Cancelled" in a note and keep it in the version history |
| Reassigning without telling the new owner | Ownership exists only on paper | Get acknowledgement from the new Accountable and Responsible people |
| Letting everyone edit | Silent changes bypass approval | Restrict edit rights and use a request process |
Putting it together
When a change arrives, work through this checklist:
- Identify the trigger and the rows and columns it touches.
- Draft the change on a copy.
- Validate: one Accountable per task, at least one Responsible, no overloaded role.
- Get confirmation from the Accountable owners of affected tasks, and approval from whoever owns scope and role decisions.
- Publish one new version in the single canonical location, with a change note.
- Collect acknowledgement from people whose A or R assignments changed.
- Add the entry to the version history.
Done consistently, this takes a few minutes per change. The cost of skipping it is paid later, when a deadline slips and no one can say who was accountable.
Exercise
A developer who is marked "A/R" for "Build feature" resigns. Their replacement starts in two weeks, and in the meantime the product owner will cover. Describe the changes you make to the matrix and the checks you run before publishing.
Show answer
Name an acting Accountable owner now, the product owner, and note the end date, so the task is never without an A. Name an acting Responsible person or team for the hands-on work, or record that work is paused. Keep exactly one "A" on the task during the overlap. When the replacement starts, move "A/R" to them in a second version. Before each publication, run the validation check (one Accountable, at least one Responsible) and re-check the product owner's load, since they now hold extra assignments. Write a change note with the effective dates and the reason, get the product owner to acknowledge the temporary assignment, and record both versions in the history.
Exercise
You compare version 1.1 and version 1.2 of a matrix and see that "Approve release" now has "A" for both the sponsor and the product owner. Name two ways this could have happened and what you do.
Show answer
Either someone edited the live matrix without validation, or a handover added the new owner before removing the old one. Roll back to the last valid version or edit a copy so the task has one "A". Ask the people involved who should be accountable, with the sponsor or the scope approver deciding if they disagree. Then run validation, publish a corrected version with a change note, and restrict editing so changes go through the review loop.
Exercise
Why should a change note include the reason for a change, even if a script or the document's page history already shows exactly which cells changed?
Show answer
The history shows what changed but not why. The reason helps later readers judge whether the change still applies, and it settles later disputes about who was accountable and on what basis. It also lets affected people see that the change followed a decision, such as a scope change, and not an arbitrary edit.