Sub topic 5
Building a Matrix from a Task List
This chapter turns a loose list of project work into a complete RACI matrix. It assumes you know the four roles (Responsible, Accountable, Consulted, Informed) and the rule that each task has exactly one Accountable owner. You should also be comfortable reading a table or spreadsheet and have worked on a project with more than one team. Checking and maintaining the finished matrix are covered in later chapters. Here the goal is a first draft that is complete and defensible.
The build process at a glance
Building a matrix is a sequence of decisions, and the order matters. Assigning Accountable owners before anything else keeps the matrix from filling up with Responsible and Consulted marks that nobody has ever agreed to.
Step 1: Write the task list
The rows of the matrix are tasks or deliverables. The quality of the matrix depends on how you word and size them.
Choose a consistent granularity
If one row says "Launch product" and another says "Rename a database column", the matrix mixes strategic and operational work. Pick one level and stay there. A workable rule is to make each row something that:
- has a clear finish, so you can say whether it is done;
- can be owned by one role;
- takes more than a trivial amount of effort, or is a decision that other work depends on.
For a project of ten to fifty people, 15 to 40 rows is typical. Fewer than 10 rows usually means the tasks are too coarse to settle anything. More than 50 rows is hard to read, so split it into one matrix per workstream.
Word tasks as a verb plus an object
"Testing" is a topic. "Run user acceptance tests" is a task. Use the verb and object form so the row has a clear finish. Decisions and approvals deserve their own rows, because they are where Accountability is most often left vague. "Approve release" and "Approve budget" are better rows than a single "Manage release".
Pull tasks from existing documents
Do not invent the list from memory. Good sources are:
- the work breakdown structure or backlog;
- the project charter's deliverables;
- the milestone plan;
- recurring obligations, such as status reporting, risk review, and change control.
Recurring obligations are the tasks teams most often forget, and they are often the ones that fail when someone is on leave.
Step 2: List the roles, not the names
The columns are roles such as Product owner, Developer, or Sponsor. Roles keep the matrix stable when people join, leave, or swap duties. You can add a separate lookup table that maps each role to a current person.
Two edge cases come up here:
- One person holds several roles. On a small team, one person may be both Product owner and Business analyst. Keep two columns if the work differs. Merge them only if the person truly acts as one role.
- A role is filled by a group. "The developers" is acceptable as a column for work done by a team. It is not acceptable as the Accountable owner, because a group cannot answer for a result. Name one lead role, such as Tech lead, as Accountable and let the group be Responsible.
Keep the number of columns small. More than about eight or nine roles makes the grid hard to scan. If you have more, group minor stakeholders under one column such as "Operations" or "Legal and compliance".
Step 3: Draw the grid
Put tasks down the left side and roles across the top. Leave every cell empty. A blank cell means "not involved", which is a valid and common state. The next steps fill the grid in a fixed order.
Step 4: Assign the Accountable owner first
For each row, ask: if this task fails or is late, which one role answers for it? Write A in that cell. Do this for the entire list before you assign anything else.
Useful tests for choosing the Accountable role:
- It has the authority to approve or reject the result.
- It has the authority to reassign the work or ask for resources.
- It is the role the sponsor would call first if the result were bad.
If two roles seem equally accountable, the task is probably two tasks. "Approve budget and release funds" can split into "Approve budget" (Sponsor) and "Release funds" (Finance lead). If the task really is one unit, pick the role with the higher authority and make the other role Consulted.
Step 5: Assign Responsible
Now find who does the work. A task needs at least one Responsible role, and it may have several if the work is split. Three cases cover most rows:
- The Accountable role also does the work. Write
A/Rin a single cell. This is common for small tasks. It is not an error, as long as the cell holds one role. - Someone else does the work. Write
Rin their cell. The Accountable role oversees and signs off. - The work is shared. Mark each doer
R. If more than three roles are Responsible, check whether the task needs splitting, because large Responsible groups usually mean unclear task boundaries.
Look at the A/R marks in aggregate. A matrix where nearly every row is A/R for the same role says that one role owns everything, which is a staffing problem and not a documentation problem.
Step 6: Add Consulted and Informed, sparingly
Consulted (C) means two-way communication before a decision or completion. Informed (I) means one-way communication afterward. Add them last because they are the easiest marks to over-assign.
Apply a filter to every candidate mark:
- Add
Conly if the task would be worse without that role's input, or if the role has a veto over some aspect (security review, legal review). - Add
Ionly if the role has to change its own behavior based on the result.
"They might want to know" is not a reason. Each extra C adds a wait or a meeting, and each extra I adds a message that people learn to ignore. A rough guide is that most rows should have one A, one or two R, zero to three C, and zero to three I.
Worked example
Here is the starting matrix from the spine. Read each row for the story it tells.
| Task | Product owner | Business analyst | Developer | Sponsor |
|---------------------|---------------|------------------|-----------|---------|
| Write requirements | A | R | C | I |
| Build feature | C | C | A/R | I |
| Approve release | R | I | C | A |- Write requirements. The Product owner answers for the requirements, the Business analyst writes them, and the Developer is consulted on feasibility. The Sponsor only needs to know they exist.
- Build feature. The Developer is both Accountable and Responsible (
A/R). The Product owner and Business analyst are consulted on questions about intent. - Approve release. The Sponsor is Accountable, because approval is a decision with business consequences. The Product owner prepares the release package, so it is
Rand notA.
Notice that the Product owner has an A in one row, an R in another, and a C in the third. That mix is normal. The Accountable column is not reserved for a single person across the whole matrix.
Building a skeleton in code
If your task list lives in a script or export, you can generate the blank grid and a Markdown table from it. This script builds the grid, fills in some assignments, prints the table, and lists tasks that still have no Accountable owner.
def blank_matrix(tasks, roles):
return {task: {role: '' for role in roles} for task in tasks}
def assign(matrix, task, role, code):
if task not in matrix:
raise KeyError(f'Unknown task: {task}')
if role not in matrix[task]:
raise KeyError(f'Unknown role: {role}')
matrix[task][role] = code
def to_markdown(matrix):
roles = list(next(iter(matrix.values())))
header = ['Task'] + roles
lines = [
'| ' + ' | '.join(header) + ' |',
'|' + '|'.join('---' for _ in header) + '|',
]
for task, cells in matrix.items():
row = [task] + [cells[role] for role in roles]
lines.append('| ' + ' | '.join(row) + ' |')
return '\n'.join(lines)
def missing_accountable(matrix):
return [
task for task, cells in matrix.items()
if not any('A' in code for code in cells.values())
]
tasks = ['Write requirements', 'Build feature', 'Approve release']
roles = ['Product owner', 'Business analyst', 'Developer', 'Sponsor']
matrix = blank_matrix(tasks, roles)
assign(matrix, 'Write requirements', 'Product owner', 'A')
assign(matrix, 'Write requirements', 'Business analyst', 'R')
assign(matrix, 'Write requirements', 'Developer', 'C')
assign(matrix, 'Write requirements', 'Sponsor', 'I')
assign(matrix, 'Build feature', 'Developer', 'A/R')
assign(matrix, 'Build feature', 'Sponsor', 'I')
assign(matrix, 'Approve release', 'Sponsor', 'I')
print(to_markdown(matrix))
print('Missing Accountable:', missing_accountable(matrix))
# Missing Accountable: ['Approve release']Two design choices are worth noting. assign raises an error on an unknown task or role, so a typo in a name cannot silently create a new row or column. And missing_accountable checks for completeness only. It does not catch two A marks on one row. The full validator, which also flags a missing Responsible role, is the subject of the next chapter.
Step 7: Review rows and columns
Read the finished grid in two directions before you share it.
Read each row
A row is healthy when:
- it has exactly one
A; - it has at least one
R, which may be the same cell as theA; - the
Cmarks each have a stated reason; - no role appears with two letters other than
A/R.
Read each column
A column shows the load on one role. Count the A and R marks in each column and look for:
- A role that is overloaded. If one role is
AorRon a large share of rows, it will become a bottleneck. Redistribute work or add capacity. - A role that is empty. A column with no marks means the role has no stated purpose in this project. Either remove it or find the tasks you missed.
- A role that is only
CandI. This is fine for advisors, but it is a warning sign for a role that you expected to do work.
The table below shows how to interpret common column patterns.
| Column pattern | Likely meaning | Typical fix |
|---|---|---|
| Many `A` and `R`, few blanks | Bottleneck or hero role | Delegate `R` to another role; split the role |
| Only `I` marks | Stakeholder with no real duties | Merge into a group column or drop |
| Many `C` marks | Role consulted on everything, which slows decisions | Limit to tasks where the role has a veto or unique knowledge |
| All blank | Role is missing from the plan, or tasks are missing | Confirm the role is needed and add the tasks |
Edge cases when building
Cross-team tasks. When work spans two departments, assign A to the role that owns the outcome, even if most of the effort is on the other team. The other team's lead is R. Do not give each team its own A.
External vendors. A vendor can be Responsible for delivery. It should not be Accountable, because your organization cannot hold an outside party accountable in the same way. Name an internal role, such as Vendor manager, as A, so that someone inside the project answers for the result.
Recurring tasks. For status reports, risk reviews, and similar work, one row is enough. Do not create a row per occurrence.
Phased projects. If the owner of a task changes by phase (for example, the Business analyst owns design in phase one and the Developer owns it in phase two), build one matrix per phase, or split the task into two rows. Do not mark both roles A for the same row.
Approvals with a committee. If a change board approves releases, the board is not a person. Make its chair the Accountable role, or use a role called "Change board chair", and list board members as C.
Tasks with no obvious owner. If you cannot identify an A after a real attempt, you have found a governance gap. Do not write a placeholder. Escalate to the sponsor and record the decision.
Common mistakes while building
- Assigning
RbeforeA. The doers fill the grid and theAcolumn becomes an afterthought. Always placeAfirst. - Marking everyone
Cto be safe. This turns the matrix into a meeting list. Apply the filter from Step 6. - Using names in column headers. The matrix then goes out of date at the first reorganization.
- Writing vague task names. "Documentation" cannot be checked. "Publish API reference" can.
- Mixing levels. A row for "Deliver project" next to a row for "Update the readme" makes the matrix inconsistent. Keep rows at one level.
- Leaving out decisions. Teams often list the work but not the approvals. Add rows for the decisions that block other work.
Putting it together
A practical sequence for a first draft:
- Export tasks from your plan and reword each as a verb plus an object.
- Merge or split rows until they are at one level.
- List the roles, and map each to a current person in a separate table.
- Assign every
A. Stop and resolve any row where you cannot choose one. - Assign
R, usingA/Rwhere the same role does the work. - Add
CandIusing the filters. - Read the rows, then the columns. Fix, then repeat.
- Review with each Accountable owner before sharing.
The review in step 8 is where most of the disagreement surfaces. Better to find it in a meeting than in the middle of a delayed delivery.
Exercise
You are building a matrix for a website redesign. The row "Approve homepage design" currently has A for both the Marketing lead and the Design lead. The Design lead produces the design, and the Marketing lead decides whether it meets the brand goals. How do you fix the row?
Show answer
A task can have only one Accountable owner. Choose the role that has the authority to approve the result, which is the Marketing lead because it judges the design against brand goals. Mark Marketing lead A. Mark Design lead R, since that role produces the design. If the Marketing lead also needs input from others, such as Legal, add them as C. If you find both approval and production are really separate decisions, you can split the row into "Produce homepage design" (Design lead A/R) and "Approve homepage design" (Marketing lead A).
Exercise
After building a matrix, you count marks per column. The Tech lead has A or R on 22 of 30 rows, the QA engineer has only I marks, and the Legal column is empty. What does each pattern suggest, and what would you check?
Show answer
The Tech lead is likely a bottleneck, so check which R marks could move to other roles or whether the role needs to be split. The QA engineer with only I marks is suspicious, because testing tasks such as "Run regression tests" may be missing or mislabeled, so review the task list for quality work. The empty Legal column means either Legal is not needed (remove the column) or tasks such as "Review data-processing terms" were left out (add the rows and assign C or A). Confirm each finding with the people involved before changing the matrix.
Exercise
A vendor will build the payment integration. Which role should be Accountable for the row "Deliver payment integration", and why?
Show answer
An internal role, such as the Vendor manager or Tech lead, should be Accountable. The vendor is Responsible for the work, but your organization needs someone inside the project who answers for the outcome, manages the contract, and can escalate. Marking the vendor A leaves no internal owner.