Reporting progress and revising objectives
This chapter covers what happens after you have written a measurable objective: tracking it, reporting on it and deciding when to change it. It assumes you can write an objective with a metric, baseline, target and deadline, and that you know the difference between outputs, outtakes and outcomes. It also assumes you are comfortable with percentages. An objective only helps if someone checks it against data while there is still time to act.
What a progress report is for
A progress report answers three questions for the people who fund and direct the work:
- Where are we against the objective?
- Why is the number moving, or not moving?
- What do we do next?
Many PR reports answer a different question: "What did we do?" That list of clippings, posts and events describes activity. It is useful as supporting detail, but it does not show whether the audience changed. Lead with the objective's own metric and put the activity underneath it.
A useful report has these parts, in this order:
- The objective, restated in one line, so readers do not need to look it up.
- The headline number: baseline, current value, target and deadline.
- Progress and pace: how much of the planned change has happened and how much time has passed.
- Leading indicators: outputs and outtakes that suggest whether the outcome will move.
- Explanation and risks: what is helping, what is hurting, and what you do not know.
- A decision request or recommendation: continue, change tactics, or revise the objective.
Report at each results level
Outputs, outtakes and outcomes move at different speeds, so they need different reporting rhythms. Outputs such as published articles are visible within days. Outcomes such as changed awareness or behavior usually show up only when you re-measure, which may be once a quarter.
| Level | Example metric | Typical check | What it tells you |
|---|---|---|---|
| Output | Articles in target outlets | Weekly | Whether the work is being delivered |
| Outtake | Message recall among people reached | Monthly or per campaign | Whether the audience received and understood the message |
| Outcome | Unaided awareness among IT managers | Each survey wave | Whether the audience changed |
| Impact | Trial sign-ups attributed to the campaign | Quarterly, with finance or sales | Whether the organizational goal moved |
Report the outcome as the main result, even if it only updates quarterly. Between waves, say plainly that the outcome figure is unchanged because no new measurement exists. Do not fill the gap with output counts presented as results.
Calculating progress and pace
Progress is the change achieved so far divided by the change planned. Pace is the share of the time window that has elapsed. Comparing the two shows whether you are ahead or behind.
Take the objective from earlier chapters: raise unaided awareness from 12% to 20% by 30 September 2027. The baseline survey ran on 31 March 2027, and the June wave reads 14%.
from datetime import date
def progress(baseline, current, target):
"""Share of the planned change achieved so far."""
return (current - baseline) / (target - baseline)
def time_elapsed(start, today, deadline):
"""Share of the time window that has passed."""
return (today - start).days / (deadline - start).days
def status(done, elapsed, on_track_gap=0.10, at_risk_gap=0.25):
"""Compare progress with elapsed time using a simple straight-line pace."""
if done >= 1:
return "met"
if done >= elapsed - on_track_gap:
return "on track"
if done >= elapsed - at_risk_gap:
return "at risk"
return "off track"
done = progress(baseline=0.12, current=0.14, target=0.20)
elapsed = time_elapsed(date(2027, 3, 31), date(2027, 6, 30), date(2027, 9, 30))
print(f"progress {done:.2f}, time elapsed {elapsed:.2f}, status: {status(done, elapsed)}")Running it prints progress 0.25, time elapsed 0.50, status: at risk. A quarter of the planned change has happened in half the time.
Limits of the straight-line check
The status function assumes steady progress. Real PR effects often do not behave that way. A product launch, a crisis or a seasonal event can move awareness in one jump. Awareness built through media coverage also lags: people see the coverage in May and the survey picks up the effect in July. Treat the status label as a prompt for discussion, not a verdict. Set the thresholds (here 10 and 25 percentage points of the plan) with your team, and write them in the report.
Reading survey numbers with care
Outcome metrics from surveys carry sampling error. If the June wave samples 400 people, a reading of 14% could plausibly reflect a true value a few points higher or lower. A move from 12% to 14% may therefore be partly noise.
- State the sample size and margin of error beside every survey figure.
- Do not call a 1- or 2-point move a trend unless it exceeds the margin of error or repeats across waves.
- Keep the questionnaire, sampling method and audience definition identical across waves. If any of these change, the new figure cannot be compared with the baseline, and you should say so.
Explaining the movement
A number without a reason invites guesses. For each outcome metric, offer a short explanation and mark how confident you are.
- What you can support: for example, "Recall of the key message is 38% among people exposed to the trade-press series, against 15% among those who were not."
- What you suspect: "The June rise may be linked to the conference keynote; the survey did not ask where respondents heard of us."
- What you do not know: "A competitor's price cut in May may have drawn attention to the category."
This keeps the report honest about attribution. PR rarely acts alone. Advertising, sales, seasonality and competitors also affect the same metric. Use comparison groups, exposed versus unexposed audiences, and dated events where you can, and say clearly when the evidence shows association and not cause.
The review loop
Reporting is part of a cycle. Each measurement either confirms the plan or triggers a decision.
When to change tactics and when to revise the objective
Most shortfalls call for changing tactics, not the objective. If awareness is behind pace, you might shift spending toward outlets your audience reads, or adjust the message. The objective stays fixed because it reflects what the organization needs.
Revise the objective only when one of these holds:
- The organizational goal changed. The company drops the small-business segment, so the audience in the objective no longer matters.
- The baseline or measure was wrong. You find the baseline sample did not match the audience definition.
- An external event changed what is feasible. A merger, a recall or a market shift makes the original target unrealistic or too modest.
- The target was set without evidence. The first quarter's data shows how fast the metric can really move, and the original target ignored it.
Do not revise the objective only because you are behind. Lowering a target after a poor result, or swapping to a metric that looks better, is moving the goalposts. It destroys the report's credibility and hides the lesson.
Keep a revision log
Record every change. Keep the original objective, add a dated entry and state the reason. This preserves the audit trail and lets readers see that the revision followed evidence and not disappointment.
objective:
organizational_goal: Grow trial sign-ups from small businesses
audience: Owners of businesses with 10 to 50 employees
level: outcome
metric: Share of survey respondents who can name the product unaided
baseline: 0.12
target: 0.20
deadline: 2027-09-30
data_source: Quarterly brand survey, same questionnaire and sampling each wave
owner: Head of Communications
revisions:
- date: 2027-07-15
changed: audience
from: Owners of businesses with 10 to 50 employees
to: Owners of businesses with 10 to 25 employees
reason: Sales stopped pursuing 26 to 50 employee accounts from 1 July
new_baseline: 0.11
new_baseline_source: Re-cut of the March wave for the narrower audience
approved_by: Chief Marketing OfficerThe log shows the revised baseline, which is re-cut from the existing data. If you change the audience or metric, the old baseline and target no longer apply. Re-establish them before you report progress against the new objective.
Common errors in reporting and revising
- Reporting activity as progress. Clip counts and impressions answer "how busy were we?", not "did the audience change?".
- Reporting only good news. Showing the metric that improved and omitting the one that did not weakens trust in every later report.
- Comparing unlike measurements. A new questionnaire, a different sample or a redefined audience breaks the comparison with the baseline.
- Over-reading small moves. Ignoring sampling error turns noise into a story.
- Revising silently. An undocumented change to the target or deadline looks like manipulation even when the reason was sound.
- Waiting for the deadline. A report at the end only records failure. Mid-course checks leave time to act.
Exercise
Your objective is to raise unaided awareness from 20% to 30% by 31 December. Halfway through the period the survey reads 23%. Calculate progress and say what you would tell the executive team, including one caution about the number.
Show answer
Progress is (23 - 20) / (30 - 20) = 0.30, so 30% of the planned change has happened with about 50% of the time gone. That is behind a straight-line pace but not necessarily failing. Report it as "at risk" or "behind pace" using the thresholds you agreed in advance, and recommend a change of tactics. A caution: a 3-point move may be within the survey's margin of error, and awareness often lags coverage, so say so and re-check at the next wave. Do not lower the target yet, because nothing about the organizational goal has changed.
Exercise
A communications manager is behind on a target of 5,000 trial sign-ups and proposes replacing the objective with "increase social media followers by 20%". Is this a legitimate revision? What would make a revision legitimate, and what should be recorded?
Show answer
It is not legitimate. Followers is an output-level or vanity metric, and swapping to it only because it is easier to hit is moving the goalposts. A legitimate revision follows a change in the organizational goal, a flawed baseline or measure, or an external event that changes what is feasible. The revision log should record the date, what changed, the old and new values, the reason, the new baseline and its source, and who approved it.