Recording Dependencies and Constraints
Assume you understand the roles of design, engineering, art, audio, and QA, and that a feature spec already has a clear design intent and scope. This chapter focuses on the conditions that can affect whether the team can build the feature as planned.
A dependency is something the feature needs from another system, discipline, or piece of work. A constraint is a limit the feature must obey. For example, a dash ability may depend on an animation set and be constrained by the player controller’s movement model.
Why these sections matter
Unrecorded dependencies create surprises late in production. Engineering may discover that a required event does not exist. Animation may learn that the feature needs three new poses. QA may not know that the feature only works after another system is enabled.
Record each dependency with:
- What the feature needs.
- Who owns or provides it.
- Its current status.
- What happens if it is late or unavailable.
Record each constraint with:
- The rule or limit.
- Why it exists.
- How the team can verify it.
- Whether it is fixed or negotiable.
A practical dependency map
Consider a dash feature:
The map does not replace the written spec. It helps reviewers see missing work and risky connections.
A dependency table makes ownership visible:
| Dependency or constraint | Owner | Status | Effect if unresolved |
|---|---|---|---|
| Movement controller exposes dash velocity | Engineering | In progress | Dash cannot move correctly |
| Dash animation and transition | Animation | Not started | Use a temporary animation |
| One dash per jump is supported | Player movement design | Confirmed | Air-dash rule can be tested |
| Input action is available on all platforms | Technical design | Unknown | Control scheme may be incomplete |
Distinguish a dependency from a suggestion. “Use a screen effect” is a suggestion unless the feature cannot ship without it. Mark optional work as such so the team can scope it without confusion.
Constraints and fallback plans
Constraints often come from technology, schedule, platform, accessibility, or content budgets. State the impact instead of listing vague warnings.
For example:
- The feature must work at 30 frames per second on the minimum console.
- The dash cannot pass through collision because the current movement controller performs swept collision checks.
- If the final animation is late, ship with the temporary animation and replace it before release candidate testing.
A fallback plan should preserve the core player experience. It should also identify who can approve using it.
>callout note > A dependency without an owner is a hidden task. A constraint without a reason is difficult to challenge or renegotiate.
Review before implementation
During review, ask:
- Can every dependency be assigned to a person or team?
- Does each unresolved dependency have a date, condition, or fallback?
- Are constraints testable rather than subjective?
- Does the proposed solution fit the existing architecture and platform limits?
- Which dependency creates the greatest schedule or technical risk?
Update this section when an assumption changes. Do not silently remove a dependency because the implementation found a workaround. Record the workaround so the spec remains useful to QA and future maintainers.
Exercise
The dash requires a new input action, but the input system cannot add actions until the next milestone. What should the spec record?
Show answer
Record the input action as a dependency owned by engineering, state the milestone constraint, describe the schedule impact, and provide a fallback such as a temporary existing binding.