Sub topic 8
Writing Risks and Issues
This chapter assumes you already know how to build the weekly report skeleton, report accomplishments, and assign an overall status. Here you will learn how to write the "Risks and issues" section so that a reader can judge how serious each item is, who is dealing with it, and whether they need to step in.
Risks and issues are different things
People often use the two words as if they meant the same thing. They do not, and mixing them up leads to weak entries.
- A risk is something that might happen and would hurt the project if it did. It has not happened yet. You describe it with a likelihood and an impact.
- An issue is something that has already happened and is hurting the project now. It needs action, not estimation.
A risk can turn into an issue. "The vendor may not approve our API access in time" is a risk. "The vendor has not approved our API access and testing is blocked" is an issue. When this happens, move the entry from the risk list to the issue list and rewrite it in the present tense.
| Row | Risk | Issue |
|---|---|---|
| Has it happened? | No, it might | Yes, it is happening now |
| Key question | How likely, and how bad? | How bad, and what is the fix? |
| Tense | Conditional ("could delay") | Present ("is delaying") |
| Typical response | Prevent or prepare | Resolve or work around |
The four parts of a good entry
The template in this tutorial gives each entry four fields: description, impact, owner, and mitigation. Each one answers a question the reader would otherwise have to ask you.
- Description: What is the situation? State the fact, and for a risk, state the trigger.
- Impact: What happens to scope, schedule, cost, or quality if this is not handled? Use numbers or dates where you can.
- Owner: Who is accountable for acting on it? One named person.
- Mitigation: What is being done, or what will be done? For a risk, this is how you reduce likelihood or impact. For an issue, it is the plan to resolve it or work around it.
Here is the pattern in the filled-in example from the template:
- Vendor API approval has not arrived (requested 3 weeks ago). Impact: launch slips one week for each further week of delay. Owner: Priya. Mitigation: escalated to the vendor account manager; testing continues against the sandbox.Notice what makes it work. The description gives a fact and a duration ("requested 3 weeks ago"). The impact is a rule the reader can calculate with ("one week for each further week"). The owner is one person. The mitigation names two concrete actions, one aimed at the cause and one that limits the damage.
Writing the description
Describe the situation in one or two sentences. Avoid vague labels such as "resourcing concerns" or "integration challenges". The reader cannot act on a label. Compare:
- Vague: "Some concerns about the test environment."
- Specific: "The shared test environment was down for 2 of 5 working days, so regression testing is 40% complete against a plan of 80%."
For a risk, include the trigger, which is the event or date that would turn it into an issue. "If the vendor has not approved access by 12 December, the integration cannot be tested before code freeze." A trigger tells the reader when to worry and tells you when to escalate.
Writing the impact
Impact is the part that most often goes missing. State the consequence in terms the reader cares about: dates, money, scope, quality, or customers affected.
- Weak: "This could affect the schedule."
- Strong: "Launch moves from 15 January to 29 January."
If you do not know the impact exactly, give a range and say so: "Between one and three weeks of delay, depending on when the vendor responds." A stated range with its cause is more useful than silence, and more honest than a precise number you invented.
For risks, you can add a rough likelihood: low, medium, or high. Keep the scale simple. Three levels are enough for a weekly report, and a detailed scoring matrix belongs in the project's risk register, not in the report.
Naming the owner
The owner is the person responsible for making sure something happens. That person might not do all the work. Rules for owners:
- Use one name, not a team or a pair. "Engineering" cannot be asked a follow-up question.
- Confirm the person agrees before you list them. A surprised owner is a sign the entry is not being managed.
- If the owner is the reader (for example, a sponsor must resolve it), say so under "Decisions and asks" as well. The next chapter covers this.
Writing the mitigation
A mitigation is an action, not a hope. "Monitor the situation" is not a mitigation unless it comes with what you monitor, how often, and what you do when it changes.
There are four common ways to respond to a risk:
| Response | Meaning | Example |
|---|---|---|
| Avoid | Change the plan so the risk cannot occur | Drop the dependency on the unapproved API for the first release |
| Reduce | Lower the likelihood or the impact | Build against the vendor sandbox so testing is not blocked |
| Transfer | Move the consequence to another party | Add a penalty clause or buy insurance |
| Accept | Do nothing now, and agree to live with the result | Accept a possible one-day slip in a low-value task |
If you accept a risk, say that you accepted it and who agreed. Silent acceptance looks the same as neglect.
For an issue, the mitigation is a recovery plan. Include the next step and a date: "Priya will call the vendor on Monday; if no answer by Wednesday, the sponsor will email their executive contact."
A complete example
This entry set belongs to the same project as the earlier example. It shows one issue and two risks, each with all four fields.
## Risks and issues
### Issues
- **Payment vendor API approval is late.** Requested 3 weeks ago, still pending. Impact: launch slips one week for each further week of delay; current launch date is 15 January. Owner: Priya. Mitigation: escalated to the vendor account manager on Tuesday; testing continues against the sandbox. Next check: Monday.
### Risks
- **Single developer knows the checkout module (likelihood: medium).** If Sam is unavailable for more than a week, checkout bug fixes stop. Impact: up to 2 weeks of delay in beta fixes. Owner: Marta. Mitigation: Sam is pairing with Lee for two sessions this week to share knowledge.
- **Staging data may not match production volumes (likelihood: low).** Performance problems could appear only after launch. Impact: possible emergency fixes in the first week after release. Owner: Jo. Mitigation: load test scheduled for the week of 5 December.Grouping issues above risks helps the reader, because issues are happening now and need attention first.
How many items to include
A weekly report is not the full register. Include only items a reader needs to know about this week.
- Include every open issue that affects a milestone, the budget, or a commitment.
- Include risks that are high impact, have rising likelihood, or have a trigger date approaching.
- Leave out low-level items that your team handles routinely. Keep them in the task tracker.
- Aim for roughly three to seven entries. A list of fifteen makes the important three hard to find.
Keep the full risk register as a separate document and link to it from the report. Each week, review it and promote or demote items to the report.
Keeping entries current
An entry that sits unchanged for six weeks tells the reader something is wrong, either with the item or with your attention to it. Each week, for every entry, ask:
- Has the likelihood or impact changed? Say how, for example "now high (was medium)".
- Did the mitigation work? If not, replace it.
- Has the item been resolved or has it expired? Report it as closed once, then remove it.
- Is it a new item? Mark it "New" so the reader notices.
Marking changes lets a reader who skims the report see movement without rereading everything.
Common mistakes
- Reporting a risk as an issue, or the reverse. If it has not happened, it is a risk. Using the wrong label hides how urgent the item is.
- No impact stated. The reader cannot decide whether to act.
- Owner is "the team" or left blank. Nobody is accountable.
- Mitigation is "keep an eye on it". Nothing is being done.
- Burying bad news. An issue that has already moved a milestone must connect to the overall status. If the report shows Green while the issues list shows a late milestone, the reader will stop trusting the status.
- Surprising the reader. A serious issue should not appear for the first time in the weekly report. Tell the affected people as soon as you know, and use the report as the written record.
Linking entries to status and asks
Risks and issues are the evidence behind your overall status. An Amber status should usually point to at least one entry here that explains it, and a Red status should point to an issue that threatens a milestone without a credible recovery. If an entry needs the reader to approve, fund, or decide something, repeat it as a line under "Decisions and asks" with a date. The risk entry explains the problem; the ask tells the reader what to do about it.
Exercise
Rewrite this entry so that it has a clear description, impact, owner, and mitigation, and decide whether it is a risk or an issue. Original: "Test environment problems are a concern for the team and might cause some delays." Facts you know: the shared test environment crashed on Tuesday and Wednesday; regression testing is 40% done against a plan of 80%; the release is due 19 December; Dana manages the environment; she has asked the infrastructure team to add a second server by Friday; in the meantime, tests run overnight on a developer machine.
Show answer
It is an issue, because the environment has already failed and testing is behind. Example rewrite: "Shared test environment crashed on Tuesday and Wednesday, so regression testing is 40% complete against a plan of 80%. Impact: if the environment is not stable by Monday, the 19 December release moves by about one week. Owner: Dana. Mitigation: infrastructure team is adding a second server by Friday; until then, tests run overnight on a developer machine." The answer must state a fact instead of "a concern", give a date-based impact, name one owner, and list concrete actions with a date.
Exercise
A vendor's contract renewal is due on 1 March. Your team thinks there is a medium chance the vendor will raise prices by 20%. Nothing has been announced. List the four fields you would write for this entry and say which response type (avoid, reduce, transfer, accept) your mitigation uses.
Show answer
This is a risk, because nothing has happened yet. Description: the vendor may raise prices by 20% at the 1 March renewal (likelihood: medium); the trigger is a price notice or no quote by 1 February. Impact: a 20% increase on the current annual cost, stated in currency if known. Owner: one named person, such as the procurement lead. Mitigation: for example, request a quote by 1 February and get a competing quote, which is the "reduce" response because it strengthens your negotiating position. Naming an alternative supplier to replace the vendor would be "avoid". Any one defensible response with a concrete action is correct.