Sub topic 9
Making decisions and asks explicit
This chapter assumes you already have a report structure with an overall status and a risks section. It also assumes you have sent at least one status report to a manager or steering group. The chapter covers the last section of the report, "Decisions and asks". This is where the reader learns what you need from them.
Why this section exists
A status report has two jobs. The first is to inform: the reader learns where the project stands. The second is to prompt action: the reader does something they would not have done otherwise. Most sections serve the first job. Only the decisions and asks section serves the second.
Readers often skim a report and miss a request buried in the risks. A request that is missed costs time. If you need approval by Friday and the reader notices on the following Tuesday, the project has lost days that no one can recover.
Giving requests their own section has three benefits:
- The reader can find every request in one place.
- You are forced to decide whether you actually need something or are just describing a worry.
- The history of the project records who was asked, when, and what happened.
Decisions, asks, and information
Three different things get mixed together in reports. Separate them before you write.
| Type | What it is | What the reader does | Where it belongs |
|---|---|---|---|
| Decision | A choice between options that only the reader (or their group) has authority to make | Chooses an option | Decisions and asks |
| Ask | A request for a resource, approval, introduction, or unblocking action | Acts or approves | Decisions and asks |
| Information | A fact the reader should know, with no action required | Reads it | Accomplishments, risks, or the summary line |
A decision usually has two or more real options. An ask usually has one desired outcome. "Should we keep the launch date or move it a week?" is a decision. "Please approve two extra contractor weeks" is an ask. Both belong in the same section because both require the reader to respond.
Information does not belong here. If a vendor delay is something the reader should be aware of but cannot influence, put it in the risks section. Padding the asks section with items that need no action teaches readers to ignore it.
The anatomy of a good request
A request that gets answered has five parts. Missing any one of them gives the reader a reason to delay or to come back with questions.
- The request. One sentence stating what you need. Start with a verb: "Approve", "Choose", "Assign", "Introduce".
- The person. Name the individual or group who must act. "Leadership" is not a person. If the whole steering group must decide, say so, and say who will collect the answer.
- The deadline. A calendar date, not "soon" or "next week". Prefer a date and day name together, such as "Friday 4 December".
- The consequence. What happens if the deadline passes. This tells the reader how urgent the request is, and it lets them judge priority against their other work.
- Your recommendation. For decisions, say which option you favor and why. Readers decide faster when they can agree or disagree with a proposal than when they must build one from scratch.
Here is a template line that holds all five parts:
- **Decision needed from:** Steering group, by Fri 4 Dec
**Question:** Keep the 14 Dec launch date or move it to 21 Dec?
**Recommendation:** Move to 21 Dec. The vendor approval is three weeks late and testing needs five days after it arrives.
**If no decision:** The team keeps working to 14 Dec, and the compressed test window raises the risk of a failed launch.You will not always need every label. For a simple ask, one sentence can carry all five parts: "Priya, please approve the two extra contractor weeks (cost: 8,000) by Wednesday, or the reporting module slips into January."
Weak and strong versions
The difference between a weak and a strong request is usually specificity. The following table shows common problems and their fixes.
| Weak version | Problem | Stronger version |
|---|---|---|
| We need more resources. | No owner, no amount, no date | Need one additional tester for three weeks from 7 Dec. Asking Marcus to approve by Wed 2 Dec. |
| Awaiting feedback on the design. | Passive, no person, no date | Please review the design document and send comments by Thu 3 Dec. Sana owns the review. |
| Leadership should consider the timeline. | "Consider" is not an action | Choose between launching on 14 Dec with reduced scope or on 21 Dec with full scope. I recommend 21 Dec. |
| Decision on vendor still pending. | Describes a state, not a request | Confirm by Mon 30 Nov whether we sign with Vendor A or restart selection. Restarting adds six weeks. |
Notice that every stronger version could be answered with a short reply. That is the test: can the reader respond in one line without needing a meeting?
Where requests come from
Requests do not appear from nowhere. They usually come from the sections that precede this one. Walking through your report from top to bottom helps you find them.
- From risks. For each risk, ask whether mitigation requires someone else's authority. If yes, the mitigation contains an ask. Write the risk in the risks section and the matching request here, and cross-reference them with a short phrase like "see the vendor risk above".
- From the status. If you set the status to amber or red, the reader will ask "what do you need?" Answer it before they do. An amber or red report with no ask can look like a complaint.
- From the plan. Items in next week's plan that depend on someone outside the team need a request. "Start data migration" depends on access; the request is "Grant database access to the migration team by Monday."
- From milestones. A milestone at risk often needs a scope, date, or budget decision.
The following diagram shows how to decide whether something belongs in this section.
Placement and visibility
The template in this tutorial puts the section last. That is a good default for a long report, because the reader finishes with the action in mind. It carries one risk: a reader who stops after the summary never sees it.
Handle this by echoing the most urgent request in the one-line summary. The example report does so: "the payment vendor's API approval is late and could delay launch" in the summary points to the steering group decision at the end. If a decision is blocking and due within a few days, mention it in the first two lines of the email or message that carries the report, not only inside the document.
Keep the section short. Three or fewer requests per report is a healthy number. If you routinely have six or seven, check whether:
- some are things you could decide yourself within your authority,
- some could be resolved in a direct conversation instead of waiting for the weekly cycle,
- or the project has a deeper problem that needs an escalation meeting, not another line in a report.
Decisions already made
Decisions are not only requests. When a decision was made this week, record it. A short line is enough:
## Decisions made this week
- 25 Nov: Steering group chose to drop the export feature from the first release (decided by Dana). Impact: saves nine days; export moves to release 2.This record protects you later. Months afterward, someone will ask why the export feature is missing, and the answer is in a dated report. Include who made the decision, the date, and the effect on scope, schedule, or cost.
You can keep these in the same section, with a subheading, or in a separate short list. Do not mix them with open requests, because a reader scanning for what they still owe must not have to filter out closed items.
Following up on open requests
An ask sent once and then forgotten is the most common failure. Treat open requests as a list you carry between reports.
- Carry it forward. If a request is unanswered by the next report, keep it, and mark it as overdue or repeated: "Raised 20 Nov, still open."
- Raise the stakes in numbers, not tone. Each week of delay should show its effect: "Launch now slips two weeks, up from one."
- Escalate once the deadline passes. A request that has passed its date with no response needs a direct message, not another line in the report. Name the person, restate the consequence, and offer a short call.
- Close it visibly. When the answer arrives, move the item to decisions made. Readers should see requests end.
If the reader answered, but not with what you hoped, record the actual answer. A "no" is still a decision, and the plan should change to match it.
Common errors
- Asking the wrong person. The person you address must have the authority. Check the decision-maker, not just the person you usually talk to.
- Hiding the ask in a risk. The risk section describes the problem. The ask is separate and goes here.
- Offering no options. "What should we do?" pushes the analysis onto the reader. Bring options and a recommendation.
- False urgency. If every item is marked "urgent", none is. Use real dates and real consequences.
- Surprise asks. Do not put a major request in the report that the reader sees for the first time. Warn them in a conversation first, and use the report as the written record.
- Vague deadlines. "ASAP" cannot be tracked. A date can.
Edge cases
There are no requests this week. Write "None this week." Do not delete the section. A visible "None" tells the reader the report is complete and that nothing is waiting on them.
The request is sensitive. Some decisions involve people or budgets that should not go to the whole distribution list. Send a short direct message instead, and write in the report: "One decision is with the sponsor separately."
The decision belongs to several people. Name one coordinator who collects the answers. A request addressed equally to five people tends to be answered by none.
You are not sure you need it. If you cannot say what happens without the answer, you probably do not need it yet. Hold it until you can.
Exercises
Exercise
Rewrite this weak line so it has a named person, a calendar date, a consequence, and a recommendation: "We need a decision on the testing approach soon." Assume the choice is between manual testing (two weeks) and automated testing (four weeks, but reusable), the decider is Elena, and the code freeze is on 11 December.
Show answer
A strong version: "Elena, please choose by Mon 30 Nov between manual testing (two weeks) and automated testing (four weeks, reusable in later releases). I recommend manual testing, because automated testing would push past the 11 Dec code freeze. If there is no decision by Monday, test preparation stalls and the freeze date is at risk." It names the person, gives a date, lists both options, includes a recommendation, and states the consequence.
Exercise
Your report has three items: (a) the vendor is late, and you can do nothing but wait, (b) you need the sponsor to approve two extra contractor weeks, (c) a milestone was met. Which belong in Decisions and asks, and where do the others go?
Show answer
Only (b) belongs in Decisions and asks, because only it needs the reader to act. Item (a) is a risk (or an issue), so it goes in the risks section with impact, owner, and mitigation. Item (c) is an accomplishment and goes in the accomplishments or milestones section.
Exercise
A request you raised two reports ago is still unanswered, and its deadline passed three days ago. List what you should do in the next report and outside it.
Show answer
In the next report, keep the item, mark it as overdue ("Raised 20 Nov, deadline 27 Nov, still open"), and state the updated consequence in numbers, such as the launch now slipping two weeks. Outside the report, message the named person directly, restate the consequence, and offer a short call to settle it. When the answer arrives, move the item to the list of decisions made.