What a Project Charter Is and Why It Matters
Prerequisites
This chapter assumes you know how a workplace project is organized. You should recognize common roles such as sponsor, project manager and team member. You should also understand that a project has a defined start, a defined end and a specific result.
What a Project Charter Is
A project charter is a short document that authorizes a project and sets its boundaries. It answers four questions: why the project exists, what it will achieve, what it includes and excludes, and who has authority over it. After the sponsor approves the charter, the project manager has formal permission to spend resources and lead the work.
A charter settles disputes early. When a stakeholder asks for extra work months later, the team can check the charter instead of relying on memory.
Charter, Business Case, Project Plan and Statement of Work
These documents overlap, but each has a different job.
| Document | Main question it answers | Typical length |
|---|---|---|
| Charter | Is the project authorized, and what are its limits? | 2 to 6 pages |
| Business case | Is the project worth its cost? | Varies |
| Project plan | How will the work be done, step by step? | Often longer |
| Statement of work | What will a supplier deliver under contract? | Varies |
Stating Why the Project Exists
The business justification explains the problem or opportunity. It states what happens if the organization does nothing and what benefit it expects from the project. Keep it to a few sentences. A reader should understand the reason for the project within one minute.
Writing Measurable Objectives
An objective states a result the project must reach. A measurable objective includes a metric, a baseline, a target and a deadline. Compare these two statements:
- Vague: Improve customer support response times.
- Measurable: Reduce the median first-response time for support tickets from 8 hours to 2 hours by 30 June.
The second version tells the team exactly when the project has succeeded.
Defining What Is In Scope and Out of Scope
Scope lists what the project includes and what it excludes. Write both lists. Explicit exclusions prevent the project from growing without a decision.
In scope
- Migrate the customer database to the new platform.
- Train support staff on the new tools.
Out of scope
- Redesign of the customer-facing website.
- Migration of archived data older than seven years.
Exercise
A stakeholder asks the project manager to add a website redesign to a project whose charter lists it as out of scope. What should the project manager do?
Show answer
Point to the out-of-scope entry and route the request through the change process. The sponsor decides whether to add the work, and if approved, the charter is revised to reflect the change.