Sub topic 2
Naming the deliverables
This chapter assumes you know how projects are organized at work and can name common roles such as sponsor, project manager and team member. You should also have a draft business case and a list of measurable objectives, because the deliverables and success criteria come from those.
Naming the deliverables
A deliverable is a tangible thing the project produces, such as a system, a report, a trained team or a new process. The charter lists deliverables so that everyone agrees on what finished looks like.
Write each deliverable as a noun phrase with a short description. Avoid activities such as "work on the database". Instead, write "Migrated customer database, live on the new platform."
- Name the deliverable, not the task.
- Keep each one specific enough for a sponsor to inspect.
- Stop at the level of detail the sponsor needs to approve.
Defining how success will be judged
Success criteria are the tests that show the project met its objectives. Each objective should map to at least one criterion, and each criterion needs a metric, a baseline, a target and a date.
Vague: Improve customer support response times.
Measurable: Reduce the median first-response time for support tickets from 8 hours to 2 hours by 30 June, without increasing headcount.
Criterion: Median first response time, measured weekly in the helpdesk tool
Baseline: 8 hours
Target: 2 hours or less
Deadline: 30 JuneIdentifying stakeholders
Stakeholders are people or groups who affect the project or are affected by it. Name them where you can, and note each one's interest and influence. Include the sponsor, the end users, the finance team and anyone who can block approval.
Assigning roles and granting authority
Name one person for each key role: sponsor, project manager and lead team members. The charter should state what the project manager may decide alone, such as daily scheduling and minor vendor choices. It should also state what needs sponsor approval, such as scope changes or spending above an agreed limit.
Setting high-level milestones
Milestones are major checkpoints with a date. They are not a task list. Most projects need five to eight. Each milestone should name a deliverable or a decision, such as "Pilot group live on the new platform, 15 May."
Exercise
A charter lists the deliverable "Work on the reporting module." Why is this weak, and how would you rewrite it?
Show answer
It names an activity, not a result, so no one can inspect it or say when it is finished. A better version is "Reporting module with monthly sales dashboards, deployed to production and accepted by the finance lead."