Sub topic 12
Tracking Open Questions and Decisions
Assume you understand the basic roles of product managers, designers, engineers, and stakeholders, and that you have already written a problem statement, goals, users, and requirements. This chapter focuses on two parts of a PRD that prevent confusion: the open-question register and the decision log.
Why open questions matter
An open question is an unresolved issue that could change the product, its scope, or its delivery plan. Examples include:
- Which user roles can export data?
- Does the first release need to support mobile devices?
- Which system owns the source data?
- What retention period does the compliance team require?
Questions often remain hidden in meeting notes, chat messages, or individual memory. That creates two risks. The team may build on an untested assumption, or different people may believe that different answers were agreed.
Record an open question when its answer affects a requirement, dependency, risk, user experience, cost, or timeline. Do not use the section as a general list of every topic the team might discuss.
Use an open-question register
Give each question an identifier and an owner. The owner is responsible for finding or requesting the answer. Add a due date when the answer is needed for a specific decision or milestone.
| ID | Question | Why it matters | Owner | Needed by | Status |
|---|---|---|---|---|---|
| OQ-01 | Can team admins export member email addresses? | May affect privacy review and FR-2 | Priya | Design review | Open |
| OQ-02 | Which data source is authoritative? | Determines the integration approach | Marco | Technical planning | Open |
| OQ-03 | Does the existing export service support CSV? | May reduce implementation work | Lena | Scope review | Answered |
Write questions so that another person can understand them without attending the original meeting. “Check privacy” is too vague. “Can team admins export member email addresses?” identifies the decision that must be made.
Separate questions from decisions
An open question records uncertainty. A decision log records a conclusion that the team has accepted. Keep both because a decision without its reasoning may later look arbitrary, while an unanswered question can be mistaken for a settled choice.
A useful decision entry includes:
- A decision identifier
- The date and people involved
- The chosen option
- The reason for choosing it
- The consequences for requirements, scope, or delivery
- A link or reference to the affected PRD section
For example:
| ID | Decision | Reason | Effect |
|---|---|---|---|
| D-01 | Export includes name, role, and work email | These fields support the finance use case and passed privacy review | Confirms FR-2; personal phone numbers remain out of scope |
Move items through a visible workflow
Review the register during planning and stakeholder reviews. When an answer is reached, do not delete the question. Mark it answered, record the answer, and create a decision entry if the answer changes the plan.
Handle reversals and stale entries
Decisions can change when new evidence appears. Do not silently edit history. Mark the earlier decision as superseded, record the new decision, and explain what changed. This preserves trust and helps the team understand why requirements moved.
Before review, check that every open question has an owner, a next action, and a useful due date. Close questions that no longer affect the work. Keep decisions that explain important scope or design choices.
Exercise
A stakeholder asks, “Are scheduled exports included?” The PRD does not answer it, and engineering needs to estimate the work. Where should you record it first?
Show answer
Record it as an open question with an owner, the reason it affects estimation, and the date by which the answer is needed. After the team decides, record the conclusion in the decision log and update scope.