Sub topic 11
Recording Assumptions, Dependencies, and Risks
This chapter assumes you understand the basic purpose of a product requirements document (PRD), the roles of product managers, designers, and engineers, and the difference between a feature and a user need. You will learn how to record what the team believes, what the work relies on, and what could prevent success.
Why these items belong in a PRD
A PRD is useful only when readers can see the conditions behind the plan. Teams often write requirements as if every fact were certain. That creates surprises later.
- An assumption is something the team believes to be true but has not fully verified.
- A dependency is an outside condition, team, system, or decision that the feature needs.
- A risk is a possible event that could harm delivery, quality, adoption, or business results.
These items make uncertainty visible. They also help reviewers challenge weak reasoning before engineers begin implementation.
Record assumptions
Write assumptions as statements that can be checked. Avoid vague entries such as “Users will like this.” Name the user, behavior, and evidence needed.
For example:
> We assume that team admins prefer CSV export over viewing member data in the application because they already share reports with finance as spreadsheets.
A useful assumption record includes:
- The belief.
- Why the team holds it.
- How it could be tested.
- The decision affected if it proves false.
- An owner and review date, when appropriate.
Do not hide an important assumption inside a requirement. If the assumption changes, the requirement may need to change too.
Map dependencies
Dependencies often come from another team, a shared service, a vendor, or a policy decision. Record the exact input required and the effect of delay.
| Dependency | Needed for | Owner | Due or trigger | Contingency |
|---|---|---|---|---|
| Identity service adds an admin-role claim | Permission checks | Platform team | Before development starts | Hide export until the claim is available |
| Finance confirms required CSV columns | Export format | Finance | Before design review | Use the current member fields |
| Privacy review approves member data export | Release approval | Legal or privacy team | Before production rollout | Limit export to non-sensitive fields |
A dependency should not be a vague statement such as “backend support.” Describe the interface or decision the feature needs. Link to a ticket, specification, or named owner if your team uses those references.
Assess risks
A risk is different from a known problem. A known problem already exists. A risk might happen. Record both the likelihood and the impact so the team can focus on material threats.
| Risk | Likelihood | Impact | Mitigation | Trigger and response |
|---|---|---|---|---|
| Large teams make exports time out | Medium | High | Generate the file asynchronously and test with large datasets | Timeout rate exceeds target; enable a queued export |
| Exported data is shared with the wrong recipient | Low | High | Restrict access and log every export | Suspicious access appears; pause exports and investigate |
A mitigation reduces the chance or effect of a risk. A contingency is the action the team will take if the risk occurs. Keep both specific and actionable.
Keep the records useful
Review these sections at planning, design, and release checkpoints. Close entries when evidence resolves them. Update the PRD when an owner, date, dependency, or mitigation changes.
A short, current register is more useful than a long list copied from an old project. Prioritize items that could change the problem, scope, architecture, launch date, or success metrics.
Exercise
The team assumes that most admins export member data for finance reports, but no evidence supports this belief. What should the PRD record?
Show answer
Record it as an assumption, state the evidence needed, assign an owner, and define how the requirement or scope will change if the assumption is false.