Sub topic 11
Recording assumptions, dependencies, and risks
This chapter covers section 7 of the PRD skeleton: assumptions, dependencies, and risks. It assumes you already know how to write a problem statement, goals, and prioritized requirements. You should also know the roles of product manager, designer, and engineer. The running example is the CSV member export from earlier chapters (FR-1 to FR-4).
Requirements describe what you want to build. This section describes what has to be true for that plan to work, what you need from others, and what could go wrong. Teams often skip it, or fill it with generic lines like "timeline may slip." A useful version is specific, has owners, and changes what the team does.
Three different things
The three terms are often mixed up. Keep them separate, because each one is handled differently.
| Item | What it is | Question it answers | Typical handling |
|---|---|---|---|
| Assumption | Something you believe is true but have not confirmed | "What are we treating as true?" | Validate it, or accept it knowingly |
| Dependency | Something outside your team's control that you need | "What do we need from someone else?" | Agree on a date and an owner |
| Risk | An uncertain event that would hurt the outcome if it happened | "What could go wrong?" | Mitigate, accept, or monitor |
One situation can produce all three. Suppose the export needs the member list from the identity service.
- Assumption: the identity service already stores each member's role.
- Dependency: the identity team must expose an endpoint that returns members in pages.
- Risk: that endpoint may be too slow for teams with tens of thousands of members.
Each is written and tracked differently, so write them in separate lists or tables.
Assumptions
An assumption is a belief your plan depends on. Every PRD has them. The goal is to make them visible, so someone can challenge them before engineering has built on top of them.
Finding assumptions
Look for them in these places:
- Statements in your problem section that rest on a single anecdote or an old survey.
- Phrases like "obviously," "users will just," or "we already have."
- Behavior you expect from users, such as "admins will export monthly."
- Technical facts you have not checked with an engineer.
- Business facts you have not checked with legal, finance, or support.
A useful test is to read each requirement and ask, "What would have to be true for this to work as written?" The answers are your assumptions.
Writing them so they can be checked
A good assumption is a specific statement that can turn out to be true or false. Pair each one with how you will find out, who will check, and what happens if it is wrong.
| Assumption | How we will validate | Owner | If wrong |
|---|---|---|---|
| Finance only needs name, email, and role. | Ask two finance contacts to review a sample file. | PM | Move FR-3 (column choice) from Could to Must. |
| Teams have fewer than 5,000 members. | Query current team sizes in the data warehouse. | Data analyst | Add paging and a size limit to the requirements. |
| Admins can open a downloaded CSV in their spreadsheet tool. | Test with the three tools support lists most often. | QA | Add an encoding requirement (see below). |
The "If wrong" column is the most useful one. It turns a vague belief into a decision rule. If you cannot say what you would change, the assumption may not matter, and you can drop it from the list.
Status of an assumption
Assumptions change over time. Mark each as open, validated, or invalidated. When one is invalidated, trace it back to the requirements that relied on it and update them. Chapter 15 returns to this when it covers keeping the PRD current.
Dependencies
A dependency is anything your delivery relies on that you do not control. It may be another team's work, a vendor, a legal approval, or a piece of infrastructure.
Kinds of dependency
- Team dependencies: another team must build or change something, such as the identity team's endpoint.
- External dependencies: a vendor, partner, or regulator, such as an email provider if exports are delivered by email.
- Decision dependencies: someone must decide something before work can proceed, such as legal confirming that exporting email addresses is allowed.
- Resource dependencies: you need a person with a particular skill, a test environment, or budget.
What to record
A dependency entry without a date and a name is only a wish. Record these fields for each one:
- What you need, described as an outcome ("a paged endpoint returning name, email, and role").
- Who provides it, by team and by named contact.
- When you need it, tied to a milestone and not a vague "early."
- Whether it is confirmed. Has the other team agreed, or have you only assumed they will?
- What you will do if it slips.
| Dependency | Provider | Needed by | Status | Fallback |
|---|---|---|---|---|
| Paged members endpoint with role field | Identity team (contact: <name>) | Start of build | Requested, not yet committed | Read from the replica database directly |
| Legal review of exporting email addresses | Legal (contact: <name>) | Before beta | Not yet requested | Ship without the email column |Notice that the second row has a status of "not yet requested." That is a useful thing to see in review. It shows a dependency on the critical path that nobody has started.
Dependencies shape the schedule
If a dependency is on the critical path, the other team's plan becomes part of yours. Check their roadmap early. A team that has committed its next quarter to other work cannot absorb your request just because you wrote it in a PRD. Writing a dependency down does not secure it. Talking to the provider does. The PRD records the result of that conversation.
Risks
A risk is something that might happen. If it already happened, it is an issue and belongs in your task tracker, not in the risk list.
Writing a risk statement
A clear risk has a cause, an event, and an impact. A common format is: "Because of <cause>, <event> might happen, resulting in <impact>."
- Weak: "Performance could be a problem."
- Stronger: "Because the export reads all members in one request, teams with more than 20,000 members might see time-outs, so large customers could not complete an export."
The stronger version tells an engineer where to look and tells a stakeholder why it matters.
Types of risk
Product risks are often grouped by what could fail:
- Value risk: users do not want it or do not use it.
- Usability risk: users cannot figure out how to use it.
- Feasibility risk: the team cannot build it as specified, or not in the time available.
- Business risk: it conflicts with legal, security, cost, or strategy constraints.
Walking through these four prompts is a fast way to avoid listing only technical risks. A CSV export has an obvious security angle: it puts personal data in a file that leaves the system.
Rating and responding
Rate each risk by likelihood and impact. Low, medium, and high are enough for most PRDs. Precise percentages suggest accuracy you do not have. Then choose a response.
| Response | Meaning | Example |
|---|---|---|
| Avoid | Change the plan so the risk cannot occur | Drop the email column to avoid the legal question |
| Mitigate | Reduce likelihood or impact | Add a row limit and a clear error message |
| Transfer | Shift it to someone better able to carry it | Use a vendor's hosted export service |
| Accept | Do nothing, knowing the cost | Accept that very large exports will be slow |
| Monitor | Watch for a trigger and act then | Alert if more than 2% of exports fail |
| Risk | Likelihood | Impact | Response | Owner | Trigger to revisit |
|---|---|---|---|---|---|
| Because the export reads all members in one request, teams with more than 20,000 members may see time-outs. | Medium | High | Mitigate: read in pages and stream the file | Engineering lead | Beta export failure rate above 2% |
| A CSV with personal data is shared outside the company. | Medium | High | Mitigate: audit log entry for every export; admin-only access (FR-1) | Security partner | Any export by a non-admin account |The "Trigger to revisit" column keeps a risk from becoming stale. It says what evidence would change the rating or the response.
Linking risks to requirements
Good mitigations often become requirements. The second risk above is why the member list export is limited to admins and why an audit log is needed. When a mitigation changes the product, add it to section 6 and cross-reference it. Otherwise the risk list says one thing and the requirements say another.
How the three connect
The lists feed each other. An unvalidated assumption is often a risk. A dependency that slips is a risk. A risk response may create a new dependency, such as asking the security team for a review.
Common mistakes
- Generic entries. "Resource constraints" fits any project and guides no decision. Name the specific thing.
- No owners. A risk with no owner is not managed. Assign one person, not a team.
- No dates. Dependencies and validation steps need a "by when."
- Treating the list as a formality. If the list is never opened after kickoff, it is documentation and not a working tool. Review it at each milestone.
- Hiding bad news. A high-impact risk in a PRD is a sign of good practice. Reviewers lose trust when they discover the risk later.
- Listing issues as risks. Something that has already happened needs action, not a likelihood rating.
- Listing everything. Twenty low-value risks bury the three that matter. Keep the list focused on items that could change a decision.
A worked pass over the export feature
Start with FR-1 to FR-4 and ask what must be true.
- FR-1 needs a list of members and their roles. That produces an assumption (roles are stored) and a dependency (identity endpoint).
- FR-2 includes email addresses. That produces a decision dependency on legal and a privacy risk.
- FR-3 lets admins choose columns. Its priority depends on an assumption about what finance needs.
- FR-4 excludes scheduled exports. That is a scope decision, so record the assumption that admins will accept manual exports in this release, and plan to check usage after launch.
After the pass, you have three assumptions, two dependencies, and two or three risks. That is the right size. The section should be short enough that every reviewer reads it.
Summary of the section's rules
- Separate assumptions, dependencies, and risks.
- Make each item specific, owned, and dated.
- Say how an assumption will be validated and what changes if it is wrong.
- Record dependencies as confirmed or unconfirmed, with a fallback.
- Write risks as cause, event, and impact, with a response and a trigger.
- Turn mitigations into requirements.
Exercise
A PRD for a new notification setting contains this line under risks: "The design might not be ready in time." Classify it, then rewrite it as one entry in the right form. Use placeholders for names and dates.
Show answer
It is a dependency (a decision or deliverable from the design team) and not a risk, because the cause is a known need from another team, not an uncertain event in the product. Rewritten as a dependency: "Final design for the notification settings screen. Provider: Design team (contact: <name>). Needed by: <start of build date>. Status: requested, not yet committed. Fallback: build with the existing settings layout and update the visuals later." If the real concern is that the design may change after build starts, add a separate risk: "Because the design is not final, late changes might require rework, delaying release. Response: mitigate by building the settings logic first and the screen last. Owner: <engineering lead>. Trigger: design not approved by <date>."
Exercise
Your PRD says: "We assume most admins export data once a month." Rewrite it as a checkable assumption with a validation method, an owner, and an "if wrong" decision.
Show answer
Assumption: "At least 70% of team admins will export data no more than once a month." Validation: review how often admins use the existing report download over the last six months, using the analytics data. Owner: <data analyst>. If wrong: if many admins export weekly, move scheduled exports (FR-4) from Won't to Should for the next release, and add a performance requirement for frequent large exports. The 70% figure is an example threshold. Agree on the real one with your team before checking the data.
Exercise
A risk entry reads: "Security issues." Name three things wrong with it and give a better version for the CSV export.
Show answer
It has no cause, no event or impact, and no owner, rating, response, or trigger. Better: "Because the export file contains names and emails, an admin might share it outside the company, exposing member data. Likelihood: medium. Impact: high. Response: mitigate with an audit log entry for each export and a confirmation notice before download. Owner: <security partner>. Trigger: any export by a non-admin account or any reported leak."