Sub topic 5
Set out the budget and costs
This chapter assumes you can already describe a solution and its scope, deliverables, and timeline (the previous chapters), and that you know basic cost terms such as one-time cost and recurring cost. The budget turns the scope into a number the decision maker can approve. It also sets up the value case in the next chapter, which compares benefits with these costs.
What the budget must do
A reader looks at the budget to answer three questions:
- How much money is being requested, and over what period?
- What does each part of the cost buy?
- How firm is the number?
If the reader has to guess at any of these, the proposal slows down or gets cut. Build the budget from the scope, so that every line traces to a deliverable you have already described.
Build the budget from the scope
Start with the list of deliverables and work down. For each one, estimate what it needs: people's time, purchases, services, and any other items. Then group the lines into categories the reader recognizes.
Separate two kinds of cost:
- One-time costs are paid once to get the solution in place, such as setup, licenses bought outright, training, and migration.
- Recurring costs continue after launch, such as subscriptions, support, hosting, and staff time to run the solution.
Many proposals understate cost because they show only the one-time figure. Decision makers approve a project's price but then live with its running costs, so show both.
Include internal staff time even when it needs no new cash. Staff time is a real cost, and leaving it out makes the total look smaller than it is.
Show your working
State how each number was reached. Give the rate, the quantity, and the source.
| Line | Basis | Type | Cost |
|---|---|---|---|
| Project manager | 40 days at 480 per day | One-time | 19,200 |
| Software setup | Vendor quote Q-1184 | One-time | 12,000 |
| Staff training | 25 staff at 150 each | One-time | 3,750 |
| Annual license | 25 users at 220 per year | Recurring | 5,500 |
| Contingency | 10% of one-time costs | One-time | 3,495 |
The one-time costs come to 38,445 including contingency (19,200 + 12,000 + 3,750 + 3,495). The recurring cost is 5,500 per year. A reader can check each line, and that is what makes the figures believable.
Handle uncertainty openly
Every estimate has error. You have three honest ways to show it:
- Add a contingency. A contingency is a reserve for costs you cannot yet predict. Show it as its own line with its percentage, as in the table above, so it is not read as padding.
- Give a range when the inputs are loose, for example "between 34,000 and 42,000", and say what decides where in the range the cost falls.
- List assumptions that the figures depend on, such as "assumes 25 users" or "assumes vendor pricing holds until March".
Show the total cost over time
Decision makers often compare options across several years. Present a simple multi-year view so recurring costs are visible.
The figures include the one-time 38,445 plus the 5,500 license in each year. Year one is therefore 43,945, not 38,445.
Common errors
- Omitting recurring costs. The project is approved, and the next budget cycle is surprised.
- Leaving out internal time. The proposal looks cheaper than it is.
- A single round number with no basis. "About 50,000" invites cuts.
- Costs that do not match the scope. If a line has no deliverable, or a deliverable has no line, the reader will notice.
- Changing figures between sections. The budget, the executive summary, and the value case must show the same totals.
Check before moving on
Confirm that every deliverable has a cost, every cost has a stated basis, one-time and recurring costs are separate, and assumptions are written down. The next chapter uses these totals to calculate return.
Exercise
A proposal lists a one-time cost of 20,000 and a yearly support fee of 4,000. The reader asks what the total cost is over three years. What is it, and what should the budget have shown to prevent the question?
Show answer
The total is 32,000 (20,000 + 3 × 4,000). The budget should have shown one-time and recurring costs separately and included a multi-year view of cumulative cost.
Exercise
Why should contingency appear as its own line with a percentage instead of being spread across the other lines?
Show answer
A separate line shows the reader exactly how much is reserved for uncertainty and why. Hidden padding looks like an unexplained margin and reduces trust in the other figures.