Sub topic 7
Address risks and mitigations
This chapter assumes you can already frame a problem, describe a solution, and set scope, budget, and a value case. Here you add the part that shows you have thought about what could go wrong.
Why decision makers want to see risks
Approvers know every project has risks. A proposal that lists none looks naive, or it looks like the writer is hiding something. A proposal that names risks and says what you will do about them shows control. That makes approval feel safer.
A risk is an uncertain event that, if it happens, hurts cost, schedule, quality, or the expected benefit. It is different from an issue, which is a problem that has already happened. Write about risks that might happen, not problems you already have.
Find the risks that matter
Start from the sections you have already written. Each one rests on assumptions, and each assumption can fail.
- Scope and timeline: a dependency on another team, or a vendor delivery date.
- Budget: prices that could rise, or effort that was underestimated.
- Value case: adoption lower than assumed, or savings that arrive later.
- People: a key person leaves, or staff lack time.
- External: new regulation, supplier failure, or a security incident.
Do not list everything. Choose the five to eight risks that an approver would care about most.
Rate each risk
Rate each risk on two scales: likelihood (how probable it is) and impact (how much damage it does). Use simple levels such as low, medium, and high. Fine numeric scores suggest accuracy you do not have.
Spend your words on risks that are high on either scale. A low-likelihood, high-impact risk, such as losing a critical vendor, still deserves a mitigation.
Write a mitigation for each risk
A mitigation is an action that lowers the likelihood or the impact. A weak mitigation is "we will monitor this." A strong one names an action, an owner, and a timing.
There are four common responses:
- Avoid: change the plan so the risk cannot occur.
- Reduce: take steps that make it less likely or less costly.
- Transfer: move it to someone else, for example through insurance or a fixed-price contract.
- Accept: do nothing now, and say why that is reasonable.
Also state a contingency where it matters. A contingency is what you will do if the risk happens anyway.
Present the risks in a table
A table lets an approver scan the whole picture in under a minute.
| Risk | Likelihood | Impact | Mitigation | Owner |
|---|---|---|---|---|
| Vendor delivers the software two weeks late | Medium | High | Contract includes a late-delivery penalty. Testing starts on partial builds. | Project manager |
| Staff do not adopt the new tool | Medium | Medium | Train two pilot teams first. Gather feedback before full rollout. | Operations lead |
| Costs exceed budget by more than 10% | Low | High | Hold a 10% contingency. Review spending monthly. | Finance partner |
Link the risks back to your budget. If you hold a contingency, show it as a line in the budget so the two sections agree.
Common errors
- Listing risks with no mitigations, which leaves the reader worried.
- Using vague wording such as "some delays may occur." Say how long and why.
- Hiding the largest risk. Approvers who find it later will doubt the rest of the proposal.
- Writing mitigations that cost money or time but do not appear in the budget or schedule.
- Describing generic risks that could appear in any proposal, rather than risks specific to this project.
Exercise
Exercise
A proposal says, "Risk: the supplier may be late. Mitigation: we will keep an eye on it." Rewrite the mitigation so it is specific, and name which of the four responses you used.
Show answer
Example: "Add a clause to the supplier contract that reduces payment by 2% for each week of delay, and order the long-lead parts first. The procurement lead will check the delivery status every two weeks." This uses Reduce, with a Transfer element through the penalty clause. A strong answer names an action, an owner, and a timing.