Sub topic 1
How a Sprint Works: Events, Artifacts, and Cadence
Prerequisites
This chapter assumes you know what a product backlog and a user story are, and that you have worked alongside software engineers. It uses Scrum terms such as sprint, increment, and time box without defining them again.
Sprint events and artifacts
A sprint is a fixed time box, usually one to four weeks. Inside it, the team runs four events: sprint planning, the daily scrum, the sprint review, and the sprint retrospective. Backlog refinement is ongoing, but it feeds sprint planning.
Three artifacts track the work. The product backlog holds everything the product might need. The sprint backlog holds the items the team committed to for this sprint. The increment is the working software produced so far.
Where the product manager fits and where the team decides
The product manager owns the backlog order and explains why items matter. The Scrum Master protects the process. Developers decide how to build the work and how much they can commit to. The product manager proposes what and why, and the team decides how.
Owning the backlog and setting priorities
Order the backlog by value, risk, and dependency. Keep the top items small and clear. Lower items can stay rough until they move up.
Writing stories and acceptance criteria engineers can build from
A story names who needs something, what they need, and why. Acceptance criteria state the conditions that make the story done. Write them as Given, When, Then:
Scenario: Saved address is pre-filled
Given a customer with a saved shipping address
When the customer opens checkout
Then the shipping form shows the saved addressRefining the backlog together with engineers
Refinement is a short, regular conversation. Engineers ask questions, reveal hidden work, and suggest smaller slices. Aim to have the next sprint's top items ready before planning starts.
Estimation: what story points are and what they are not
Story points are a relative measure of effort and uncertainty, agreed by one team. They are not hours, not a productivity score, and not a promise. A 5-point story is roughly twice the work of a 3-point story for that team. Do not compare points across teams.
Exercise
A story has acceptance criteria that say "the page loads quickly." Why is this a weak criterion, and how would you rewrite it?
Show answer
"Quickly" is not testable. Rewrite it with a measurable condition, for example: "The checkout page finishes loading within 2 seconds at the 90th percentile on the staging test profile."