Sub topic 2
Definition of Ready and Definition of Done
This chapter assumes you know what a product backlog and a user story are, and that you have sat in on at least one sprint. It covers how the Definition of Ready and Definition of Done gate your work, how to set a sprint goal, how to size a sprint, how to run planning, and how to stay useful during the sprint.
Definition of Ready and Definition of Done
The Definition of Ready (DoR) is a checklist a story must pass before the team pulls it into a sprint. The Definition of Done (DoD) is a checklist a story must pass before the team counts it as complete.
| Checklist | Applies when | Example check |
|---|---|---|
| Definition of Ready | Before sprint planning | Acceptance criteria written and story estimated |
| Definition of Done | Before the story counts as complete | Code reviewed, tested, and deployed to staging |
> Keep both lists short and shared by the whole team. You can propose items, but engineers own the DoD.
Setting a sprint goal
A sprint goal is one sentence describing the outcome the sprint should deliver. Write it so a stakeholder can read it and know whether the sprint succeeded. Example: "Guest customers can complete checkout without creating an account."
Capacity and velocity
Capacity is the work time the team has in a sprint after holidays, meetings, and on-call duty. Velocity is the number of story points the team finished in recent sprints. Use the average of the last three sprints to forecast how many sprints remain:
import math
completed_points = [21, 18, 24, 20]
remaining_points = 85
recent = completed_points[-3:]
average_velocity = sum(recent) / len(recent)
sprints_needed = math.ceil(remaining_points / average_velocity)
print(f"Average velocity (last 3 sprints): {average_velocity:.1f}")
print(f"Forecast: about {sprints_needed} sprints to finish {remaining_points} points")Present the result as a range, not a promise.
Running sprint planning with the team
- Restate the sprint goal and confirm the team agrees with it.
- Walk the backlog from the top. Answer questions about acceptance criteria.
- Let engineers estimate capacity and commit to the stories they can finish.
- Stop when the sprint is full. Leave the rest in the backlog.
During the sprint: the daily scrum and your availability
Attend the daily scrum to listen for blockers and scope questions. Do not assign tasks there. Set fixed hours when engineers can reach you for quick answers, and resolve blockers the same day when you can.
Exercise
Exercise
A story has clear acceptance criteria but no estimate. Does it meet the Definition of Ready?
Show answer
No. The team must estimate it before it can enter the sprint.