Sub topic 16
Using velocity and flow metrics for forecasting without gaming
Assume you understand product backlogs, user stories, story points, and the basic sprint cycle. This chapter focuses on forecasting, not on estimating individual stories.
What velocity can and cannot tell you
Velocity is the number of story points a team finishes in a sprint. It is useful for forecasting a range of possible delivery dates when the team, work type, and point scale remain reasonably stable.
Velocity is not a productivity score. Story points are relative estimates, so 30 points in one team cannot be compared with 30 points in another team. A team can also increase its velocity by changing estimates without delivering more customer value.
Use several recent sprints rather than one unusually high or low sprint. For example, if the last three sprints delivered 18, 21, and 24 points, the average is 21 points. If 85 points remain, the rough forecast is five sprints. Present this as an estimate with uncertainty, not a commitment.
import math
completed_points = [21, 18, 24, 20]
remaining_points = 85
recent = completed_points[-3:]
average_velocity = sum(recent) / len(recent)
low_velocity = min(recent)
high_velocity = max(recent)
best_case = math.ceil(remaining_points / high_velocity)
likely_case = math.ceil(remaining_points / average_velocity)
worst_case = math.ceil(remaining_points / low_velocity)
print(f"Recent average velocity: {average_velocity:.1f} points")
print(f"Forecast range: {best_case} to {worst_case} sprints")
print(f"Likely case: about {likely_case} sprints")Add flow metrics
Flow metrics describe how work moves through the system. They help you notice problems that velocity hides.
| Metric | Meaning | Useful question |
|---|---|---|
| Throughput | Completed work items per period | How many items do we finish each week? |
| Cycle time | Time from starting an item to finishing it | How long does a typical item take? |
| Work in progress | Items currently being worked on | Are too many items open at once? |
| Aging work | Time an unfinished item has been open | Which item may become a delay? |
Track these metrics using consistent states and item types. A sudden increase in cycle time may indicate dependencies, unclear requirements, review queues, or too much work in progress. Investigate the cause before changing the forecast.
Forecasting without gaming
Agree with engineering which completed items count. A story should count only when it meets the Definition of Done. Do not count partially finished work because it makes the forecast look better while leaving unfinished work hidden.
Explain assumptions beside every forecast:
- which sprints or weeks are included;
- whether team capacity will change;
- whether the remaining work is estimated consistently;
- which dependencies or risks could alter the range.
Review the forecast when new evidence arrives. If cycle time rises while velocity stays stable, the team may be completing fewer, larger items. That is a reason to inspect the workflow, not to demand higher velocity.
Exercise
The team completed 24, 20, and 16 points in its last three sprints. The backlog has 90 points remaining. What should you communicate?
Show answer
The average velocity is 20 points, so the central estimate is about five sprints. Communicate a range based on recent variation and state assumptions about capacity, scope, and dependencies. Do not promise delivery in exactly five sprints.