Sub topic 10
Running Sprint Planning with the Team
Assume you understand the product backlog, user stories, story points, and the team’s Definition of Done. Sprint planning turns those inputs into a shared plan for one sprint. The product manager brings product context and priorities. The developers decide how the work can be built. The Scrum Master helps the conversation stay focused and makes the process effective.
Prepare before the meeting
Sprint planning works best when the highest-priority backlog items are already refined. Each candidate story should explain the user need, include testable acceptance criteria, and be small enough to complete within the sprint.
Before planning, check:
- The product goal and current priority.
- The proposed sprint goal.
- The team’s availability, including holidays, leave, support duty, and planned technical work.
- Recent delivery history, such as velocity or completed work.
- Dependencies, risks, and unresolved decisions.
- Whether the top stories meet the team’s Definition of Ready.
Do not use planning to discover every detail of an unclear backlog. Move unclear items back to refinement or agree on a short investigation, called a spike, when the uncertainty is essential.
Run the planning conversation
A useful sequence is:
- Explain the outcome. State the customer or business problem the sprint should address.
- Propose a sprint goal. Make it specific enough to guide trade-offs but broad enough to allow implementation choices.
- Review candidate stories. Explain why each item matters and answer product questions.
- Estimate or clarify work. Developers discuss complexity, dependencies, and technical risks. They own the estimates.
- Check capacity. Compare the proposed work with actual availability and recent delivery patterns.
- Build a forecast. Developers select the work they believe they can complete while pursuing the goal.
- Confirm the plan. Record the sprint goal, selected items, known risks, and any follow-up decisions.
The product manager should not assign stories to individual engineers or pressure the team to accept a fixed number of points. The team makes the commitment or forecast. The product manager explains the value and decides priority when trade-offs are needed.
Example: connect the goal to the plan
Feature: Guest checkout
Scenario: A new customer completes an order without an account
Given a customer has items in the cart
When the customer provides payment and delivery details
Then the customer can place the order without creating an account
And the customer receives an order confirmationThe scenario gives the team a shared outcome. Developers still choose the design, technical approach, and task breakdown.
| Planning input | Who provides or owns it | How it is used |
|---|---|---|
| Customer priority | Product manager | Orders candidate work |
| Technical approach | Developers | Shapes implementation |
| Capacity estimate | Whole team, based on availability | Limits the forecast |
| Sprint process | Scrum Master | Keeps the event focused |
Check the result
At the end, ask each participant to explain the goal in their own words. Confirm that the selected stories support it and that unfinished work has a clear product decision. A good plan is an informed forecast, not a promise that ignores uncertainty.
Exercise
The team has capacity for either a high-value checkout story or three low-value cleanup stories. The checkout story supports the proposed sprint goal but has a dependency risk. What should you do?
Show answer
Explain the checkout story’s value, ask developers to assess the dependency, and decide whether the risk can be managed within the sprint. If it cannot, revise the goal or choose work that still supports the intended outcome.