Sub topic 3
Planning the Data You Need
Before collecting data, turn the suspected root cause into a clear measurement plan. This chapter assumes you know basic Lean Six Sigma terms such as DMAIC, defect, process output (Y), and process input (X). You should also be able to read simple charts and calculate a mean and standard deviation.
A data plan prevents a common mistake: collecting many numbers without knowing what question they answer. The plan should state what you will measure, where the data will come from, how much data you need, and what result would support or challenge the suspected cause.
Start with the question
Write the verification question in one sentence:
> Does the suspected cause change the process output?
For example:
- Suspicion: the evening shift creates more packaging defects.
- Output Y: whether each package has a seal defect.
- Suspected input X: work shift.
- Verification question: Is the defect rate different between the day and evening shifts?
A useful hypothesis includes a direction when you have a reason to expect one:
- Null hypothesis: the defect rate is the same for both shifts.
- Working hypothesis: the evening shift has a higher defect rate than the day shift.
Do not collect data until the terms in the question have clear operational definitions. An operational definition states exactly how a value is observed and recorded.
For the packaging example:
- A defect is a seal that fails the defined pressure test.
- Shift is the shift assigned when the package was produced.
- The unit is one completed package.
- The collection period covers both shifts across several normal production days.
Define the data fields
List each field before collection. Separate fields that identify the observation from fields that measure the process.
| Field | Type | Operational definition | Example |
|---|---|---|---|
| Unit ID | Identifier | Unique record number for one package | P-00427 |
| Timestamp | Date/time | Time the package leaves sealing | 2026-11-28 18:42 |
| Shift | Category | Shift assigned at the timestamp | Evening |
| Defect | Binary | 1 if the seal fails the pressure test, otherwise 0 | 1 |
| Sealer temperature | Continuous | Temperature in degrees Celsius from the calibrated display | 182.4 |
| Operator | Category | Coded operator identifier | O-17 |
The output must be measured consistently. If inspectors use different definitions of a seal failure, the data may reflect inspector differences instead of process differences.
Choose a sampling plan
A sampling plan describes which units you will measure and when. Include these decisions:
- Population: the full set of units you want to understand.
- Sampling unit: the individual item, transaction, batch, or time period recorded.
- Sampling method: how units are selected.
- Sample size: how many observations are collected.
- Time window: when collection starts and ends.
- Strata: groups that may hide differences, such as shift, machine, product, or supplier.
Prefer a representative sample over a convenient sample. For example, collecting only the first hour of the day may miss warm-up problems. Collecting only defective units cannot estimate the defect rate because the good units are missing.
When the suspected cause is a category, collect observations from every category under comparable conditions. If you compare shifts, try to cover the same products, machines, and workload on each shift. Record those conditions so you can identify confounding later.
Check the plan before collecting
Run a small pilot with a few observations. Ask:
- Can each field be recorded without guessing?
- Are the units and time stamps unambiguous?
- Are all relevant groups represented?
- Can two people record the same observation and agree?
- Are the instruments available and calibrated?
- What happens when a value is missing or impossible?
A pilot can reveal that “operator” means the person who starts a job for one recorder and the person who finishes it for another. Resolve such differences before full collection.
Plan how to handle missing data. Do not silently replace missing values with zero. Record a missing-value code and its reason, such as equipment unavailable, unit not produced, or inspection skipped. Also preserve the original records so that later corrections are traceable.
Link the plan to the decision
Define what evidence would change your action. For example:
- Accept the suspected cause for further improvement work if the evening shift has a practically important and statistically supported higher defect rate.
- Reject the cause if the groups are comparable and the difference is small.
- Revise the hypothesis if the difference appears only for one product or machine.
Statistical significance alone is not enough. A tiny difference may be statistically detectable but too small to matter. State the practical threshold before collecting data, such as “an increase of at least 3 percentage points in the defect rate.”
Exercise
A team suspects that machine 2 causes longer cycle times. Name the output, the suspected input, one operational definition, and one sampling concern.
Show answer
The output is cycle time in minutes. The input is machine number. An operational definition is the elapsed time from the first processing scan to the completed-unit scan. A sampling concern is comparing machines while they run different products or workloads.