Sub topic 10
Baselining the Metric and Setting a Target
Assume you know basic Lean Six Sigma terms such as DMAIC, defect, process, and SIPOC, along with proportions and means. This chapter uses the CTQ tree from the previous steps. The focus is turning one measurable CTQ requirement into a trustworthy baseline and a useful project target.
What the baseline tells you
A baseline is the current measured performance of the process before improvement work begins. It answers, “How does the process perform now?” The baseline must use the same specification, defect definition, population, and time window that you will use later.
Suppose the CTQ requirement is:
- Order delivered within 3 calendar days of the order date.
- A defect is any order delivered after 3 calendar days.
- The project Y is the percentage of orders delivered within 3 days.
If 98 of 100 orders meet the requirement, the baseline is 98% on-time delivery. The defect rate is 2%.
Do not calculate the baseline from a convenient sample without recording how it was selected. Include the measurement period, number of orders, exclusions, and data source. A baseline from one unusually quiet week may not represent normal performance.
from datetime import date
SPEC_DAYS = 3
orders = [
(date(2026, 3, 2), date(2026, 3, 4)),
(date(2026, 3, 2), date(2026, 3, 6)),
(date(2026, 3, 3), date(2026, 3, 5)),
(date(2026, 3, 3), date(2026, 3, 9)),
]
defects = sum(
(delivered - ordered).days > SPEC_DAYS
for ordered, delivered in orders
)
defect_rate = defects / len(orders)
on_time_rate = 1 - defect_rate
dpmo = defect_rate * 1_000_000
print(f"Orders: {len(orders)}")
print(f"On-time rate: {on_time_rate:.0%}")
print(f"Defect rate: {defect_rate:.0%}")
print(f"DPMO: {dpmo:,.0f}")This sample has two defects in four orders. The baseline on-time rate is 50%, the defect rate is 50%, and the defect opportunity count is one per order, so the DPMO is 500,000.
Setting a meaningful target
A target is the performance level the project commits to achieve by a stated date. A target should be specific, measurable, time-bound, and connected to the customer requirement.
For example:
- Baseline: 92% of orders delivered within 3 calendar days during April.
- Target: at least 98% of orders delivered within 3 calendar days by the end of September.
The target should reflect customer expectations and process capability. A target of 100% may sound attractive, but it can be misleading when delays are caused by factors outside the process team's control. A target below the customer’s minimum acceptable level is also unsuitable, even if it is easy to achieve.
Use evidence to choose the level:
- Customer survey results or service commitments.
- Historical performance from the best stable periods.
- Benchmark data, when the processes are comparable.
- Variation and capability observed in the baseline.
- The improvement needed to close the customer-impacting gap.
State whether the target applies to the average, proportion, defect rate, or another statistic. “Improve delivery” is not a target. “Reach at least 98% on-time delivery for orders released during September” is.
Link the metric to the CTQ tree
The CTQ tree provides the logic for selecting the project Y:
If the customer has several important drivers, do not combine them into one vague score unless the business has explicitly defined how the score works. Delivery speed and order accuracy may need separate Ys because each has a different defect definition and improvement path.
Common errors
- Choosing a target before collecting a baseline.
- Using a mean when the CTQ is a pass-or-fail requirement.
- Omitting the denominator or reporting only the defect count.
- Mixing calendar days with business days.
- Excluding inconvenient cases without documenting the rule.
- Setting a target that rewards the team for changing the measurement method.
- Treating a single short-term result as stable performance.
Record the baseline and target in the project charter, including the operational definition and data period. Later phases can update the baseline as measurement quality improves, but any change must be documented.
Exercise
A process delivers 450 of 500 orders within the promised time. The project target is 97% on-time delivery. What are the baseline rate and the required additional on-time orders if the future sample also contains 500 orders?
Show answer
The baseline is 450 / 500 = 90%. The target requires 0.97 × 500 = 485 on-time orders, so at least 35 additional orders must meet the promise.