Carrying the metric into the project charter
This chapter assumes you have finished the earlier chapters of this tutorial. You should have a CTQ tree with a validated requirement, an operational definition, and a baseline and target for the project Y. You should also know the basic Lean Six Sigma terms (DMAIC, defect, process) and be able to read a proportion and a DPMO figure.
The CTQ work is only useful if the project keeps it. The project charter is where that happens. It is the short document that sponsors, the team, and the process owner agree on before the Measure phase starts. If the charter drops or rewrites the metric, the team will measure and improve something other than what the customer asked for.
What the charter must inherit from the tree
A charter has several sections. Four of them depend directly on the CTQ work:
| Charter section | What it takes from the CTQ work |
|---|---|
| Problem statement | The Y, its operational definition, and the baseline |
| Goal statement | The target, the same unit as the baseline, and a date |
| Scope | The process boundaries where the Y is measured |
| Business case | The cost of defects counted by the specification |
The remaining sections (team, schedule, risks) do not come from the tree.
The rule is that the charter copies these items and does not restate them. Copy the Y name, the unit, and the definition of a defect word for word. If you paraphrase "delivered within 3 calendar days of the order date" as "fast delivery", you have lost the specification that makes the metric countable.
Writing the problem statement
A problem statement describes the gap between what the customer needs and what the process delivers today. It states facts. It does not state a cause or a solution.
A usable problem statement has four parts:
- The customer need, in the customer's terms.
- The requirement and the defect definition from the CTQ tree.
- The baseline, with the period and sample size it came from.
- The process and location where it happens.
Here is a weak version:
- "Customers are unhappy with slow shipping, so we need a new carrier."
It names a solution (a new carrier) before any analysis. It has no metric, no baseline, and no definition of "slow".
Here is a stronger version:
- "Customers need orders to arrive quickly. Our requirement is delivery within 3 calendar days of the order date. From 1 September to 31 October 2026, 18% of 600 sampled standard-shipping orders missed this requirement (baseline DPMO 180,000, one opportunity per order)."
A reader can check every number in this statement against the tree and the baseline study.
Writing the goal statement
A goal statement says what will change, by how much, and by when. It uses the same Y, unit, and definition as the problem statement. A common format is: reduce Y from baseline to target by date.
For the example: "Reduce the percentage of standard-shipping orders delivered more than 3 calendar days after the order date from 18% to 9% by 30 June 2027."
Check these properties:
- Same unit. The baseline and target are both percentages of orders. If the baseline is a defect rate and the target is a mean number of days, the goal cannot be tested.
- Same definition. The target applies to the operational definition used for the baseline, including the same exclusions.
- Direction. The wording makes clear whether lower or higher is better.
- Date. The date falls after the baseline period and leaves time for Improve and Control.
- No solution. "By installing a new routing system" does not belong in the goal. The Analyze phase decides how.
Where the target number comes from
The target should have a reason. Acceptable sources are a customer requirement, a benchmark, a business case, or a stated improvement fraction such as "halve the defect rate". A target of 9% here is a 50% reduction. Say so in the charter, so that the sponsor knows the target is a decision and not a result of analysis.
A target that is too soft is met by noise. A target that demands more than the process can deliver wastes the project. If the baseline is unstable, the target is hard to interpret, so note in the charter whether the baseline process was stable.
Keeping the charter and the tree traceable
Traceability means you can follow any charter number back to its source. Keep a small record next to the charter. This YAML file ties the charter fields to the CTQ tree from earlier chapters:
project: Late standard-shipping orders
ctq_tree_version: 3
need: "My order should arrive quickly and correctly"
driver: Delivery speed
requirement: "Order delivered within 3 calendar days of the order date"
defect: "Delivered more than 3 calendar days after the order date"
y_metric:
name: "% of orders delivered within 3 days (reported as the defect rate)"
unit: proportion of orders
operational_definition: "doc/opdef-delivery-days-v2"
baseline:
value: 0.18
sample_size: 600
period: ["2026-09-01", "2026-10-31"]
target:
value: 0.09
due: "2027-06-30"
rationale: "Halve the defect rate"The record has two benefits. A reviewer can see which version of the tree the charter used. When the tree changes, you can see what the charter must change too.
Checking the numbers before sign-off
Many charter errors are arithmetic or consistency errors, and a short script can catch them. This script checks the example's numbers and prints the reduction and the DPMO values.
from dataclasses import dataclass
from datetime import date
@dataclass
class CharterMetric:
baseline: float # defect rate as a proportion
target: float # defect rate as a proportion
baseline_n: int
baseline_end: date
due: date
def reduction(self) -> float:
return (self.baseline - self.target) / self.baseline
def problems(self) -> list[str]:
found = []
if not 0 < self.target < self.baseline < 1:
found.append("target must be lower than baseline, and both between 0 and 1")
if self.due <= self.baseline_end:
found.append("due date must be after the baseline period")
if self.baseline * self.baseline_n < 5:
found.append("baseline sample holds fewer than 5 expected defects")
return found
m = CharterMetric(
baseline=0.18,
target=0.09,
baseline_n=600,
baseline_end=date(2026, 10, 31),
due=date(2027, 6, 30),
)
print(f"Reduction {m.reduction():.0%}; "
f"baseline DPMO {m.baseline * 1_000_000:,.0f}; "
f"target DPMO {m.target * 1_000_000:,.0f}")
print(m.problems() or "No problems found")The script prints a 50% reduction, a baseline DPMO of 180,000, and a target DPMO of 90,000. It then prints "No problems found". The checks are deliberately simple. The 5-defect rule is a rough guard against a baseline too small to trust, and it does not replace a proper confidence interval.
Scope and the boundary of the metric
The scope section tells the team where the Y is measured and what is out of bounds. Use the operational definition to set it. If the definition counts only standard-shipping orders placed on the web store, say that. If express orders, wholesale orders, and returns are excluded, list them as out of scope.
Two scope errors are common:
- Scope wider than the metric. The charter says "improve the order process", but the Y measures only delivery time. The team will be asked to fix invoicing and cannot show progress.
- Metric wider than the scope. The Y covers all orders, but the team may change only the warehouse. They cannot move the number if carriers cause the delay.
Add a short line on the order accuracy driver if it was left out. Leaving a driver out of this project is a valid choice. The charter should say it was deferred, and not let it vanish without comment.
Business case and the specification
The business case converts defects into money or risk. Use the defect definition from the specification to count them. If 18% of 40,000 yearly orders are late, that is 7,200 late orders. Multiply by a documented cost per late order, such as refunds, support contacts, or lost repeat sales. State the source of the cost figure. A business case built on an unsourced cost per defect is the weakest part of most charters.
Changing the metric after approval
A charter is not frozen. Sometimes the Measure phase shows that the operational definition is flawed, for example if the order date field is overwritten when customers edit an order. Then the Y or its baseline must change.
Handle this as a recorded change:
- State what changed in the definition, and why.
- Recompute the baseline using the new definition.
- Restate the target on the same basis.
- Get the sponsor's agreement and update the tree version in the traceability record.
Never change the target quietly because the baseline looks worse than expected. If you change the definition and keep the old target, the project may be declared a success or a failure for reasons unrelated to the process.
Common errors at the charter step
| Error | How to spot it | Fix |
|---|---|---|
| Solution in the problem statement | Phrases such as "we need a new system" | Rewrite as a gap between requirement and baseline |
| Metric name differs from the tree | Charter says "lead time", tree says "% delivered within 3 days" | Copy the name and unit from the tree |
| Baseline with no period or size | A single number without context | Add period, sample size, and data source |
| Target without a basis | No rationale given | Cite requirement, benchmark, or reduction fraction |
| Mixed units | Baseline in percent, target in days | Express both in the unit of the Y |
| Goal date inside the baseline period | Due date earlier than data end | Set the date after the baseline and leave time for Improve and Control |
Exercise
A draft charter says: "Customers complain about late deliveries. Reduce average delivery time to 2 days by installing a regional warehouse." The CTQ tree for this project uses the Y "% of orders delivered within 3 calendar days of the order date", with a baseline of 18% defective from 600 orders. Name three problems with the draft and rewrite the goal statement.
Show answer
Problems: (1) The goal uses a different Y (average delivery time) from the tree, so it cannot be compared with the baseline. (2) It names a solution (a regional warehouse) before analysis. (3) It has no baseline, no definition of a defect, and no date. A corrected goal statement: "Reduce the percentage of standard-shipping orders delivered more than 3 calendar days after the order date from 18% to 9% by 30 June 2027." The reasoning for the target (for example, halving the defect rate) goes in the charter, and the regional warehouse is left for the Improve phase to consider.
Exercise
Your baseline study covers 1 September to 31 October 2026, and your sponsor wants the project to finish improvements by 15 October 2026. What does the script's date check report, and what should you do?
Show answer
The check reports that the due date must be after the baseline period, because 15 October falls before the baseline period ends on 31 October. The charter date is not possible, since the project cannot meet a goal before its own baseline data was collected. Set a due date after the baseline period that leaves time for the Improve and Control phases, and agree it with the sponsor.