Sub topic 3
Turning Variances into Risks and Issues
This chapter assumes you know what a baseline is, can compute a simple schedule or cost variance (actual minus plan), and can read a task list or burndown chart.
From variance to risk or issue
A variance is a gap that already happened or is measurable now. A risk is an event that might happen and would hurt the plan. An issue is a problem that has already happened and needs a response.
Record each significant variance in the risk and issue log. Ask two questions:
- Has the gap already happened? If yes, log an issue.
- Could the gap grow if nothing changes? If yes, log a risk with a likelihood and impact.
Choosing a corrective action
Pick the smallest action that closes the gap. Options include adding resources, reducing scope, changing the sequence of work, or accepting the variance and monitoring it.
def suggest_action(cpi, spi):
if cpi >= 0.95 and spi >= 0.95:
return "monitor"
if cpi < 0.80 or spi < 0.80:
return "change request or rebaseline"
return "corrective action"
print(suggest_action(cpi=0.89, spi=0.80))
# change request or rebaseline
print(suggest_action(cpi=0.92, spi=0.97))
# corrective actionChange control and when to rebaseline
Use change control for any change to scope, schedule, or cost that the sponsor must approve. Rebaseline only when the original plan can no longer serve as a useful measure, for example after an approved scope change. Rebaselining to hide a variance removes the ability to measure progress honestly.
Reporting status on a steady cadence
Send status reports on a fixed schedule, such as weekly. Each report should state:
- Progress against the baseline, with the variance values
- The forecast final cost and completion date
- Open risks and issues, with owners
- Decisions needed from the sponsor
| Section | Content |
|---|---|
| Progress | Percent complete and variance |
| Forecast | Expected final cost and date |
| Risks and issues | Top items with owners |
| Decisions | What the sponsor must approve |
Exercise:
Exercise
A project has CPI 0.75 and the scope change would need approval. Should you monitor, take corrective action, or submit a change request?
Show answer
Submit a change request. A CPI of 0.75 is below the 0.80 threshold in the example, and a structural gap needs sponsor approval through change control.