Break the work into measurable pieces
Prerequisites
You should know basic project terms (scope, schedule, budget, task), be able to read a task list or Gantt chart, and be comfortable with simple arithmetic and ratios. The code example requires Python 3.
Decompose the scope
A work breakdown structure (WBS) is a hierarchy of the deliverables a project produces. Split each deliverable into work packages small enough to estimate, assign, and check. A good package has a clear done condition, one owner, and an estimate in hours or points.
Test each package with one question: can someone say "done" or "not done" without debate? If not, split it again.
Fix a baseline to measure against
A performance measurement baseline is the approved plan for scope, schedule, and cost. Every later comparison uses it. For each package, record the planned start date, planned finish date, and planned cost. Freeze this version and store it where changes are visible.
Without a baseline, "behind" has no meaning.
Measuring progress: rules for percent complete
A progress rule defines how a package earns credit. Choose the rule before work starts.
- 0/100: credit is zero until the package is finished. Use it for short tasks.
- Weighted milestones: split the package into steps with fixed weights, such as design 20 percent, build 60 percent, test 20 percent.
- Units completed: credit per unit, such as pages written out of 40.
Avoid estimates based on feel. Teams often report 90 percent complete for weeks.
def percent_complete(steps):
"""steps: list of (weight_percent, done) pairs whose weights sum to 100."""
total = sum(weight for weight, _ in steps)
if total != 100:
raise ValueError("weights must sum to 100")
return sum(weight for weight, done in steps if done)
steps = [(20, True), (60, True), (20, False)]
print(percent_complete(steps)) # 80Tracking milestones and the schedule
A milestone is a dated checkpoint, such as "design approved." Record each milestone's planned date and its forecast date. A milestone that slips more than one week needs a note in the status report.
Exercise
A package has three weighted steps: design 30 percent, build 50 percent, and test 20 percent. Design and build are done, but test is not. What percent complete is the package under the weighted milestone rule?
Show answer
80 percent, because 30 + 50 = 80 and test contributes nothing until it is done.