Sub topic 14
Worked example: planning a release
Assume you know basic product terms such as feature, backlog, stakeholder, and release. You also understand that Kano categories describe customer satisfaction, while MoSCoW categories describe the commitment for a fixed release.
A team has 17 effort points available for its next release. It combines Kano survey results with stakeholder review. The Kano results are shown as the category with the most responses. The Better and Worse values summarize the possible effect on satisfaction.
| Feature | Kano result | MoSCoW proposal | Effort |
|---|---|---|---|
| Account recovery | Must-be | Must | 5 |
| Search | One-dimensional | Must | 5 |
| CSV export | One-dimensional | Should | 4 |
| Dark mode | Attractive | Could | 3 |
| Single sign-on | Attractive | Won't have | 6 |
The team does not treat the Kano category as an automatic priority. Account recovery is Must because users need a reliable way to regain access. Search is also Must because the release supports a large catalog, and users cannot complete their main task without it.
CSV export improves satisfaction in proportion to its quality, but users can complete the main workflow without it. The team therefore labels it Should. Dark mode is a possible delight, but it does not address the release goal, so it is Could. Single sign-on receives positive customer reactions, but its effort is too high for this release. It becomes Won't have for now.
Check the fixed capacity
The selected work uses 5 + 5 + 4 + 3 = 17 effort points, exactly matching capacity. The Must items use 10 points. Their share of planned effort is about 59%, close to the commonly used guideline of keeping Must work near 60%. This leaves room for Should and Could work without making the release too fragile.
items = [
{"name": "Account recovery", "effort": 5, "moscow": "must"},
{"name": "Search", "effort": 5, "moscow": "must"},
{"name": "CSV export", "effort": 4, "moscow": "should"},
{"name": "Dark mode", "effort": 3, "moscow": "could"},
{"name": "Single sign-on", "effort": 6, "moscow": "wont"},
]
capacity = 17
planned = [item for item in items if item["moscow"] != "wont"]
planned_effort = sum(item["effort"] for item in planned)
must_effort = sum(item["effort"] for item in planned
if item["moscow"] == "must")
print(f"Planned effort: {planned_effort}/{capacity}")
print(f"Must share: {must_effort / planned_effort:.0%}")If an unexpected task consumes two points, the team should remove or reduce a Could item first. It should not silently remove part of a Must item. If the team cannot fit all Must work, the category is probably disputed or the release goal is too large.
Make the decision visible
The release plan can be represented as a decision flow.
The team should record why each Must item is necessary and who agreed with the decision. This prevents a stakeholder from later treating every preferred feature as mandatory. It should also revisit the labels when customer needs, regulations, or the release goal change.
Exercise
Capacity falls from 17 to 14 effort points. Which item should the team remove first, and what should it do if a stakeholder objects?
Show answer
Remove Dark mode, the Could item, first. If the stakeholder objects, compare the feature with the release goal and customer evidence, then negotiate a smaller scope or move another non-Must item rather than quietly dropping a Must item.