Sub topic 3
Must, Should, Could and Won't Have
This chapter assumes you know basic product terms such as feature, requirement, backlog, stakeholder, and release. It also assumes that a release has limited time, budget, or team capacity.
What MoSCoW categories mean
MoSCoW is a prioritization method. It groups backlog items by how important they are for a specific delivery period. The letters represent:
- Must have: The release cannot succeed without this item.
- Should have: The item is important, but a workable alternative exists.
- Could have: The item is useful, but its absence has little effect.
- Won't have this time: The team agrees not to deliver the item in this release.
| Category | Decision test | If the item is missing |
|---|---|---|
| Must | Does the release fail, become unsafe, or break a firm obligation without it? | The release goal is not met |
| Should | Is it important, but can users work around its absence? | Users can still complete the main task |
| Could | Would it improve the experience without changing the core outcome? | The impact is small |
| Won't | Is it outside the current release boundary? | Nothing changes for this release |
The categories apply to a particular release, not permanently to a product. A feature could be a Should for a pilot and a Must for a later regulated launch.
Must have
A Must is essential to the release outcome. Typical reasons include:
- It supports the primary user journey.
- It satisfies a legal, security, safety, or contractual requirement.
- Without it, another Must cannot operate.
- Its absence would make the product unusable for the target customer.
Use the category sparingly. If every item is a Must, the team has not made a useful priority decision. A claimed Must should have a clear failure statement, such as “Without account recovery, locked-out users cannot regain access.”
A technical dependency is not automatically a Must. A particular database or framework may be replaceable. The user or business outcome it enables may be the real Must.
Should have
A Should adds important value, reduces risk, or supports a significant user group. However, the team can release without it by using a workaround, a manual process, or a simpler version.
For example, a reporting export might be a Should if users can view the same information in the application and copy it manually. The workaround should be realistic. A painful or expensive workaround may indicate that the item is actually a Must.
Could have
A Could is desirable but has limited effect on the release goal. These items are often removed when estimates increase. Examples include an extra sorting option, a visual refinement, or a convenience shortcut.
Could items should still have acceptance criteria and estimates. Calling something a Could does not mean it is free. It means the team accepts delivering without it.
Won't have this time
A Won't item is deliberately outside the current release. This is a commitment about scope, not a permanent rejection. Recording it prevents repeated debate and makes the boundary visible.
“Won't” should include the words “this time.” The product team may reconsider the item after learning from users, reviewing capacity, or changing the release goal.
Making disputed categories explicit
When stakeholders disagree, compare each item against the same questions:
- What release outcome does this item support?
- What happens if the team removes it?
- Is the workaround available, affordable, and acceptable?
- Is the item required by law, contract, safety, or security?
- Can a smaller version meet the same need?
Document the reason for each Must and Should. Then review the list against actual capacity. A release plan with more Must work than the team can complete is not a plan. The team must reduce scope, split items, change the release date, or add capacity.
Exercise
A mobile app release has login, password recovery, profile themes, and CSV export. Users cannot regain access without password recovery. They can view reports in the app but cannot download them. Classify the four items if the release goal is secure account access and basic reporting.
Show answer
Login and password recovery are Must items. CSV export is a Should because users have a workable, though less convenient, alternative. Profile themes are Could items because they do not affect the release goal.