Sub topic 10
Step 5: Recognizing revenue over time or at a point in time
This chapter assumes you can post basic journal entries, you know accrual accounting, and you have read Steps 1 to 4. You already know the performance obligations in a contract and the price allocated to each. Step 5 answers one question: when does each obligation turn into revenue?
The core test
An entity recognizes revenue when it satisfies a performance obligation. That happens when control of the promised good or service passes to the customer. Control means the customer can direct the use of the asset and obtain substantially all of its remaining benefits.
Apply the test to each performance obligation separately. Ask first whether it is satisfied over time. If it is not, it is satisfied at a point in time. You do not get to choose. The standards set the criteria, and the default is point in time.
The three over-time criteria
A performance obligation is satisfied over time if any one of these is met:
- The customer receives and consumes the benefits as the entity performs. Routine services such as cleaning or payroll processing are typical.
- The entity's performance creates or enhances an asset the customer controls as it is created. An example is building on the customer's own land.
- The asset has no alternative use to the entity, and the entity has an enforceable right to payment for performance completed to date.
Criterion 3 needs both parts. A custom-built machine can have no alternative use. If the contract lets the customer walk away without paying for work done, the obligation is not over time.
Point in time: when does control pass?
If no over-time criterion is met, look for the moment control transfers. The standards list indicators. No single one decides the matter, and you weigh them together:
- The entity has a present right to payment.
- The customer has legal title.
- The customer has physical possession.
- The customer has the significant risks and rewards of ownership.
- The customer has accepted the asset.
For a product sold with standard delivery terms, this is often shipment or delivery. Revenue is then recognized in full on that date.
Over time: recognize with a measure of progress
For an over-time obligation, revenue is recognized by applying a measure of progress to the amount allocated to it. The next chapter covers input and output methods in detail. A short example shows the mechanics.
A contractor builds a facility on the customer's land for $1,000,000. Estimated total cost is $800,000, and costs to date are $200,000. Using cost-to-cost, progress is 25%.
price = 1_000_000
estimated_total_cost = 800_000
cost_to_date = 200_000
revenue_recognized_before = 0
progress = cost_to_date / estimated_total_cost
cumulative_revenue = price * progress
revenue_this_period = cumulative_revenue - revenue_recognized_before
print(progress, revenue_this_period) # 0.25 250000.0Revenue is computed on a cumulative basis, then reduced by revenue already recognized. This lets later changes in estimates flow through the current period as a catch-up adjustment.
Common errors
- Treating an entire contract as over time or at a point in time. Test each performance obligation. A contract can contain both kinds.
- Recognizing revenue because cash was received. Billing and payment affect the balance sheet, not the timing of revenue.
- Missing the enforceable right to payment in criterion 3. Without it, a customized asset is still recognized at a point in time.
- Ignoring the mismatch between billing and performance. That mismatch creates the contract assets and liabilities in a later chapter.
Timing and the balance sheet
Suppose a customer pays $1,200 in advance for a one-year subscription. The entity has not yet performed, so it records a liability.
Dr Cash 1,200
Cr Contract liability 1,200
Each month:
Dr Contract liability 100
Cr Revenue 100Exercise
A manufacturer builds a specialized machine to a customer's design. It has no alternative use to the manufacturer. The contract says the customer may cancel at any time and pay nothing for work done. When is revenue recognized?
Show answer
At a point in time, when control transfers. The no-alternative-use condition is met, but the entity has no enforceable right to payment for work completed to date, so criterion 3 fails. No other over-time criterion applies.
Exercise
A contractor has recognized $250,000 of a $1,000,000 contract. Cost to date is now $500,000 and the estimated total cost is still $800,000. How much revenue is recognized this period?
Show answer
Progress is 500,000 / 800,000 = 62.5%. Cumulative revenue is $625,000. Subtract the $250,000 already recognized to get $375,000 for this period.