Accounting for contract modifications
This chapter assumes you know the five steps, how to identify performance obligations, and how to allocate a transaction price using standalone selling prices (SSP).
What a modification is
A contract modification is a change in the scope or price of a contract, or both, that the parties approve. Approval can be written, oral, or implied by customary business practice. The change must create or change enforceable rights and obligations.
Sometimes the parties agree on a change in scope but not yet on the price. This is often called an unpriced change order. The entity estimates the change in price using the variable consideration rules, including the constraint. It then applies the modification guidance below.
The three treatments
The standards give three outcomes. You choose among them with two questions: does the modification add distinct goods or services, and does the added price reflect their SSP?
- Separate contract. Account for the added goods or services on their own. The original contract is untouched.
- Termination and new contract (prospective). Combine the unrecognized original consideration with the new consideration. Allocate the total to the remaining obligations. Revenue already recognized is not changed.
- Part of the existing contract (cumulative catch-up). This applies when the remaining goods or services are not distinct, as with a partly complete construction project. Update the transaction price and the progress measure. Record the effect on revenue at the modification date.
A single modification can have both effects. In that case, apply the matching treatment to each part.
Worked example
A customer buys 100 units at $10 each, so the contract price is $1,000. After 60 units are delivered, the customer orders 40 more units. The SSP is $10 per unit.
- Case A: the extra units cost $10 each. The price reflects SSP and the units are distinct, so this is a separate contract. The original contract continues at $10 per unit.
- Case B: the extra units cost $9 each. The price does not reflect SSP, but the remaining units are distinct from those already delivered. Treat this as a prospective change.
For Case B, the remaining consideration is the 40 undelivered original units at $10 plus the 40 new units at $9. That total is spread over 80 remaining units.
# Case B: prospective treatment of a contract modification.
original_remaining_units = 40 # 100 ordered - 60 delivered
original_price = 10
added_units = 40
added_price = 9
remaining_consideration = (original_remaining_units * original_price
+ added_units * added_price)
remaining_units = original_remaining_units + added_units
price_per_unit = remaining_consideration / remaining_units
print(remaining_consideration, remaining_units, price_per_unit)
# 760 80 9.5The $600 already recognized for the first 60 units stays as it is. Each of the remaining 80 units is recognized at $9.50.
Common errors
- Restating past revenue under the prospective method. Only the catch-up method changes revenue already recognized, and it does so through a current-period adjustment.
- Testing only the price. A price at SSP is not enough. The added goods or services must also be distinct.
- Ignoring unapproved changes. Do not account for a change until it is approved. Once it is approved but unpriced, estimate the price.
Exercise
A contractor is building a single integrated facility under one performance obligation that is 40% complete. The customer approves a design change that raises the price and the total estimated cost. Which treatment applies, and how is it recorded?
Show answer
The remaining work is not distinct from the work already done, because it is part of one integrated obligation. So the change is accounted for as part of the existing contract (cumulative catch-up). The entity updates the transaction price and the measure of progress. It then records the resulting change in cumulative revenue as an adjustment in the period of the modification.