Measuring Progress Toward Satisfaction of an Obligation
This chapter assumes you know the five steps, can tell an over-time obligation from a point-in-time one, and can post basic journal entries. Once a performance obligation qualifies for over-time recognition, the entity must choose one method to measure how far along it is. This chapter covers that choice, the calculations, and the errors that most often appear in practice.
The objective: depict transfer of control
Both ASC 606 and IFRS 15 say the measure of progress must depict the entity's performance in transferring control of the goods or services to the customer. The method is not a free choice. It must fit the nature of what is promised.
Three rules apply to every method:
- Apply one method to each performance obligation, and use it consistently for similar obligations in similar circumstances.
- Exclude inputs or outputs that do not depict performance. Examples are uninstalled materials and costs of inefficiency.
- Update the measure at each reporting date, because progress is an estimate that changes.
The two families of methods are output methods and input methods.
| Family | Measures | Typical examples | Main weakness |
|---|---|---|---|
| Output methods | Value transferred to the customer | Surveys of work performed, units delivered, milestones reached | The output may not be directly observable, or may ignore work in progress |
| Input methods | The entity's effort or resources used | Costs incurred, labor hours, machine hours | Inputs may not map to the transfer of control |
Output methods
An output method recognizes revenue based on what the customer has received to date. It is the most faithful depiction when it can be observed directly.
- Units delivered or produced. Suitable when each unit has a similar value to the customer.
- Milestones reached. Suitable when milestones track real value transferred. A milestone that merely marks an internal checkpoint does not.
- Surveys or appraisals. For example, an architect's certified percentage of completion.
The right-to-invoice practical expedient
If the entity has a right to consideration from the customer in an amount that corresponds directly with the value transferred to date, it may recognize revenue in the amount it has the right to invoice. A typical case is a service billed at a fixed rate per hour. If the contract pays $120 per hour of consulting, then revenue is $120 for each hour worked.
The expedient does not apply when the invoice amount does not track value. Front-loaded billing or large up-front fees fail the test.
Limits of output methods
Output methods can misstate progress when work in progress at the reporting date is material but not yet reflected in a unit or milestone. If the entity cannot observe the output without undue cost, an input method is the better choice.
Input methods
An input method recognizes revenue based on the entity's efforts relative to the total expected efforts. The most common version is cost-to-cost, where progress is costs incurred to date divided by estimated total costs.
The formula is:
- Progress % = cost to date ÷ estimated total cost
- Cumulative revenue = transaction price × progress %
- Revenue this period = cumulative revenue − revenue recognized in earlier periods
Worked example: first period
A contractor builds a facility for a transaction price of $1,000,000. Estimated total cost is $800,000. At the end of year 1, costs incurred are $200,000.
# Construction contract recognized over time using a cost-to-cost input method.
price = 1_000_000
estimated_total_cost = 800_000
cost_to_date = 200_000
revenue_recognized_before = 0
progress = cost_to_date / estimated_total_cost # 0.25
cumulative_revenue = price * progress # 250000.0
revenue_this_period = cumulative_revenue - revenue_recognized_before
print(progress, revenue_this_period) # 0.25 250000.0Revenue for year 1 is $250,000 and cost of revenue is $200,000, giving a gross profit of $50,000.
Worked example: a change in estimate
Estimates change. Suppose in year 2 cumulative costs reach $600,000, and the estimated total cost rises to $900,000. Progress is now 600,000 ÷ 900,000, which is 66.67%.
price = 1_000_000
estimated_total_cost = 900_000
cost_to_date = 600_000
revenue_recognized_before = 250_000
progress = cost_to_date / estimated_total_cost
cumulative_revenue = price * progress
revenue_this_period = cumulative_revenue - revenue_recognized_before
print(round(progress, 4), round(cumulative_revenue, 2), round(revenue_this_period, 2))
# 0.6667 666666.67 416666.67Cumulative revenue is $666,667, so year 2 revenue is $416,667. The change in estimate is accounted for as a cumulative catch-up adjustment in the period of change. Prior periods are not restated. The catch-up is a consequence of applying the new percentage to the whole contract and subtracting what was already recognized.
Common errors with cost-to-cost
Cost-to-cost works only if costs are proportionate to progress. Two adjustments are required.
Wasted costs
Costs that do not contribute to progress are excluded from the numerator. Examples are abnormal amounts of wasted materials, labor, or rework due to errors. Including them would recognize revenue for effort that gave the customer nothing. Such costs are expensed as incurred, and the estimate of total cost is adjusted so the percentage is not distorted.
Uninstalled materials
Suppose the entity buys a large piece of specialized equipment for a project, and the customer does not yet have control of it. If the cost is significant relative to total expected cost, the entity should not simply let that cost raise progress. The standards say that when the cost is not distinct and the customer obtains control well before installation, the entity recognizes revenue for the transferred good at an amount equal to its cost. That is a zero-margin treatment. The entity must also exclude that cost when measuring progress on the rest of the work.
Worked example: uninstalled materials
A $1,000,000 contract has estimated total cost of $800,000. This includes $100,000 for a custom generator that the customer controls on delivery but that is installed later. At year-end the entity has incurred $300,000. That total includes the full $100,000 generator and $200,000 of other costs.
- Remove the generator from both sides of the ratio. Other costs incurred are $200,000. Estimated other costs are $700,000.
- Progress on the remaining work is 200,000 ÷ 700,000, which is 28.57%.
- Revenue for the generator is recognized at cost, $100,000.
- The price attributable to the remaining work is $1,000,000 less $100,000 of generator revenue, a base of $900,000. Revenue on it is 900,000 × 28.57%, or $257,143.
Total revenue is $357,143. A naive calculation of 300,000 ÷ 800,000 would give $375,000. The difference arises because the generator is passed through at zero margin.
Choosing the method
The diagram is a guide, not a hierarchy written in the standards. The requirement is to choose the method that best depicts transfer of control. Output methods are often preferred in principle because they measure value to the customer directly.
Measuring progress when you cannot yet estimate it
Sometimes the entity cannot reasonably measure the outcome, for example early in a contract. If it expects to recover the costs incurred, it recognizes revenue only to the extent of costs incurred. This is a zero-margin approach and continues until the outcome can be measured reliably.
Other points to watch
- Estimate quality. The estimated total cost is a judgment. Poor estimates move revenue between periods, so controls over the estimate matter as much as the arithmetic.
- Loss-making contracts. Revenue recognition does not remove the need to assess onerous contracts. Under US GAAP and IFRS, a separate loss provision may apply when total costs exceed the price. The rules differ by framework and industry, so check the applicable guidance.
- Variable consideration. If the transaction price changes, the new price is applied to the whole contract using the current progress percentage, with a catch-up in the period of change.
- Time-based measures. Straight-line recognition suits stand-ready obligations, such as a one-year subscription, where effort is spread evenly. Recording $100 per month on a $1,200 subscription is an output-style, time-elapsed measure.
- Disclosure. Entities must disclose the methods used and explain why they faithfully depict the transfer of goods or services.
Summary
Choose the method that best shows control passing to the customer. Use output methods when value transferred is observable. Use cost-to-cost when it is not, and strip out wasted costs and uninstalled materials. Recompute cumulative revenue at every reporting date and book the difference as the period's revenue.
Exercise
A contract has a transaction price of $600,000 and estimated total cost of $450,000. At the end of year 1, costs incurred are $180,000, and the estimate has not changed. In year 2, cumulative costs are $360,000 and the estimated total cost rises to $480,000. How much revenue is recognized in year 2?
Show answer
Year 1 progress is 180,000 ÷ 450,000 = 40%, so year 1 revenue is $240,000. Year 2 progress is 360,000 ÷ 480,000 = 75%, so cumulative revenue is $450,000. Year 2 revenue is $450,000 − $240,000 = $210,000, which includes the catch-up from the changed estimate.
Exercise
A cleaning company bills $80 per hour for services, and the customer receives value for each hour worked. Which method of measuring progress is the simplest to use, and what condition must hold?
Show answer
The right-to-invoice practical expedient. Revenue equals $80 for each hour worked. The condition is that the amount the entity can invoice corresponds directly with the value transferred to the customer to date.