Sub topic 9
Accounting for Contract Modifications
This chapter assumes you know double-entry bookkeeping, accrual accounting, and the first four steps of the model: identifying the contract, identifying performance obligations, determining the transaction price, and allocating it. Contract modifications sit on top of those steps. A modification changes the scope or price of a contract, and you must decide how to reflect that change in revenue.
What counts as a modification
A contract modification is a change in the scope or price (or both) of a contract that the parties have approved. Approval can be written, oral, or implied by customary business practice. The change must also be enforceable under the law that governs the contract.
Two situations are common:
- Approved change in scope, with an agreed price. The customer orders more units, or removes a service.
- Approved change in scope, with price not yet agreed. The parties agree the scope has changed but have not settled the price. This is sometimes called an unpriced change order.
For an unpriced change, you estimate the price change using the variable consideration guidance from Step 3, including the constraint. You do this only if the parties have approved the change in scope and the change is enforceable. If the parties are still disputing whether the change was ever approved, there is no modification yet.
A modification is not the same as a variable term that was already in the original contract. A volume rebate or performance bonus written into the original terms is variable consideration. A modification is a new change to those terms.
The decision path
The standards give three treatments. Which one applies depends on two questions:
- Does the modification add distinct goods or services?
- Is the price increase equal to the standalone selling price of those additions, adjusted for the circumstances of the contract?
If the answer to both is yes, the modification is treated as a separate contract. Otherwise, you look at whether the remaining goods or services are distinct from those already transferred.
Treatment 1: a separate contract
When the modification adds distinct goods or services and the added price reflects their standalone selling price, you account for the addition as a new, separate contract. The original contract keeps its accounting, and nothing is reallocated.
The phrase "adjusted for the circumstances of the contract" matters. A seller might charge an existing customer less than the usual list price for an add-on because it avoids selling costs. If that discount reflects what the seller would really charge that customer, the price can still count as the standalone selling price.
Example. A company agrees to sell 100 units at $10 each. After 60 units have been delivered, the customer orders 20 more units at $9 each. The company's usual price for such a quantity is $9, and the units are distinct. The 20 units are a separate contract at $9. The remaining 40 units of the original order stay at $10.
Treatment 2: prospective, as a termination and new contract
If the modification does not meet the separate contract test, but the remaining goods or services are distinct from those already transferred, you treat the modification as if the old contract ended and a new one began. Revenue already recognized stays as it is.
The transaction price for the new contract is the sum of:
- the consideration promised by the customer that was included in the estimate of the transaction price but not yet recognized as revenue, and
- the consideration promised as part of the modification.
You allocate this combined amount across the remaining performance obligations, using the relative standalone selling price method from Step 4.
Example. Take the same 100-unit contract at $10 each. After 60 units, the customer orders 20 more units, but at $7 each. This is a discount that does not reflect the standalone price of $9. The remaining 40 original units are distinct from the 60 already delivered.
- Unrecognized consideration from the original contract: 40 × $10 = $400.
- Consideration from the modification: 20 × $7 = $140.
- Combined: $540 for 60 remaining units, or $9 per unit.
The company recognizes $9 per unit for the remaining 60 units. The $600 recognized on the first 60 units is not touched.
Treatment 3: cumulative catch-up
If the remaining goods or services are not distinct from those already transferred, they form part of a single performance obligation that is partly satisfied at the modification date. In that case you cannot start fresh. Instead, you treat the modification as part of the original contract and update the measure of progress.
The effect on revenue is recognized as an adjustment at the modification date, either increasing or decreasing revenue. This is called a cumulative catch-up adjustment.
This is typical of long-term construction or customized development work, where the pieces are highly interdependent and form one combined output.
Worked calculation
A builder has a fixed-price contract for $1,000,000 with estimated total cost of $800,000. The builder recognizes revenue over time using a cost-to-cost measure of progress. At the end of the period, costs to date are $400,000, so progress is 50% and cumulative revenue is $500,000.
The customer then approves a change that adds $200,000 to the price and $120,000 to the estimated cost. The work is not distinct from the work already done, so the builder uses the catch-up method.
# Cumulative catch-up after a contract modification (cost-to-cost method).
original_price = 1_000_000
original_estimated_cost = 800_000
cost_to_date = 400_000
# Revenue recognized before the modification
progress_before = cost_to_date / original_estimated_cost # 0.50
revenue_before = original_price * progress_before # 500,000
# After the modification
new_price = original_price + 200_000 # 1,200,000
new_estimated_cost = original_estimated_cost + 120_000 # 920,000
progress_after = cost_to_date / new_estimated_cost
cumulative_revenue_after = new_price * progress_after
catch_up = cumulative_revenue_after - revenue_before
print(f"Progress before: {progress_before:.4f}")
print(f"Progress after: {progress_after:.4f}")
print(f"Cumulative revenue after: {cumulative_revenue_after:,.2f}")
print(f"Catch-up adjustment: {catch_up:,.2f}")Running this gives progress of 0.4348 after the change, cumulative revenue of $521,739.13, and a catch-up adjustment of $21,739.13. The builder records this additional revenue in the period of the modification. Later periods continue to use the new price and the new estimated cost.
Notice that the percentage of completion fell from 50% to about 43.5%. Revenue still rose, because the price rose by more than the cost changed in proportion.
Dr Contract asset (or receivable) 21,739.13
Cr Revenue 21,739.13Mixed modifications
A modification can touch several parts of a contract. Some remaining goods or services may be distinct from what has been transferred, and others may not be. In that case you apply the prospective treatment to the distinct ones and the cumulative catch-up treatment to the rest, within the same modification.
This is easy to get wrong, so work through it in this order:
- List the remaining goods and services, including any added by the modification.
- Check each one for distinctness from what has already transferred.
- Group them into the distinct set and the non-distinct set.
- Allocate the modification's effect to each group, then recognize accordingly.
Common errors
- Treating every price increase as a separate contract. The price must reflect standalone selling price, and the additions must be distinct. A larger order at a discount fails the test.
- Restating revenue already recognized under the prospective method. Treatment 2 never changes past revenue. Only Treatment 3 produces a catch-up.
- Skipping the distinctness test on the remaining items. The choice between Treatments 2 and 3 depends on it, so check it before choosing a method.
- Recognizing an unpriced change as zero. If the scope change is approved, estimate the price with the constraint. Do not wait until the price is finalized, and do not ignore the work.
- Forgetting the constraint on the new estimate. Estimates added through a modification are variable consideration if the price is uncertain, so apply the constraint.
- Mixing up modification and change in estimate. If the cost to finish rises with no change in contract scope or price, that is a change in estimate of progress, not a modification.
Where this fits
Modifications reuse tools from earlier steps: distinctness from Step 2, constraint from Step 3, and relative standalone selling price from Step 4. The result feeds Step 5, because the measure of progress and the remaining transaction price both change after a modification.
Exercise
A company has a contract to deliver 50 units at $20 each. After 30 units are delivered, the customer orders 10 more units at $15 each. The usual standalone selling price of a unit is $20, and all units are distinct. How should the company account for the modification, and what price per unit applies to the remaining units?
Show answer
The additional price of $15 does not equal the standalone selling price of $20, so the modification is not a separate contract. The remaining units are distinct from those already delivered, so use the prospective treatment. Unrecognized consideration from the original contract is 20 × $20 = $400. Consideration from the modification is 10 × $15 = $150. The combined $550 is allocated across 30 remaining units, giving about $18.33 per unit. Revenue already recognized on the 30 delivered units ($600) is unchanged.
Exercise
A contractor is building a single custom facility under a $2,000,000 fixed-price contract with estimated total cost of $1,500,000, and has incurred $750,000. A change order adds $300,000 to the price and $200,000 to estimated cost. The work is not distinct from the work already done. Revenue recognized to date is $1,000,000. What is the cumulative catch-up adjustment?
Show answer
Revenue to date is $2,000,000 × (750,000 / 1,500,000) = $1,000,000. After the change, the price is $2,300,000 and estimated cost is $1,700,000. Progress is 750,000 / 1,700,000 = 0.44118. Cumulative revenue is $2,300,000 × 0.44118 = about $1,014,706. The catch-up adjustment is about $14,706 of additional revenue, recognized in the period of the modification.