Sub topic 3
Skills: unused talent and ideas
This chapter assumes you know how a process turns inputs into outputs and can read simple time figures.
The eighth waste in TIMWOODS is skills: unused talent and ideas. It happens when people's knowledge, experience, or suggestions go unused. A worker who knows the fastest fix for a jam but is never asked is a waste of that talent. The organization pays for the skill and gets none of its benefit.
How the wastes feed each other
Wastes often cause one another. Overproduction creates inventory. Inventory creates waiting, because items sit in queues. Waiting hides defects, because problems surface late.
Finding waste: gemba walks and value stream maps
A gemba walk means visiting where the work happens and watching it. Walk the process yourself, then draw a value stream map. List each step, its time, and whether it adds value for the customer. Waiting usually shows up as the largest gap.
Measuring waste: lead time, cycle efficiency, and Little's Law
Lead time is the elapsed time from request to delivery. Process cycle efficiency (PCE) is value-added time divided by lead time.
steps = [
("Receive request", 5, False),
("Wait in queue", 240, False),
("Prepare quote", 30, True),
("Wait for approval", 120, False),
("Send quote", 5, True),
]
lead_time = sum(minutes for _, minutes, _ in steps)
value_added = sum(minutes for _, minutes, adds_value in steps if adds_value)
print(f"Lead time: {lead_time} min")
print(f"Process cycle efficiency: {value_added / lead_time:.1%}")The lead time is 400 minutes and the PCE is about 8.8%. Most of the elapsed time is waiting.
Little's Law states that average lead time equals work in progress divided by throughput. If 60 items are in progress and 20 finish per day, lead time is 3 days. Halving the queue to 30 items halves the lead time to 1.5 days.
Tracing a waste to its root cause with the 5 Whys
Ask "why" repeatedly, usually about five times, until you reach a cause you can fix. For example: the quote is late. Why? It waited for approval. Why? The approver was out. Why? No backup was named. Why? No one owns the approval rules. The fix is to name a backup approver.
Choosing countermeasures: 5S, pull, standard work, poka-yoke
Match each waste to a fix.
| Waste | Countermeasure |
|---|---|
| Inventory | Pull and kanban |
| Motion and clutter | 5S |
| Defects | Poka-yoke (mistake-proofing) |
| Variation in method | Standard work |
| Unused talent | Cross-training and idea boards |
Keeping the gains: standard work, audits, and continuous improvement
Write the improved method down as standard work. Audit it on a schedule. Ask the people who do the work for the next improvement. They hold the most useful knowledge about the process, which makes them the best source of ideas and the best check on whether the fix still holds.
Exercise
A process has a lead time of 400 minutes, and 35 minutes of it adds value. What is the process cycle efficiency?
Show answer
35 / 400 = 0.0875, which is about 8.8%. Most of the time is waiting, not work.