This chapter covers the second half of step 4 in the CompTIA process: carrying out the plan you wrote, or handing it to someone else. It assumes you can already name the six steps and have read the chapters on testing a theory, escalation, and planning. You should also be comfortable with basic Windows command-line tools.
What this step is
Once a test confirms the cause, you have a plan. Implementing the solution means you carry out that plan, or you escalate the work to someone with the authority or skill to do it. CompTIA treats both as correct outcomes. Escalating is not a failure. Making a change you are not qualified or approved to make is the real mistake.
Before you touch anything
Check these items first, in this order:
- Confirm a current backup exists for any data the fix could affect.
- Confirm the change is approved if your organization uses change management.
- Check safety: power down and unplug hardware, use an ESD strap, and follow your site's rules.
- Review the plan and note how to undo each action.
Make one change at a time
Apply one change, then check its effect. If you change three things and the problem disappears, you do not know which one fixed it. You also cannot cleanly undo a change that made things worse.
For the corrupted-files theory from the testing chapter, the fix is System File Checker. Run it from an elevated command prompt (one started with "Run as administrator"):
sfc /scannowFor the loose-cable ticket, the fix is two small actions: reseat the cable, then renew the IP lease.
ipconfig /renewEach action is small, reversible, and followed by a check.
Escalate when the plan is beyond you
Escalate when the fix needs access, skill, or approval you do not have. Examples include a server-side change, a warranty repair, or a vendor-only firmware update. Hand over your notes: the symptoms, what you tested, and what you ruled out. That way the next person does not repeat your work.
Common errors
| Error | Why it fails |
|---|---|
| Skipping the backup | A failed fix can cause permanent data loss. |
| Changing several things at once | You cannot tell which change worked. |
| Fixing without approval | It can break change-management rules and affect other users. |
| Escalating without notes | The next technician starts from zero. |
| Declaring success right away | Step 5 still has to confirm that the whole system works. |
When the change is done, do not close the ticket. Move on to verification.
Exercise
A technician confirms that a corrupted driver is causing a user's display problem and has written a plan to replace it. The user's work files are stored only on that PC. What should the technician do before applying the fix, and why?
Show answer
Confirm that the user's data is backed up, and check that the change is approved if the organization requires it. The fix could fail or make the system unbootable, and a backup prevents permanent data loss. The technician then applies the single change and moves on to verification.
Exercise
You apply a fix and the problem seems gone, but you also changed a second setting "just in case." What went wrong in your implementation?
Show answer