Sub topic 12
Change Management and Safety During the Fix
This chapter assumes you know the six steps in order and have a plan of action from Step 4. Here you will see what must happen between "I have a plan" and "I changed the system."
Why a plan is not permission
A technician often has the skill to apply a fix. That does not mean the fix may be applied right now. In a business, many systems depend on each other. A change to one server, switch, or shared application can affect people who never opened a ticket.
Change management is the formal process an organization uses to approve, schedule, and record changes. CompTIA tests it as part of the plan of action, before implementation.
What a change request contains
A typical change request covers these items:
- Scope: which systems and users the change touches.
- Risk analysis: what could go wrong and how likely it is.
- Rollback plan: the exact steps to undo the change if it fails.
- Backup confirmation: proof that data and configuration were saved first.
- Schedule: a window that limits business impact, such as after hours.
- Approval: sign-off from the change board or the system owner.
Emergency changes exist for outages that cannot wait. They are still documented, usually with approval given quickly and paperwork finished afterward.
Safety during the fix
Safety applies to people and to equipment. Check these before you start work:
| Hazard | Precaution |
|---|---|
| Electrostatic discharge (ESD), a static shock that can damage components | Wear an ESD strap and work on an antistatic mat |
| Electrical shock | Power off and unplug the device before opening it |
| Power supplies and CRT-style or high-voltage parts | Do not open them. Send them to qualified service |
| Heavy equipment | Lift with your legs and ask for help |
| Damaged batteries | Handle with care and follow local disposal rules |
Also follow the organization's own rules. These include property handling, data privacy, and which tools you are allowed to install.
Example of a documented change
Change request: Replace failed DIMM in finance workstation FIN-07
Scope: One workstation, one user
Risk: Low. Data is on the network share.
Backup: User profile synced to file server, confirmed 16:40
Window: Friday 18:00-18:30
Rollback: Reinstall original DIMM and set BIOS to default memory settings
Approval: Service desk manager, ticket #4821Exam tips
- If a scenario says a fix is ready but no approval is mentioned, the best next step is usually to follow change management.
- If a scenario involves the possibility of data loss, confirm a backup first.
- A failed change calls for the rollback plan, not improvisation.
Exercise
A technician has tested a theory and confirmed that a faulty switch port causes a department's outage. The technician wants to move the cable to another port on the production switch right away. Which step should come first, and why?
Show answer
Submit a change request, with scope, risk, rollback plan, and approval, as part of the plan of action. Even a small change on shared network gear can affect other users, so it needs approval and a rollback plan before implementation. If the outage is severe, an emergency change process may speed approval, but it is still documented.