Sub topic 4
Total Cost as Fixed Plus Variable
Prerequisites and the short-run setting
This chapter assumes that you know opportunity cost, can read a graph with quantity on the horizontal axis, and can use basic algebra. You should also be familiar with the idea that a firm turns inputs into output.
The short run is a period in which at least one input is fixed. A fixed input cannot be changed quickly. For example, a bakery may be unable to expand its building this month, even though it can change how many workers it schedules.
A firm’s total cost is the cost of all resources used to produce its output. In the short run, total cost has two parts:
- Fixed cost, or total fixed cost (TFC), does not change when output changes.
- Variable cost, or total variable cost (TVC), changes when output changes.
The basic relationship is:
TC = TFC + TVC
Here, TC means total cost at a particular quantity of output.
Fixed cost
Fixed cost is a cost that the firm must pay even when it produces zero units. Rent, property insurance, and some equipment leases are common examples.
If a bakery pays $2,000 per month to rent its building, that $2,000 is fixed in the short run. The bakery owes it whether it produces 0 loaves or 10,000 loaves.
Fixed cost does not mean that the cost can never change. It means that the cost is fixed with respect to current output. A new lease or a larger building could change the fixed cost later.
Variable cost
Variable cost changes as the firm changes its output. Payments for flour, packaging, electricity used by production, and hourly labor may be variable costs.
Variable cost is usually zero when output is zero, but this depends on the cost definition. If a firm has no production-related expenses when it shuts down, then TVC(0) = 0. The total cost at zero output is still positive because the firm must pay its fixed cost:
TC(0) = TFC + TVC(0)
If TFC = $2,000 and TVC(0) = $0, then TC(0) = $2,000.
Building a total-cost schedule
Suppose a firm has a fixed cost of 20. Its variable cost is described by:
TVC(Q) = Q³ - 6Q² + 15Q
To find total cost for each quantity, add 20 to the variable cost.
| Quantity (Q) | Fixed cost | Variable cost | Total cost |
|---|---|---|---|
| 0 | 20 | 0 | 20 |
| 1 | 20 | 10 | 30 |
| 2 | 20 | 14 | 34 |
| 3 | 20 | 18 | 38 |
| 4 | 20 | 28 | 48 |
The difference between total cost and variable cost is 20 at every quantity. This constant difference is the fixed cost.
FC = 20
def variable_cost(q):
return q**3 - 6*q**2 + 15*q
print(" Q TFC TVC TC")
for q in range(0, 9):
tvc = variable_cost(q)
tc = FC + tvc
print(f"{q:2} {FC:5} {tvc:5} {tc:5}")Total cost is a level, or dollar amount, at each output quantity. It does not tell us by itself whether producing another unit is expensive. That question requires marginal cost, which measures the change in total cost when output increases by one unit. Because fixed cost does not change, the change in total cost comes from the change in variable cost:
MC = change in TC / change in Q = change in TVC / change in Q
This equality is important for later cost-curve analysis.
Common errors
- Do not set total cost to zero at zero output when fixed costs exist.
- Do not add fixed cost again for every unit. Add it once to the variable cost at the chosen output.
- Do not confuse a fixed cost with a sunk cost. A sunk cost cannot be recovered, while a fixed cost is defined by whether it changes with current output.
- Keep units consistent. If fixed cost is monthly, variable cost and total cost must also describe one month.
Exercise
A firm has TFC = 50. Its TVC is 0 at Q = 0, 12 at Q = 1, and 21 at Q = 2. What is TC at Q = 2, and why?
Show answer
TC = TFC + TVC = 50 + 21 = 71. Fixed cost is included even though it does not change with output.