Sub topic 9
Managing change with change orders
Prerequisites and scope
This chapter assumes you know what a master service agreement (MSA) and a statement of work (SOW) are, and how a SOW defines scope, deliverables, schedule and fees. If those are unfamiliar, read the earlier chapters first. The chapter is general education, not legal advice. Whether a change is binding without a signed document varies by jurisdiction, so check with counsel.
Why change control exists
No project runs exactly as the SOW describes it. Requirements shift, assumptions turn out wrong, and the client's own staff miss dependencies. If the contract has no way to handle change, two bad outcomes become likely:
- The vendor absorbs extra work without payment, then resents it or cuts quality.
- The client assumes the extra work is included, and a later invoice for it becomes a dispute.
Change control is the agreed process for proposing, pricing, approving and recording changes to the SOW. A change order (also called a change request, variation or amendment, depending on the industry) is the written record of one approved change. It protects both sides. The client gets a price and a date before committing. The vendor gets payment and relief from the original schedule.
Change control sits where two earlier topics meet. The scope section says what is in and out. The pricing section says what the work costs. A change order is the only sanctioned way to move either one.
What counts as a change
A change is anything that alters the SOW's agreed terms. Common triggers:
- Adding, removing or reworking a deliverable.
- Moving a milestone date for a reason other than vendor delay.
- A failed assumption, such as the client not providing test data on time.
- A change in law or in a third-party system the project depends on.
- A change to acceptance criteria after signature.
Not every adjustment needs a change order. Clarifying an ambiguous requirement within existing scope is not a change, though parties often disagree about which side of the line a request falls on. A good SOW makes that line easy to see through its explicit exclusions and assumptions. Many contracts also set a threshold, for example "changes with no effect on fees, schedule or deliverables may be agreed by the project leads by email."
The change control process
A typical process has five steps.
- Request. Either party submits a written change request. It states what is wanted and why.
- Impact assessment. The vendor analyzes the effect on deliverables, schedule, fees and risk. The contract should say who pays for this analysis and how quickly the vendor must respond. Small assessments are often free. Large ones may be chargeable.
- Proposal. The vendor issues a written proposal, often as a draft change order.
- Decision. The client approves, rejects or negotiates. Only named, authorized people may approve.
- Execution and record. Once signed by both parties, the change order amends the SOW. The vendor starts the changed work. Both sides file the document.
What a change order contains
A change order should be short but complete. At minimum it records:
- A number and the SOW it amends.
- Who requested it and the date.
- A description of the change and the reason.
- The effect on deliverables, schedule and fees.
- A statement that all other terms stay unchanged.
- Signature lines for authorized representatives of both parties.
Change Order No. 1 to SOW No. 1
Requested by: [Name, party]
Date: [Date]
Description of change: [What is added, removed or modified]
Reason for change: [Why the change is needed]
Impact on deliverables: [Affected deliverables]
Impact on schedule: [Revised milestone dates, or none]
Impact on fees: [Additional or reduced amount, or none]
All other terms of the SOW remain unchanged.
Approved for Client: ____________ Date: ______
Approved for Vendor: ____________ Date: ______The sentence "All other terms of the SOW remain unchanged" matters. Without it, a later dispute can turn on whether the change order silently altered something else.
Fill in every impact line
Write "none" rather than leaving an impact line blank. A blank line invites the argument that the effect was not considered. If a change affects the schedule and the order says nothing about it, the vendor may later claim an extension while the client claims the original dates still hold.
Pricing a change
How a change is priced depends on the SOW's pricing model.
| Pricing model | How changes are usually priced |
|---|---|
| Fixed fee | The change order adds a fixed amount for the new work, or reduces the fee for removed work. |
| Time and materials | The existing rates apply. The change order may raise the estimate or the not-to-exceed cap. |
| Retainer | The change may shift hours between activities, or it may need a larger retainer for the period. |
The SOW should state the rates or method to use. Without them, every change becomes a fresh negotiation, and the vendor has leverage because the client is already mid-project.
A worked example: a vendor builds a customer portal for a fixed fee of 120,000. Midway, the client asks for a new reporting dashboard. The vendor estimates 80 hours at the SOW's rate of 150 per hour, so the change order adds 12,000, moves the final milestone back by two weeks, and adds a dashboard deliverable with its own acceptance criteria. The new fee total is 132,000, and the order states that.
Change control and the MSA
The MSA usually holds the general change process, and the SOW refers to it, as in the skeleton from the earlier chapter: "Changes follow the change order process in the MSA." A SOW may add details for its project, such as named approvers or response times.
The order-of-precedence clause covers how change orders rank against other documents. In the sample clause from the earlier chapter, a signed change order has the highest priority, but only for the matters it changes. That is why the change order should say exactly what it amends.
Common failure modes
Work starts before signature
The most frequent problem is informal approval. A project manager says "go ahead" in a call or an email, the vendor does the work, and nobody signs. Later the client disputes the invoice. Some contracts address this with a clause stating that no change binds either party unless it is in a signed change order. Courts in some jurisdictions still find that the parties changed the contract by their conduct, or that the client owes payment for benefits received. Other jurisdictions enforce the clause strictly. Do not rely on either result.
A practical approach is a defined urgent path. For example, the client's named representative may authorize work in writing up to a stated amount or number of days while the formal change order is prepared.
Unauthorized approvers
A person who lacks authority may approve a change. The SOW should name who can sign change orders, and ideally set approval levels by value.
Bundled or creeping changes
Many small requests that each seem free can add up to large unpaid work. The vendor should log each request and its effect, even if the answer is "no impact." Some contracts set a cumulative threshold above which a bundled change order is required.
Impact on dependent items
A change to one deliverable can affect acceptance criteria, payment milestones, service levels and the assumptions list. Check each of these when you draft the order.
Disputes about whether something is a change
Parties may disagree on whether a request is in scope. The contract should say what happens in the meantime. A common solution is that the vendor continues the work and the parties escalate through the governance path, with rights reserved.
Vendor-caused change
Rework caused by the vendor's own error or delay is not a client change. The change order process should not be used to charge for it.
Drafting tips
- Define "change" and "change order" in the MSA, and say that only a signed change order amends a SOW.
- Set a response time for impact assessments, such as ten business days.
- Name the authorized approvers for each party, and say how that list is updated.
- Number change orders in sequence and keep a change log.
- State whether work may proceed on a written authorization before signature, and the limits on it.
- Say whether the vendor may decline a change that is technically unfeasible or would breach law.
Exercise
A client's project manager emails the vendor, "Please add the reporting dashboard, we'll sort out the paperwork later." The vendor builds it. The MSA states that changes bind the parties only through a signed change order, and the client now refuses to pay. Name two steps that would have prevented the dispute.
Show answer
First, the vendor should have prepared a change order with the price, schedule effect and acceptance criteria and had an authorized client approver sign it before starting. Second, the contract could have included an urgent authorization path, so that a named client representative can approve limited work in writing up to a stated amount while the change order is drafted. Checking that the project manager was an authorized approver would also have helped.
Exercise
A change order adds a new deliverable and a 12,000 fee but leaves the "Impact on schedule" line blank. What risk does this create, and how do you fix it?
Show answer
The parties may later disagree about whether the milestones moved. The vendor may claim an extension, and the client may insist the original dates apply. Fix it by writing the revised dates, or "none", on every impact line before signature.