Sub topic 6
Acceptance Criteria and the Review Process
This chapter covers how a statement of work (SOW) defines what "done" means, and how the client's review of a deliverable leads to acceptance, rejection or payment. It assumes you have read the earlier chapters on the master service agreement (MSA), the SOW structure, and scope and deliverables. It is general education, not legal advice. Enforceability varies by jurisdiction.
Why acceptance matters
Acceptance is the point where the client confirms that a deliverable meets the agreed standard. Several consequences usually attach to it:
- The vendor becomes entitled to invoice a milestone payment.
- A warranty period often starts running.
- The client's right to reject the work ends, or narrows to defects it could not have found earlier.
- Risk and, in some contracts, ownership of the deliverable pass to the client.
Because so much depends on one decision, both sides need the test for acceptance written down before work starts. Without it, a client can withhold payment by saying it is "not what we expected," and a vendor can demand payment for work that technically exists but does not function.
Acceptance criteria
Acceptance criteria are the conditions a deliverable must satisfy to be accepted. They belong in the deliverables table of the SOW, next to the due date, as in the skeleton from the SOW chapter:
| ID | Deliverable | Acceptance criteria | Due date |
|---|---|---|---|
| D1 | [Name] | [Measurable criteria] | [Date] |
Make criteria measurable
A criterion is measurable when two people can check it independently and reach the same answer. Compare these pairs:
| Vague | Measurable |
|---|---|
| The website loads quickly. | The home page loads in under 3 seconds at the 95th percentile, tested with 500 concurrent users on the staging environment. |
| The report is accurate. | The report totals match the source ledger to the cent for all 12 test months supplied by the client. |
| The system is secure. | The penetration test report lists no open findings rated high or critical. |
| The documentation is complete. | The user guide covers every function in Appendix A and has been reviewed by the client's named trainer. |
Each measurable version names a metric, a threshold, and a test method or test data. Where possible, also name the environment and who runs the test.
Separate objective and subjective standards
Some deliverables, such as a logo or a training course, cannot be fully reduced to numbers. For these, replace a bare "to the client's satisfaction" with a structured standard:
- State the inputs, such as an approved brief or style guide.
- Limit the number of revision rounds included in the fee.
- Require the client to give reasons for rejection that refer to the brief.
An unqualified satisfaction clause gives the client wide discretion, and courts in some jurisdictions read it as requiring only honest dissatisfaction. A vendor should resist it. A client should recognize that it is also hard to apply consistently.
The review process
The review process is the sequence of steps from delivery to a final accept or reject decision. A complete clause answers six questions: who delivers, who reviews, how long review takes, what testing is allowed, what the client must say if it rejects, and what happens if the client says nothing.
Delivery notice
Review time should start from a defined event, not from whenever the client first notices the files. Require the vendor to give written notice that the deliverable is ready, with any materials the client needs to test it, such as access details or test scripts.
Review period
The SOW sets a fixed review period, commonly 5 to 15 business days. Shorter periods suit small deliverables. Large systems may need a longer period or a staged process, for example a functional test followed by a user acceptance test (UAT), where real users try the system on realistic tasks.
Specify business days or calendar days. Disputes often arise over this single word.
Rejection
If the deliverable fails, the client sends a written notice that lists each failed criterion and describes the failure well enough for the vendor to reproduce it. A rejection that says only "not acceptable" does not trigger the vendor's duty to fix. Many contracts also limit rejection to failures against the agreed criteria, so that new preferences cannot be added at review time.
Correction and re-review
After rejection the vendor gets a cure period to correct the defects and redeliver. The client then reviews again, usually within a shorter period, and only against the criteria that failed plus any regression the fix caused. Set a cap on the number of cycles, often two or three. After the cap, the contract should give the client a defined remedy, such as a price reduction, a refund of the milestone fee, or a right to terminate that SOW.
Deemed acceptance
A deemed acceptance clause says a deliverable counts as accepted if the client does not accept or reject it in writing by the deadline. This protects the vendor from a client that goes silent to delay payment. Clients should calendar every review deadline, because silence has legal effect. A client may negotiate a reminder notice first, so that deemed acceptance applies only after a second notice goes unanswered.
A related idea is acceptance by use. If the client puts the deliverable into production use, many contracts treat that as acceptance. Say so explicitly, and say whether limited testing in a live environment counts.
Partial acceptance and defect severity
Software projects rarely pass with zero defects. A severity scale lets the parties accept work that has minor issues:
| Severity | Meaning | Effect on acceptance |
|---|---|---|
| Critical | The system cannot be used for its main purpose | Blocks acceptance |
| Major | A key function fails and has no workaround | Blocks acceptance |
| Minor | Small defect with a workaround | Does not block acceptance; vendor fixes within an agreed time |
| Cosmetic | Appearance only | Does not block acceptance; fixed in a later release |
Define the levels in the SOW or an appendix, and say who decides the severity of a disputed defect.
Linking acceptance to payment
Acceptance is most useful when it controls money. Typical structures are:
- Milestone payment on acceptance. Each deliverable's fee is invoiced only after written or deemed acceptance.
- Holdback. The client pays most of the fee on acceptance but retains a percentage, such as 10 percent, until the end of a warranty period or final acceptance of the whole project.
- Staged acceptance. Payment is split across design acceptance, build acceptance and go-live acceptance.
State the invoice trigger precisely, for example "The Vendor may invoice a deliverable on the date of its acceptance, and the Client shall pay within 30 days of receiving a correct invoice." Do not link payment to the delivery date alone if the intent is to pay for working results.
Time-and-materials work has no deliverable to accept in the same way, since the client pays for hours. Even so, many such SOWs require client approval of timesheets or periodic status reports, which serves a similar control purpose.
Common errors
- Criteria that restate the title. "Deliver the mobile app" is a deliverable. It is not a criterion.
- Testing by an unnamed party. If nobody is named, each side assumes the other tests.
- No cure period. Rejection then becomes a dispute instead of a repair loop.
- Inconsistent documents. The MSA says review takes 30 days and the SOW says 10. The order-of-precedence clause decides which applies, but the conflict should not exist. For a SOW to change the MSA's default, it should say so expressly.
- Dependencies ignored. If the client must supply test data or access and does not, the vendor should be able to extend its dates and treat the review clock as paused. Record this in the assumptions and dependencies section.
- Acceptance of a part treated as acceptance of the whole. Say whether accepting one deliverable waives defects in related ones.
A drafting example
The following clause combines the main elements. Adapt the numbers to the project.
Acceptance. The Vendor shall notify the Client in writing when a Deliverable is ready for review. The Client has ten (10) business days from receipt of that notice to test the Deliverable against its Acceptance Criteria in the SOW and to either accept it in writing or reject it by written notice identifying each failed criterion. If the Client does not respond within that period, the Vendor shall send a reminder, and the Deliverable is deemed accepted if the Client does not respond within five (5) business days after the reminder. If the Client rejects a Deliverable, the Vendor shall correct the failures within ten (10) business days and redeliver it, and the Client shall re-test the failed criteria within five (5) business days. After two unsuccessful redeliveries, the Client may elect to terminate the affected SOW and receive a refund of fees paid for the rejected Deliverable.Exercise
A SOW says a reporting dashboard will be "user-friendly and fast," and the vendor invoices on delivery. The client refuses to pay, saying the dashboard is slow. Rewrite the acceptance criteria to be measurable, and describe two other provisions that would reduce the dispute.
Show answer
Example criteria: the dashboard's main view loads in under 4 seconds at the 95th percentile with 100 concurrent users on the staging environment, and 5 of 6 named client test users complete a defined set of three tasks without help. Provisions that reduce the dispute: (1) a review period with a written rejection procedure and cure period, so the client must list failures and the vendor gets a chance to fix them; (2) an invoice trigger tied to acceptance, with deemed acceptance after a reminder, so payment follows a defined decision instead of the delivery date.
Exercise
Why should a client calendar the review deadline when the contract contains a deemed acceptance clause?
Show answer
If the client does not accept or reject in writing before the deadline, the deliverable counts as accepted. The client then may lose the right to reject it and must pay, leaving only warranty remedies for defects.